JAPAN

(Updated 2017)

PREAMBLE

This report provides information on the status and development of nuclear power programmes in Japan, including factors related to the effective planning, decision making and implementation of the nuclear power programme that together lead to safe and economical operations of nuclear power plants.

The CNPP summarizes organizational and industrial aspects of nuclear power programmes and provides information about the relevant legislative, regulatory and international framework in Japan.

Japan has numerous nuclear power reactors in operation.

1. COUNTRY ENERGY OVERVIEW

1.1. Energy Information

1.1.1. Energy Policy

Without sufficient domestic sources of energy, Japan depends heavily on imports. That is, the country’s energy situation is highly subject to changes in international circumstances, as well as in domestic demand; this sometimes presents challenges to Japan’s energy security.

In order to handle these situations, Japan should develop an energy policy based on a long term, comprehensive, systematic perspective.

The Basic Act of Energy Policy was enforced in June 2002 for the purpose of ensuring steady implementation of energy policies. Based on the act, the First Strategic Energy Plan was drawn up in October 2003, followed by the second and third plans in March 2003 and June 2010, respectively. In the third plan, Japan aims to nearly double its self-sufficiency primary energy supply ratio to about 70% by 2030 by domestically developing fossil fuel.

However, after the third plan, the domestic and international circumstances surrounding energy changed drastically in the wake of the Great East Japan Earthquake and the accidents at the Tokyo Electric Power Company (TEPCO) Fukushima Daiichi Nuclear Power Station (hereinafter referred to as the “TEPCO Fukushima Daiichi accident”).

In Japan, the fourth “Strategic Energy Plan” was drawn up in April 2014, following the TEPCO Fukushima Daiichi accident. The plan shows the direction of the government policies to balance the achievement of the “3E+S (Energy Security, Economic Efficiency, Environmental Protection, and Safety)”. The following policies were set forth to construct a multilayered, diverse and flexible energy supply–demand structure: (1) achieving a strong, realistic and multi-layered supply structure by which each energy’s strengths are used and its weaknesses are compensated; (2) having the participation of various main bodies and availability of various options and creation of a more flexible and effective energy supply–demand structure; and (3) promoting and developing and introducing domestic energy, as well as improving the energy self-sufficiency ratio to minimize the impact of changes in circumstances overseas.

In the above government policy, nuclear energy is positioned as follows:

Nuclear power’s energy output per amount of fuel is overwhelmingly large and it can continue producing power for several years using a domestic fuel stockpile. Further, nuclear power is an important baseload power source. As a low carbon and quasi-domestic energy source, it contributes to the stability of the energy supply–demand structure, on the major premise that its safety is ensured, because of: (1) its superiority in terms of stability of energy supply and efficiency, (2) its low and stable operational costs, and (3) freedom from GHG emissions during operation.

Dependency on nuclear power generation will be lowered to the extent possible through energy savings and introduction of renewable energy, as well as improvements to the efficiency of thermal power generation.

1.1.2. Estimated Available Energy

Table 1 shows estimated energy reserves in Japan.

TABLE 1. ESTIMATED AVAILABLE ENERGY SOURCES

Estimated available energy sources
 Fossil fuels Nuclear  Renewables
Solid Liquid** Gas** Uranium*** Hydro Other
renewable
 Total amount in specific units* 8.05 74.21 3.05 23.36 45.79 0.61
Total amount in exajoule (EJ)

* Solid, Liquid: Million tons; Gas: Billion m3; Uranium: Thousand tons; Hydro, Renewable: GW

Data at the end of 2015.

** Conversion rate from Oil (kl) to Oil (t): 0.855; from LNG(t) to LNG (m3): 1,220.

*** Uranium excludes depleted uranium.

Sources: Uranium; Nuclear Regulation Authority.

Others: Agency for Natural Resources and Energy.

1.1.3. Energy Statistics

In the past, Japan imported a large amount of inexpensive crude oil. In fiscal year 1973, oil accounted for 75.5% of its total energy consumption. However, Japan then sustained surging oil prices amid the first oil crisis, which arose in 1973. With growing fears of oil supply cuts, Japan decided to reduce its reliance on oil as the primary energy source and instead introduce more nuclear power, natural gas and coal in order to stabilize the country’s energy supply.

As a result, Japan’s dependence on oil reduced from 75.5% in 1973 to 39.8% in fiscal 2010. Meanwhile, the country accelerated the diversification of energy sources to include coal (22.5%), natural gas (19.2%), and nuclear power (11.1%). However, with the shutdown of nuclear power plants after the Great East Japan Earthquake of 2011, consumption of fossil fuel as an alternative to nuclear power increased to a great extent. Although oil consumption has been decreasing in recent years, the role of oil in total energy consumption increased to 41.0% in fiscal 2015, with nuclear power representing 0.4%.

TABLE 2. ENERGY STATISTICS

(EJ) Average annual growth rate (%)
1980 1990 2000 2010 2015* 2000 to 2015*
Energy consumption**          
- Total 15.92 19.69 22.74 22.16 19.81 -0.92
- Solids*** 2.80 3.31 4.20 4.98 5.13 1.34
- Liquids*** 10.30 11.01 11.16 8.82 8.11 -2.11
- Gases 1.01 2.10 3.13 4.24 4.81 2.89
- Nuclear**** 0.78 1.88 2.86 2.46 0.08 -21.30
- Hydro**** 0.86 0.81 0.76 0.70 0.71 -0.42
- Other
renewables****
0.18 0.58 0.62 0.94 0.97 2.99
Energy production          
- Total 2.48 3.58 4.44 4.29 1.89 -5.54
- Solids*** 0.55 0.19 0.07 0.00 0.00 -100.00
- Liquids*** 0.02 0.02 0.03 0.03 0.02 -1.94
- Gases 0.10 0.09 0.11 0.15 0.11 0.26
- Nuclear**** 0.78 1.88 2.86 2.46 0.08 -21.30
- Hydro**** 0.86 0.81 0.76 0.70 0.71 -0.42
- Other
renewables****
0.18 0.58 0.62 0.94 0.97 2.99
Net import (Import - Export)          
- Total 13.41 16.27 18.46 17.69 17.76 -0.26
Stock change 0.03 -0.16 -0.16 0.17 0.16 -

* Latest available data (fiscal year).

** Energy consumption = Energy production+ Net import (Import - Export) ± Stock change.

*** Solid fuels include coal, anthracite and lignite. Liquid fuels include crude oil, kerosene, gasoline, light oil and heavy oil, as well as LNG and refinery gas.

**** Conversion from electricity production to primary energy production is based on net efficiency of

thermal power generation by general electricity utilities.

Source: “General Energy Statistics,” Agency for Natural Resources and Energy.

1.2. The Electricity System

1.2.1. Electricity System and Decision Making Process

The Electricity and Gas Industry Committee, comprising non-governmental professionals and experts, provides advice and recommendations to the Ministry of Economy, Trade and Industry (METI) on a regular basis regarding the basic national policies to achieve stable supplies of power, promote demand-oriented energy-saving measures, promote load leveling and further develop electric power. Based on this advice, METI and related ministries and agencies confer regularly with individual power companies to review up to date demand and supply performance and evaluate the power supply programme for the future.

1.2.2. Structure of Electric Power Sector

The Japanese electricity market was divided into nine geographical zones with an electric power company in each zone. These are private enterprises that specialize only in electric utility operations and are the main power suppliers in each zone, though the electricity market was partially liberalized. Apart from these companies, there is also the Okinawa Electric Power Company. This is a smaller electric utility company operating in Okinawa Prefecture, which comprises many small islands. These power companies operate their own facilities from power generation to transmission and distribution as integrated business operations.

The Electric Power Development Company maintains thermal and hydroelectric power stations, while the Japan Atomic Power Company oversees nuclear power stations. The two are private enterprises that produce electric power and act as wholesalers to the nine electric power companies. However, in relation to Japan’s total installed capacity, their installed capacity is relatively small.

It was decided by the Cabinet to carry out a bold reform under the “Policy on Electricity System Reform” (April 2013) to expand cross-regional system operation and full retail competition, and to ensure the neutrality of the power transmission and distribution sectors through legal unbundling.

Under the proposed reform, some steps have already taken place. Firstly, the Organization for Cross-regional Coordination of Transmission Operators (OCCTO) was established in April 2015. Then, in September 2015, the Electricity and Gas Market Surveillance Commission (EGC) was established under the Ministry of Economy, Trade and Industry, in order to strengthen monitoring of the electricity, gas and heat power trading market. After setting up those two new institutions, the electricity retail market was fully liberalized as of April 2016. The legal unbundling has not been done except for TEPCO (Tokyo Electric Power Company), but it is planned to take place by April 2020.

1.2.3. Main Indicators

TABLE 3. INSTALLED CAPACITY, ELECTRICITY PRODUCTION AND CONSUMPTION

Average annual growth rate (%)
1980 1990 2000 2010 2015* 2000 to 2015*
Capacity of electrical plants (GWe) G            
- Thermal 80.77 104.09 138.16 135.07 143.04 0.23
- Nuclear 15.51 31.48 45.08 48.96 44.26 0.13
- Hydro 28.54 36.32 44.85 43.85 45.79 0.14
- Wind 0.00 0.09 0.05
- Geothermal 0.13 0.24 0.50 0.50 0.47 -0.41
- Other renewable 0.01 0.09
- Total 124.95 172.12 228.60 228.48 231.48 0.08
Electricity production (TWh) G
- Thermal 317.7 446.6 526.9 553.3 675.7 1.7
- Nuclear 82.0 201.4 321.3 288.2 0.0 -100.0
- Hydro 84.5 88.1 89.3 74.2 74.9 -1.2
- Wind 0.0 0.1 0.1
- Geothermal 0.9 1.5 3.1 2.5 2.4 -1.7
- Other renewable 0.0 0.1
- Total** 485.5 737.6 940.7 918.2 790.6 -1.4
Total electricity consumption (TWh)*** 575.1 862.0 1 080.0 1 134.8 1 018.3 -0.4

* Latest available data (fiscal year).

** Electricity transmission losses are not deducted.

*** Total electricity consumption is based on the “General Energy Statistics”, which includes electricity own-use by autoproducers and electricity transmission losses.

Source: Agency for Natural Resources and Energy.

TABLE 4. ENERGY RELATED RATIOS

1980 1990 2000 2010 2015*
Energy consumption per capita (GJ/capita)** 136 160 180 175 155
Electricity consumption per capita (kWh/capita) 4 915 7 000 8 552 8 941 7 951
Electricity production/Energy production (%) 83.4 87.7 87.9 95.1 188.2
Nuclear/Total electricity (%)*** 16.9 27.3 34.2 31.4 0.0
Ratio of external dependency (%)**** 84.4 81.8 80.5 80.6 90.5

* Latest available data (fiscal year).

** Energy consumption = Energy production + Net import (Import - Export) ± Stock change.

*** Nuclear/Total electricity is based on the figures of Electricity Production in Table 3.

**** Ratio of external dependency = (Energy consumption - Energy production) /Energy consumption.

Sources: “General Energy Statistics,” Agency for Natural Resources and Energy.

“Basic Resident Register,” Ministry of Internal Affairs and Communications.

2. NUCLEAR POWER SITUATION

2.1. Historical Development and Current Organizational Structure

2.1.1. Overview

Enactment of the “Atomic Energy Basic Law (1955)” promoted atomic energy development and utilization for peaceful objectives in compliance with the three basic principles of Democratic Management, Voluntary Action, and Open Information. Inauguration of the Atomic Energy Commission (1956) established an advisory board for the Prime Minister on matters regarding the promotion of atomic energy development and utilization.

“Long-term programme for Research, Development, and Utilization of Nuclear Energy” (Long-term Programme) was formulated in 1956. The plan was revised and updated every five years between 1956 and 2000.

The Ministry of International Trade and Industry (formerly METI) was reorganized in 1966 to accommodate its increasing workload. This change provided additional rules and regulations for introducing commercial light water reactors in Japan after 1966.

In 1974, three basic laws for promoting electric power development were enacted, namely, the “Law for the Adjustment of Areas Adjacent to Power-Generating Facilities,” the “Electric Power Development Promotion Tax Law,” and the “Special Account Law for Electric Power Promotion.” These laws also advanced the appropriate siting of nuclear power stations.

In 1978, the Nuclear Safety Commission was formed as a separate entity from the Atomic Energy Commission. Safety assurance measures were enhanced in 1980 to reflect lessons learned from the TMI-2 Accident (1979) and, later, the Chernobyl No. 4 Accident in 1986.

The overall appraisal of the “Vision of Nuclear Power” in 1986 provided long range prospects for energy availability and electric power requirements through 2030, and a programme for enhancing safety called “Safety 21,” which further reinforced safety assurance measures. In 1990, Japan revised its supply targets to include alternative energy sources to mitigate its growing demand for oil and its contribution to the greenhouse effect.

The Japanese government carried out administrative reforms in January 2001. In that year, the Nuclear and Industrial Safety Agency (NISA) was formed as a special institution of the Agency of Natural Resources and Energy of the Ministry of Economy, Trade and Industry (or METI, which was renamed from the Ministry of International Trade and Industry, or MITI), to have jurisdiction over matters of nuclear and industrial safety. In addition, the Atomic Energy Commission and Nuclear Safety Commission (NSC) of the Cabinet Office gave high level independent and appropriate directions to other ministries and agencies.

The earthquake that occurred off the Pacific coast of the Tohoku region on 11 March 2011 and subsequent tsunami damaged the TEPCO Fukushima Daiichi Nuclear Power Station and Fukushima Daini Nuclear Power Station. In particular, at TEPCO’s Fukushima Daiichi Nuclear Power Station, an extremely serious accident measured at Level 7 on the International Nuclear and Radiological Event Scale (INES) occurred. A report by the National Diet of Japan Fukushima Nuclear Accident Independent Investigation Commission noted the following:

“The regulators did not monitor or supervise nuclear safety. The lack of expertise resulted in ‘regulatory capture,’ and the postponement of the implementation of relevant regulations. They avoided their direct responsibilities by letting operators apply regulations on a voluntary basis. Their independence from the political arena, the ministries promoting nuclear energy, and the operators was a mockery. They were incapable, and lacked the expertise and the commitment to assure the safety of nuclear power.”

Based on the lessons learned from the accident, the Nuclear Regulation Authority (NRA) was established as an external organ of the Ministry of the Environment by separating the functions of promotion and regulation of nuclear energy, with the aim of avoiding potential problems when a single government organization acted both as a regulatory authority and one promoting wider use of nuclear energy. It was also established as an authority under Article 3(1) so that the Chairman and the Commissioners can exercise an independent, neutral and fair role, based on their own expertise. Additionally, in order to eliminate the harmful effects of a vertically divided administration, the NRA shall integrally govern regulations on nuclear energy, nuclear security, safeguards based on international commitments, radiation monitoring, and regulations on the use of radioisotopes, which previously had been governed by other administrative organs. On 1 March 2014, the Incorporated Administrative Agency, Japan Nuclear Energy Safety Organization and all of its activities were integrated into the NRA.

2.1.2. Current Organizational Structure

The Ministry of Education, Culture, Sports, Science and Technology (MEXT) was created through a merger of the former Ministry of Education, Science, Sports and Culture and the Science and Technology Agency (STA). MEXT is responsible for administering nuclear energy for science and technology. Its key roles are nuclear research and development (including nuclear fuel cycle, FBR and accelerators), human resources in the field of nuclear energy and nuclear liability. It is also responsible for supervising the Japan Atomic Energy Agency.

The Ministry of Economy, Trade and Industry (METI) is in charge of those areas in which it had been involved previously as the Ministry of International Trade and Industry (MITI), or took over from STA, related to nuclear fuel cycle activities (refining, enrichment, fabrication, reprocessing and waste disposal). Nuclear power related issues are the responsibility of the Agency of Natural Resources and Energy.

The Ministry of Foreign Affairs (MOFA) is responsible for international aspects of nuclear energy utilization, including implementation of related international treaties and conventions.

FIG. 1. Japan’s organization chart.

Legend of Fig. 1:

MOE: Ministry of Environment.

NRA: Nuclear Regulation Authority.

METI: Ministry of Economy, Trade and Industry.

JAEC: Japan Atomic Energy Commission.

ANRE: Agency of Natural Resources and Energy.

MEXT: Ministry of Education, Culture, Sports, Science and Technology.

MOFA: Ministry of Foreign Affairs.

JAEA: Japan Atomic Energy Agency.

2.2. Nuclear Power Plants: Overview

2.2.1. Status and Performance of Nuclear Power Plants

Table 5 and Figure 2 provide lists and locations in Japan of nuclear power plants in operation, under construction or out of service. As of May 2016, the total capacity of nuclear power generation was 45 775 MWe.

Due to the TEPCO Fukushima Daiichi accident, it was decided to decommission Units 1 to 4 on 19 April 2012 and Units 5 and 6 on 31 January 2014.

TABLE 5. STATUS AND PERFORMANCE OF NUCLEAR POWER PLANTS

Reactor Unit Type Net
Capacity
[MW(e)]
Status Operator Reactor
Supplier
Construction
Date
First
Criticality
Date
First Grid
Date
Commercial
Date
Shutdown
Date
UCF
for
2016
FUKUSHIMA-DAINI-1 BWR 1067 Operational TEPCO TOSHIBA 1976-03-16 1981-06-17 1981-07-31 1982-04-20 0.0
FUKUSHIMA-DAINI-2 BWR 1067 Operational TEPCO HITACHI 1979-05-25 1983-04-26 1983-06-23 1984-02-03 0.0
FUKUSHIMA-DAINI-3 BWR 1067 Operational TEPCO TOSHIBA 1981-03-23 1984-10-18 1984-12-14 1985-06-21 0.0
FUKUSHIMA-DAINI-4 BWR 1067 Operational TEPCO HITACHI 1981-05-28 1986-10-24 1986-12-17 1987-08-25 0.0
GENKAI-2 PWR 529 Operational KYUSHU MHI 1977-02-01 1980-05-21 1980-06-03 1981-03-30 0.0
GENKAI-3 PWR 1127 Operational KYUSHU MHI 1988-06-01 1993-05-28 1993-06-15 1994-03-18 0.0
GENKAI-4 PWR 1127 Operational KYUSHU MHI 1992-07-15 1996-10-23 1996-11-12 1997-07-25 0.0
HAMAOKA-3 BWR 1056 Operational CHUBU TOSHIBA 1983-04-18 1986-11-21 1987-01-20 1987-08-28 0.0
HAMAOKA-4 BWR 1092 Operational CHUBU TOSHIBA 1989-10-13 1992-12-02 1993-01-27 1993-09-03 0.0
HAMAOKA-5 BWR 1325 Operational CHUBU TOSHIBA 2000-07-12 2004-03-23 2004-04-30 2005-01-18 0.0
HIGASHI DORI-1 (TOHOKU) BWR 1067 Operational TOHOKU TOSHIBA 2000-11-07 2005-01-24 2005-03-09 2005-12-08 0.0
IKATA-2 PWR 538 Operational SHIKOKU MHI 1978-08-01 1981-07-31 1981-08-19 1982-03-19 0.0
IKATA-3 PWR 846 Operational SHIKOKU MHI 1990-10-01 1994-02-23 1994-03-29 1994-12-15 37.0
KASHIWAZAKI KARIWA-1 BWR 1067 Operational TEPCO TOSHIBA 1980-06-05 1984-12-12 1985-02-13 1985-09-18 0.0
KASHIWAZAKI KARIWA-2 BWR 1067 Operational TEPCO TOSHIBA 1985-11-18 1989-11-30 1990-02-08 1990-09-28 0.0
KASHIWAZAKI KARIWA-3 BWR 1067 Operational TEPCO TOSHIBA 1989-03-07 1992-10-19 1992-12-08 1993-08-11 0.0
KASHIWAZAKI KARIWA-4 BWR 1067 Operational TEPCO HITACHI 1990-03-05 1993-11-01 1993-12-21 1994-08-11 0.0
KASHIWAZAKI KARIWA-5 BWR 1067 Operational TEPCO HITACHI 1985-06-20 1989-07-20 1989-09-12 1990-04-10 0.0
KASHIWAZAKI KARIWA-6 BWR 1315 Operational TEPCO TOSHIBA 1992-11-03 1995-12-18 1996-01-29 1996-11-07 0.0
KASHIWAZAKI KARIWA-7 BWR 1315 Operational TEPCO HITACHI 1993-07-01 1996-11-01 1996-12-17 1997-07-02 0.0
MIHAMA-3 PWR 780 Operational KEPCO MHI 1972-08-07 1976-01-28 1976-02-19 1976-12-01 0.0
MONJU FBR 246 Operational JAEA T/H/F/M 1986-05-10 1994-04-05 1995-08-29 0.0
OHI-1 PWR 1120 Operational KEPCO WH 1972-10-26 1977-12-02 1977-12-23 1979-03-27 0.0
OHI-2 PWR 1120 Operational KEPCO WH 1972-12-08 1978-09-14 1978-10-11 1979-12-05 0.0
OHI-3 PWR 1127 Operational KEPCO MHI 1987-10-03 1991-05-17 1991-06-07 1991-12-18 0.0
OHI-4 PWR 1127 Operational KEPCO MHI 1988-06-13 1992-05-28 1992-06-19 1993-02-02 0.0
ONAGAWA-1 BWR 498 Operational TOHOKU TOSHIBA 1980-07-08 1983-10-18 1983-11-18 1984-06-01 0.0
ONAGAWA-2 BWR 796 Operational TOHOKU TOSHIBA 1991-04-12 1994-11-02 1994-12-23 1995-07-28 0.0
ONAGAWA-3 BWR 796 Operational TOHOKU TOSHIBA 1998-01-23 2001-04-26 2001-05-30 2002-01-30 0.0
SENDAI-1 PWR 846 Operational KYUSHU MHI 1979-12-15 1983-08-25 1983-09-16 1984-07-04 81.2
SENDAI-2 PWR 846 Operational KYUSHU MHI 1981-10-12 1985-03-18 1985-04-05 1985-11-28 95.6
SHIKA-1 BWR 505 Operational HOKURIKU HITACHI 1989-07-01 1992-11-20 1993-01-12 1993-07-30 0.0
SHIKA-2 BWR 1108 Operational HOKURIKU HITACHI 2001-08-20 2005-05-26 2005-07-04 2006-03-15 0.0
SHIMANE-2 BWR 789 Operational CHUGOKU HITACHI 1985-02-02 1988-05-25 1988-07-11 1989-02-10 0.0
TAKAHAMA-1 PWR 780 Operational KEPCO WH/MHI 1970-04-25 1974-03-14 1974-03-27 1974-11-14 0.0
TAKAHAMA-2 PWR 780 Operational KEPCO MHI 1971-03-09 1974-12-20 1975-01-17 1975-11-14 0.0
TAKAHAMA-3 PWR 830 Operational KEPCO MHI 1980-12-12 1984-04-17 1984-05-09 1985-01-17 84.8
TAKAHAMA-4 PWR 830 Operational KEPCO MHI 1981-03-19 1984-10-11 1984-11-01 1985-06-05 81.2
TOKAI-2 BWR 1060 Operational JAPCO GE 1973-10-03 1978-01-18 1978-03-13 1978-11-28 0.0
TOMARI-1 PWR 550 Operational HEPCO MHI 1985-04-18 1988-11-16 1988-12-06 1989-06-22 0.0
TOMARI-2 PWR 550 Operational HEPCO MHI 1985-06-13 1990-07-25 1990-08-27 1991-04-12 0.0
TOMARI-3 PWR 866 Operational HEPCO MHI 2004-11-18 2009-03-03 2009-03-20 2009-12-22 0.0
TSURUGA-2 PWR 1108 Operational JAPCO MHI 1982-11-06 1986-05-28 1986-06-19 1987-02-17 0.0
OHMA BWR 1325 Under Construction EPDC H/G 2010-05-07
SHIMANE-3 BWR 1325 Under Construction CHUGOKU HITACHI 2007-10-12
FUGEN ATR HWLWR 148 Permanent Shutdown JAEA HITACHI 1972-05-10 1978-03-20 1978-07-29 1979-03-20 2003-03-29
FUKUSHIMA-DAIICHI-1 BWR 439 Permanent Shutdown TEPCO GE/GETSC 1967-07-25 1970-10-10 1970-11-17 1971-03-26 2011-05-19
FUKUSHIMA-DAIICHI-2 BWR 760 Permanent Shutdown TEPCO GE/T 1969-06-09 1973-05-10 1973-12-24 1974-07-18 2011-05-19
FUKUSHIMA-DAIICHI-3 BWR 760 Permanent Shutdown TEPCO TOSHIBA 1970-12-28 1974-09-06 1974-10-26 1976-03-27 2011-05-19
FUKUSHIMA-DAIICHI-4 BWR 760 Permanent Shutdown TEPCO HITACHI 1973-02-12 1978-01-28 1978-02-24 1978-10-12 2011-05-19
FUKUSHIMA-DAIICHI-5 BWR 760 Permanent Shutdown TEPCO TOSHIBA 1972-05-22 1977-08-26 1977-09-22 1978-04-18 2013-12-17
FUKUSHIMA-DAIICHI-6 BWR 1067 Permanent Shutdown TEPCO GE/T 1973-10-26 1979-03-09 1979-05-04 1979-10-24 2013-12-17
GENKAI-1 PWR 529 Permanent Shutdown KYUSHU MHI 1971-09-15 1975-01-28 1975-02-14 1975-10-15 2015-04-27
HAMAOKA-1 BWR 515 Permanent Shutdown CHUBU TOSHIBA 1971-06-10 1974-06-20 1974-08-13 1976-03-17 2009-01-30
HAMAOKA-2 BWR 806 Permanent Shutdown CHUBU TOSHIBA 1974-06-14 1978-03-28 1978-05-04 1978-11-29 2009-01-30
IKATA-1 PWR 538 Permanent Shutdown SHIKOKU MHI 1973-09-01 1977-01-29 1977-02-17 1977-09-30 2016-05-10 0.0
JPDR BWR 12 Permanent Shutdown JAEA GE 1960-12-01 1963-08-22 1963-10-26 1965-03-15 1976-03-18
MIHAMA-1 PWR 320 Permanent Shutdown KEPCO WH 1967-02-01 1970-07-29 1970-08-08 1970-11-28 2015-04-27
MIHAMA-2 PWR 470 Permanent Shutdown KEPCO MHI 1968-05-29 1972-04-10 1972-04-21 1972-07-25 2015-04-27
SHIMANE-1 BWR 439 Permanent Shutdown CHUGOKU HITACHI 1970-07-02 1973-06-01 1973-12-02 1974-03-29 2015-04-30
TOKAI-1 GCR 137 Permanent Shutdown JAPCO GEC 1961-03-01 1965-05-04 1965-11-10 1966-07-25 1998-03-31
TSURUGA-1 BWR 340 Permanent Shutdown JAPCO GE 1966-11-24 1969-10-03 1969-11-16 1970-03-14 2015-04-27
Data source: IAEA - Power Reactor Information System (PRIS).
Note: Table 7 is completely generated from PRIS data to reflect the latest available information and may be more up to date than the text of the report.

FIG. 2. Nuclear facilities in Japan.

2.2.2. Plant Upgrading, Plant Life Management and Licence Renewals

The approval system for ‘the extension of an operational period’ includes a new regulatory regime that also places a 40 year limit on the operation of power reactors, although operators may apply for a one time life extension of no more than 20 years for a reactor with 40 operational years, provided that regulatory approval is obtained before the normal 40 year expiration date.

2.2.3. Permanent Shutdown and Decommissioning Process

Fifteen reactors in total have been shut down permanently and are to be decommissioned in Japan, including Fukushima Daiichi NPS Unit 1 to 6.

Decommissioning work has already begun on three reactors (Tokai NPS, Hamaoka NPS Units 1 and 2).

Utilities have submitted their decommissioning plans for the following five reactors to the NRA, and NRA approved the decommissioning plans in April 2017.

Mihama NPS Units 1 and 2;

  • Shimane NPS Unit 1;

  • Genkai NPS Unit 1;

  • Tsuruga NPS Unit 1.

A decision was made in May 2016 to decommission Ikata NPS Unit 1. Its decommissioning plan was submitted to the NRA in December 2016 and is under review as of May 2017.

2.3. Future Development of Nuclear Power Sector

2.3.1. Nuclear Power Development Strategy

On the premise that safety comes first and that every possible effort is made to resolve the public’s concerns, a judgement as to whether nuclear power plants meet the new regulatory requirements will be left to the NRA. If the NRA confirms the nuclear power plants conform to the new regulatory requirements, GOJ will follow NRA’s judgement and proceed to restart the nuclear power plants. In such case, GOJ will make its best efforts to obtain the understanding and cooperation of the host municipalities and other relevant parties. At present, GOJ is not considering adding power generation capabilities or replacing existing facilities.

Dependency on nuclear power generation will be lowered to the extent possible by saving energy and introducing renewable energy, as well as improving the efficiency of thermal power generation.

GOJ released the Long-term Energy Supply and Demand Outlook on 16 July 2015. In the plan, the Government set a target of reducing its dependency on nuclear power to 20–22% by 2030.

2.3.2. Project Management

In Japan, private electric power suppliers manage construction of nuclear energy plants. Those electric power suppliers are the owners and operators of nuclear energy plants. Electric power suppliers manage entire construction projects, with construction work and manufacturing of equipment and facilities done by the companies that constructed the nuclear energy plants.

2.3.3. Project Funding

The financial resources for constructing nuclear power plants are procured by electric power suppliers, which are the implementing entities of construction projects. The methods of procuring funds are comparatively flexible, with sources including banking institutions, government financial institutions, stock markets and internal reserves. The financial plan for constructing a nuclear energy plant requires an examination of the financial status of the applicant in procedures for obtaining permission to install reactors. Therefore, a situation in which a construction project for a nuclear power plant becomes financially stalled can be avoided.

2.3.4. Electric Grid Development

Most electric power suppliers that generate nuclear power in Japan have their own electric distribution networks. Those distribution networks cover the whole country. Under the power generation and distribution management system of individual electric power suppliers, distribution networks ensure stable distribution by appropriately adjusting the amount of power generated in accordance with momentarily changing demand.

Electricity system reforms ensure the neutrality of power transmission and distribution sectors through legal unbundling.

2.3.5. Sites

As a technical requirement, electric power suppliers should choose locations for nuclear power plants that are less vulnerable to natural disasters, with stable ground conditions, and that are sufficiently remote from resident areas. In the procedures for obtaining permission to install reactors, site conditions are subject to safety reviews.

2.3.6. Public Awareness

GOJ will enhance public relations activities based on scientific evidence and objective facts with regard to such matters as risks related to nuclear energy and impacts of accidents, regulatory requirements, safety measures to be taken after accidents, disaster management measures following severe accidents (assuming one has taken place), problems related to spent fuels, economic efficiency of nuclear energy, and international trends. Carefully planned public hearings and public relations activities will be enhanced not only in regions with nuclear power plants but also in electricity consuming regions that have until now received the benefits of power supply, through sincere dialogues with various stakeholders and reinforcing sharing information. In addition, GOJ will enhance education on nuclear power to improve the public’s understanding of nuclear power across generations.

2.4. Organizations Involved in Construction of NPPs

There are three reactor manufacturers in Japan. Toshiba Corporation, which took over Westinghouse Electric Company in 2006, can offer both PWRs and BWRs. Hitachi, Ltd., which has a strategic global alliance with GE, and Mitsubishi Heavy Industries, Inc. can offer BWRs and PWRs, respectively.

Many companies are capable of supplying equipment and services to Japan’s nuclear power industry. These range from suppliers of major items of equipment and machinery to those supplying conventional equipment or offering engineering services. They also include firms related to the nuclear fuel cycle and nuclear fuel recycling.

2.5. Organizations Involved in Operation of NPPs

Nine electric power companies operate commercial light water reactors, and another company is a producer and wholesaler of electricity generated from nuclear power in Japan.

Regarding the training of nuclear power plant operators in Japan, both BWR and PWR groups have their own training centres. These are financed, built and used jointly by member companies in each group, comprising electric power companies and contracted engineering firms. In addition, each electric power company has its own training facility. Engineering qualification tests for operator certification are conducted at training centres operated jointly by member companies.

Representative suppliers of Japan’s maintenance services are Toshiba, Hitachi and Mitsubishi. The electric power companies make contracts with these maintenance service companies. Contractors assume responsibility for repair and maintenance services for their nuclear power plants.

2.6. Organizations Involved in Decommissioning of NPPs

It is Japan’s fundamental policy to dismantle and remove decommissioned nuclear power generation facilities that have completed their service lives, while ensuring the complete safety of that process. Based on this fundamental policy, the standard procedure (standard work schedule) is one of safe storage plus disassembly/removal. It is appropriate to choose a safe storage period of ten to fifteen years and a disassembly/removal period of five to ten years.

The estimated cost of decommissioning a reactor in Japan (referring to precedents in other countries) is several tens of billion JPY.

2.7. Fuel Cycle Including Waste Management

Fuel cycle activities in Japan comprise enrichment, conversion, fuel fabrication, zircaloy cladding, reprocessing and radioactive waste activities. Figure 3 shows the enterprises involved.

FIG. 3. Nuclear fuel cycle diagram.

2.8. Research and Development

2.8.1. R&D Organizations

Government responsibilities for R&D are shared between the Ministry of Education, Culture, Sports, Science and Technology (MEXT) and the Ministry of Economy, Trade and Industry (METI). MEXT is responsible for planning and administering nuclear energy for science and technology. MEXT plays a key role in many areas of nuclear research and development, including the nuclear fuel cycle, FBR and accelerators. MEXT supervises the work of the Japan Atomic Energy Agency (JAEA), which was established in 2005. The Agency of Natural Resources and Energy (ANRE) carries out various activities, which include studies on improving reactor designs of Light Water Reactors (LWRs), approving design modifications proposed by utilities and decommissioning.

2.8.2. Development of Advanced Nuclear Power Technologies

In addition to LWRs for power production, Japan is actively developing other types of reactor, such as HTGRs and FBRs. Toshiba Corporation and the Tokyo Institute of Technology are developing a natural circulation, simplified LSBWR with passive safety systems and a long operating cycle: 100–300 MWe power capacity and 15 year core life.

HTGR is expected to be utilized in various industries including hydrogen production. Japan’s principal HTGR development programme is R&D using the JAEA (former JAERI) High-temperature Engineering Test Reactor (HTTR) at Oarai, Ibaraki Prefecture. The HTTR is a helium gas cooled reactor with 30 MWth capacity. This reactor was used to establish and upgrade technologies for advanced HTGR, and to demonstrate the effectiveness of selected high temperature heat utilization systems. The initial criticality of the HTTR was achieved in November 1998. The HTTR achieved full power operation of 30 MWth and a gas temperature of 950°C at the reactor outlet in April 2004. Fifty day long term high temperature operation at 950°C to demonstrate that HTTR can supply high temperature heat for planned heat utilization systems in 2010 followed. Loss of focused cooling test was accomplished at power of 9 MWth in 2010 under the framework of the international joint research OECD/NEA LOFC project. The HTTR has not operated since the Great East Japan Earthquake in March 2011 because all nuclear reactors in Japan were required to meet the new regulation standard. JAEA submitted the application for the HTTR to the NRA to confirm the adjustability to the new regulation standard on 26 November 2014. The review by the NRA is in progress. JAEA is also working on R&D for a hydrogen production system using an iodine–Sulphur (IS) process. In October 2017, JAEA achieved 31 hours of hydrogen production by using the continuous hydrogen production test facility made of industrial material. HTGR development was promoted in the “Strategic Energy Plan”, which was adopted by the cabinet in 2014. On the basis of the Strategic Energy Plan, MEXT established the task force in the Nuclear Science Committee to develop future R&D plans for HTRs in May 2014, and this task force developed an interim report in September 2014. On the basis of the recommendation of the task force report, an industrial–academic–government forum for HTGR in Japan was established aiming to discuss future HTGR plans. Four meetings have been held so far (April 2015, September 2015, April 2016 and June 2016), and discussions are underway.

JAEA (former JNC) is conducting research and development (R&D) on FBRs and nuclear fuel reprocessing technology to establish an economical nuclear fuel cycle. The experimental fast reactor (Joyo) was operated from 1982 to 2000 with the MK-II core (100 MWth). Thereafter, the core and the cooling system were modified and attained initial criticality as the MK-III core (140 MWth) in July 2003. Irradiation tests for the self-actuated shutdown system, MA-MOX fuel and ODS ferritic steel were conducted with the MK-III core. In 2007, an irradiation rig (MARICO-2) bent on an in-vessel storage rack. Restoration work, including retrieving MARICO-2 and exchanging the upper core structure, finished in 2015. JAEA submitted an application for Joyo restart to comply with the new regulatory requirements on 30 March 2017. The prototype Monju Liquid Metal-cooled Fast Breeder Reactor (LMFBR) with a capacity of 280 MW reached initial criticality in April 1994, and was connected to the grid in August 1995. Reactor operation was interrupted in December 1995 due to a sodium leak in the non-radioactive secondary cooling system. After carrying out the investigation into the cause and the comprehensive safety review for two years and the necessary licensing procedure, JAEA completed a series of modifications in order to reinforce countermeasures against potential sodium leak accidents. Monju was restarted in May 2010 and the core confirmation test was conducted until July 2010. However, an in-vessel transfer machine (IVTM) dropped down when hung up by the gripper of the auxiliary handling machine succeeding to the refueling in August 2010. JAEA completed the withdrawal and restoration of the IVTM by November 2011. But after the TEPCO Fukushima Daiichi accident in 2011, an order on measures for plant safety was issued by the NRA to suspend preparations for the pre-operational tests in the system startup tests due to inadequate maintenance management in May 2013 and JAEA has continued to address the order. JAEA totally revised the plant maintenance management system and the quality assurance system, and their results were reported to NRA in August 2016. After that, JAEA implemented the inspection of components and systems of Monju on the basis of the new plant maintenance programme. In parallel with the approach for restart of Monju by JAEA, the research plan of Monju was adopted by MEXT in September 2013. The research items for Monju are summarized as follows: (1) compilation of outcomes of fast reactor (FR) development, (2) reduction of the amount and toxic level of radioactive waste, and (3) safety enhancement of FR. Given this situation, the Inter-Ministerial Council for Nuclear Power was held in September 2016, resulting in the decision that “A fundamental review of Monju taking decommissioning into consideration is conducted”. Following that decision, a Council on Fast Reactor Development was held from October through December 2016 to discuss the development policy on fast reactors in Japan. In consideration of the discussion of the Council on Fast Reactor Development, the Inter-Ministerial Council for Nuclear Power concluded in December 2016 as follows:

Based on the “Basic Energy Plan in Japan”, the nuclear fuel cycle will be promoted, along with work on R&D toward commercialization of fast reactors.

  • However, Monju will not be restarted as a nuclear reactor, and will make the transition to decommissioning in the future.

Knowledge and experience obtained from the design, construction and R&D on Monju are being assembled and organized for the future fast reactors. The Monju decommissioning plan is also being developed to establish the decommissioning technology for fast reactors such as sodium handling techniques. Through these R&D activities, the Monju site will be utilized as a core entity of the nuclear research and human resource development.

With regard to the development of future fast reactors in Japan, a practical level strategic working group was set up to draw up a “Strategic road map on sodium-cooled fast reactors”. The strategic road map specifies the development work in the next 10 years in Japan. Drawing up the road map is targeted to be completed by 2018. In addition to these development activities, the “Feasibility Study on Commercialized Fast Breeder Reactor Cycle Systems” (FS) undertaken by JAEA with the cooperation of electric utilities and other interested parties was carried out from 1999 to 2005 with the objective of presenting an optimal commercialization vision for FBR technologies and a research and development programme toward that end. Based on the conclusion of the FS and check and review by the government, the “Fast Reactor Cycle Technology Development” (FaCT) programme was launched as an advanced stage toward commercialization of FR cycle technology in 2006. But FaCT was suspended due to the TEPCO Fukushima Daiichi accident which occurred on 11 March 2011. In accordance with “Strategic Energy Plan”, R&D for the reduction of waste volume and radiotoxicity and safety enhancement optimizing the use of international cooperation are being conducted by JAEA.

2.8.3. International Cooperation and Initiatives

Implementation of Nuclear Safety and Research and Development through International Cooperation is as following:

Activities with IAEA: Japan has contributed to developing and revising IAEA nuclear safety standards by dispatching experts to CSS, NUSSC, WASSC, RASSC, TRANSSC and EPReSC. Regarding the “Convention on Nuclear Safety” and “Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management,” Japan dispatched experts from the draft planning stage. Japan has also participated in review activities after the submission of national reports, promotion of peaceful uses for nuclear energy (safety related cooperation, technical aid to developing countries and R&D), and provision of safeguards to ensure that nuclear activities are not converted for military applications. Japan participates positively in the International Nuclear Safety Advisory group (INSAG), Assessment of Safety Significant Event Team (ASSET), Operational Safety Review Team (OSART), Integrated Regulatory Review Service (IRRS), Site and External Events Design (SEED), International Physical Protection Advisory Service (IPPAS) and special studies to evaluate the safety of reactors in the former USSR. Japan has annually made an extrabudgetary contribution to the IAEA for: (1) the Expanded Programme of Public Understanding of Nuclear Energy (EPPUNE), (2) the development of national infrastructure for nuclear power plants, (3) the decommissioning of Fukushima Daiichi Nuclear Power Station, and (4) nuclear knowledge management.

  • Activities with OECD/NEA: The purpose is to provide useful information to member countries through technological studies and mutual cooperation on common problems in using nuclear energy in advanced countries. Japan participates actively in the Committee on Nuclear Regulatory Activities (CNRA), Committee on the Safety of Nuclear Installations (CSNI), Radioactive Waste Management Committee (RWMC), Nuclear Science Committee (NSC), Committee on Radiation Protection and Public Health (CRPPH), Nuclear Law Committee (NLC), Data Bank (DB), and Committee for Technical and Economic Studies on Nuclear Energy Development and the Fuel Cycle (NDC).

  • Japan has participated in multilateral cooperation frameworks and projects such as the Generation IV International Forum (GIF), the Multinational Design Evaluation Programme (MDEP) and the International Framework for Nuclear Energy Cooperation (IFNEC).

  • Japan has hosted the Forum for Nuclear Cooperation in Asia (FNCA).

2.9. Human Resources Development

GOJ will also take an integrated approach to support development of human resources, institutional infrastructure, and other items for countries planning to introduce nuclear power through cooperation with international organizations such as the IAEA.

2.10. Stakeholder Involvement

GOJ will be more actively involved in communications, referencing examples in other countries, and will take the necessary measures to enhance the sharing of information within regions through careful dialogues with various stakeholders, including local residents.

2.11. Emergency Preparedness

In the case of a nuclear emergency, appropriate measures have to be taken promptly for protecting people, to avoid deterministic effects and to reduce stochastic effects of ionizing radiation. In light of the experience of the TEPCO Fukushima Daiichi accident, it is necessary to take protective actions such as evacuation even before a release of radioactive materials by detecting abnormal conditions at facilities. When radioactive materials are released, appropriate protective actions are required promptly according to the radiation conditions. The approach mentioned below is based upon the framework outlined by the IAEA.

It is necessary to define emergency classes associating plant conditions and corresponding hazards, to understand the plant situation clearly and to share this understanding among the staff at the site, responsible persons in local, regional and national organizations as well as the international community, and in order to establish a management system for protective actions. Three emergency classes are defined and Emergency Action Levels (EALs) for commercial reactors are predetermined to identify proper emergency class.

Emergency classes in Japan:

Alert

There are no radiation effects, nor any imminent hazards to the public, but caution is required because incidents detected might lead to abnormal phenomena at the nuclear facility.

  • Site Area Emergency

    It is necessary to start preparing for main protective actions such as evacuation around a nuclear facility because an incident that may possibly cause radiation effects on residents around the facility was detected in the facility.

  • General Emergency

    Competent authorities, including local governments, must conduct prompt protective actions in order to avoid deterministic effects and to reduce stochastic effects, because an incident which could possibly cause radiation effects on residents around the facility was detected.

In addition, Emergency Planning Zones for protective actions have also been determined for commercial reactors as follows considering lessons learned from the TEPCO Fukushima Daiichi accident:

Precautionary Action Zone (PAZ)

An area around a facility for which emergency arrangements were made to take urgent protective actions in the event of a nuclear or radiological emergency to avoid or to minimize severe deterministic effects off the site. Protective actions within this area are to be taken before or shortly after a release of radioactive materials or an exposure, on the basis of prevailing conditions at the facility. The range of a PAZ is recommended to be within approximately a 5 km radius from the nuclear facility.

  • Urgent Protective Action Planning Zone (UPZ)

    An area around a facility for which arrangements have been made to take urgent protective actions in the event of a nuclear or radiological emergency to avert doses off the site. Protective actions within this area are to be taken on the basis of environmental monitoring or, as appropriate, prevailing conditions at the facility. The range of a UPZ is recommended to be within approximately a 30 km radius from the nuclear facility.

Furthermore, Operational Intervention Levels (OILs) have been defined in order to implement appropriate protective actions after the release of radioactive materials into the environment.

  • OILs are expressed in terms of ground or surface concentrations, or activity concentrations of radionuclides in environmental, food or water samples.

  • OILs are used immediately and directly to determine the appropriate protective actions on the basis of an environmental measurement.

Figures 4 and 5 show the protective actions which are taken during each emergency class and each emergency planning zone.

FIG. 4. Protective actions in an emergency based on EALs.

FIG. 5. Protective actions in an emergency based on OILs.

Relevant local governments shall establish Regional Disaster Prevention Plans based on the Basic Act on Disaster Control Measures and provide basic measures for nuclear disaster control.

In the Fukushima Prefecture Regional Disaster Prevention Plans (nuclear emergency preparedness), however, which had been established before the accident :TEPCO Fukushima Daiichi accident with the Great East Japan Earthquake on 11 March 2011, various problems arose, including confusion regarding the evacuation of residents. Because the plans did not postulate accidents with natural disasters including earthquakes, etc., communication for residents was difficult due to the shortage of communication lines on disaster prevention administration wireless equipment and the damage to communication devices by earthquake and tsunami. Based on that situation, relevant local governments shall establish Evacuation Plans for residents with more concrete evacuation measures.

Based on the Basic Disaster Management Plan and Nuclear Emergency Response Guidelines, relevant local governments within approximately 30 km from nuclear power plants shall establish Regional Disaster Prevention Plans.

It is important that the contents in Regional Disaster Prevention Plans are effective and concrete. The state is expected support for measures that are unsolvable by the relevant local governments, once Evacuation Plans and measures for persons requiring assistance are established.

In March 2015, the Nuclear Disaster Management of the Cabinet Office, based on the Nuclear Emergency Preparedness Council’s decision in September 2013, established “Regional Nuclear Emergency Preparedness Committees” as working teams in 13 regions that are home to nuclear power plants to resolve problems. It then established working groups under the Committees. In the working group in each region, the support for establishment of Evacuation Plans, coordination for wide areas, and support for the State’s actual working units are considered. Furthermore, the State and relevant local governments together handle concrete actions and development of the Regional Disaster Prevention Plans and Evacuation Plans. The nuclear disaster control measures are compiled in areas in which the Regional Disaster Prevention Plans and Evacuation Plans are concrete and are developed. The Regional Nuclear Emergency Preparedness Committees confirm that the measures are concrete and reasonable, in the light of Nuclear Emergency Response Guidelines. The Nuclear Disaster Management of the Cabinet Office reports the results of this confirmation to the Nuclear Emergency Preparedness Council to request approval. In the confirmed nuclear disaster control measures, PDCA (plan, do, check, action) cycles are introduced and nuclear disaster control measures are developed on an ongoing basis. In this cycle, “plan” refers to the support and confirmation of concreteness and development, and the confirmation of nuclear disaster control measures; “do” refers to exercises based on nuclear disaster control measures that are confirmed in Regional Nuclear Emergency Preparedness Committees; “check” refers to the extraction reflection points from the results of the exercises; and “action” refers to the development of the nuclear disaster control measures in said areas based on these points.

In fiscal year 2015, “The measures in emergency situation in Ikata area” for the Ikata Regional Nuclear Emergency Preparedness Committee and “The measures in emergency situation in Fukui area” for the Fukui Regional Nuclear Emergency Preparedness Committee were confirmed. Those results were approved by the Nuclear Emergency Preparedness Council.

FIG. 6. Formulation of Regional Disaster Prevention Plans/Evacuation Plans.

3. NATIONAL LAWS AND REGULATIONS

3.1. Regulatory Framework

3.1.1. Regulatory Authority(s)

The use of nuclear power for energy is under the jurisdiction of Ministry of Economy, Trade and Industry in Japan. Regarding nuclear safety regulations, the Nuclear Regulation Authority was established as an external organ of the Ministry of the Environment in September 2012 (see also Section 2.1.1).

3.1.2. Licensing Process

The process for approval of or permission for nuclear power plants in Japan is as follows:

  • Review if the facilities conform to regulatory requirements by commissioners and safety review officers of the NRA.

    • Review meetings open to the public.

    • On-site investigations.

  • Opinion hearing on the permission.

    • Requesting the Atomic Energy Commission and the Minister of METI for their official comments based on the Reactor Regulation Act.

    • Public Comments on the “draft review report” from scientific and technical perspectives.

  • Installation permit/amendment of permit.

    • The NRA finalizes the review results based on the opinions, etc., and makes the decision.

3.2. National Laws and Regulations in Nuclear Power

Figure 7 shows the main laws controlling nuclear power plants in Japan as of May 2017.

FIG. 7. Schematic diagram of major nuclear laws in Japan.

(As of May 2017)

(1) “The Atomic Energy Basic Law” (1955-12-19 — Publications).

The research, development and use of nuclear energy shall be limited to peaceful purposes only to ensure safety. The Act prescribes three principles governing these activities:

(i) They shall be carried out under democratic management.

(ii) They shall be carried out voluntarily.

(iii) Information about them shall be freely available.

Nuclear related laws and regulations are enacted based on the spirit of the Act.

(2) “The Act on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors” (1957-6-10 — Publications) (hereafter called Reactor Regulation Act).

The main purpose of the Reactor Regulation Act is to ensure that the uses of nuclear source material, nuclear fuel material and reactors are limited to peaceful ones in accordance with the spirit of the Atomic Energy Basic Act (Act No. 186 of 1955), and also to provide necessary regulations on refining activities, fabricating and enrichment activities, interim storage activities, reprocessing activities and waste disposal activities, as well as on the installment and operation, etc. of reactors in order to prevent radioactive substances from being released in unusual levels from the area where the nuclear facilities are installed, as a result of either a severe accident or a large scale natural disaster.

In response to the TEPCO Fukushima Daiichi accident, the Reactor Regulation Act was revised by the Supplementary Provisions of the Act for Establishment of the Nuclear Regulation Authority (June 2012), for the purpose of introducing new regulations based on “lessons learned”, availability of the latest technical knowledge, as well as trends in overseas regulations, including regulatory requirements specified by international organizations such as the IAEA. The main points of the revision include (1) strengthening countermeasures against severe accidents, (2) adoption of the latest technical knowledge and introduction of the backfit system under which already authorized nuclear facilities are also required to conform to new regulatory requirements, (3) introduction of an approval system for the extension of operational periods, and (4) integration of all safety regulations on power reactors into the Reactor Regulation Act.

Based on the Reactor Regulation Act, it is necessary to go through the following steps for the installation of a nuclear power plant (Figure 8): installation permit/amendment of permit, approval of construction plan and approval of operational safety programme.

FIG. 8. Regulations in installation of nuclear power plants.

(3) “The Act on Prevention of Radiation Hazards due to Radioisotopes, etc.” (1957-6-10 — Publications).

The Act intends to prevent radiation hazards and ensure public safety by regulating use, sale, lease, waste management and other handling of radioisotopes, use of radiation generating apparatus and management of radioactive contaminants.

(4) “The Act on Special Measures Concerning Nuclear Emergency Preparedness” (1999-12-17 — Publications).

Taking quick initial action and ensuring integrated cooperation between state and local governments.

  • Strengthening the national emergency preparedness system for responding to a nuclear disaster.

  • Clarification of licensees’ role in preventing nuclear disasters.

(5) “The Law on Compensation for Nuclear Damage” (1961-6-17 — Publication).

Nuclear energy enterprises (electric power companies) owe no-fault liability for compensation to injured parties when nuclear damage is caused by the operation of nuclear reactors and the like. In such cases, liability focuses on the nuclear energy enterprises concerned.

Nuclear energy enterprises are compelled to deposit a fixed amount of money (maximum of JPY 120 billion) to cover the cost of measures taken to compensate for damage:

To make insurance contracts for damage compensation with private insurers.

  • To execute an indemnity contract with the government.

When damage is more than the amount deposited for compensation, the government will assist if necessary.

(6) “Electric Power Development Promotion Tax Law”.

(7) “Special Account Law”.

(8) “Law for the Adjustment of Areas Adjacent to Power-Generating Facilities”.

(9) “Law on Special Measures Concerning Promotion of the Development of Nuclear Power Sited Regions”.

These Laws are intended to promote electric power development by returning benefits gained for the whole country from a stable supply of electricity through the siting of a power plant to the local area.

“The Electric Power Development Promotion Tax Law” provides for collecting taxes used to fund the promotion of electric power development (according to electric power sold); the “Special Account Law” is for clarifying the government accounts for the uses of the tax revenue; the “Law for the Adjustment of Areas Adjacent to Power-Generating Facilities” is for smoothly setting up generating facilities by the promotion of public institutions; and the “Law on Special Measures Concerning Promotion of the Development of Nuclear Power Sited Regions” promotes the development of nuclear power plant site regions by giving financial and other assistance, and protection against the spread of nuclear accidents.

(10) “Designated Radioactive Waste Final Disposal Act” (2000-6-7 — Publications).

The law prescribes the establishment of implementation for disposal, a funding mechanism for securing disposal costs, and a three step site selection process.

REFERENCES

[1] “The New Long-range Plan for Development and Utilization of Nuclear Energy” (Revised in November 2000).

[2] “IAEA Energy and Economic Database” (EEDB).

[3] “IAEA Power Reactor Information System” (PRIS).

[4] “Organization and Staff of Electric Utilities and Related Corporations, Japan Electric Association”.

[5] “Nuclear Power Yearbook,” Japan Atomic Industrial Forum, Inc.

APPENDIX 1: INTERNATIONAL, MULTILATERAL AND BILATERAL AGREEMENTS

AGREEMENTS WITH THE IAEA

“Amendments of Article VI of the Statute of the IAEA”
Ratified:
31 May 2000
  • “Agreement on the privileges and immunities of the IAEA”

Entry into force:
18 April 1963
  • “Agreement between Japan and the IAEA implementation of Article III, 1 and 4 of the NPT”

Entry into force:
2 December 1977
  • “Protocol Additional to the Agreement between Japan and the IAEA implementation of Article III, 1 and 4 of the NPT”

Entry into force:
16 December 1999
  • “Regional Co-operative Agreement for Research, Development and Training Related to Nuclear Science and Technology for Asia and the Pacific (RCA)”

Entry into force:
12 June 2012

MAIN INTERNATIONAL TREATIES

“Treaty on the Non-proliferation of Nuclear Weapons”
Entry into force:
8 June 1976
  • “Convention on physical protection of nuclear material”

Entry into force:
27 November 1988
  • “Amendment to the Convention on the Physical Protection of Nuclear Material”

Entry into force:
8 May 2016
  • “Convention on early notification of a nuclear accident”

Entry into force:
10 July 1987
  • “Convention on assistance in the case of a nuclear accident or radiological emergency”

Entry into force:
10 July 1987
  • “Vienna Convention on civil liability for nuclear damage”

Non-party

  • “Protocol to amend the Vienna Convention on civil liability for nuclear damage”

Non-party

  • “Convention on Supplementary Compensation for Nuclear Damage”

Entry into force:
15 April 2015
  • “Convention on nuclear safety”

Entry into force:
24 October 1996
  • “Joint convention on the safety of spent fuel management and on the safety of radioactive waste management”

Entry into force:
24 November 2003

BILATERAL AGREEMENTS(2)

Agreement for:
Canada

Provision of information
Effective date:
27 July 1960
  • Provision of nuclear materials, facilities and equipment

Agreement revised:
2 September 1980
Transfer of patent rights
(Valid for 10 years, terminated thereafter by notice 6 months prior to the said termination date)

  • Use of facilities and equipment


  • Provision of technical assistance and services


  • Other means





Agreement for:
United Kingdom

Exchange of experts
Effective date:
15 October 1968
  • Provision and exchange of information

  • Provision of nuclear material and equipment

Agreement revised:
12 October 1998
  • Provision of services

(Valid for 25 years, terminated thereafter by notice 6 months prior to the said termination date)

  • Other means





Agreement for:
France

Exchange of experts
Effective date:
22 September 1972
  • Exchange of information

Agreement revised
19 July 1990
  • Provision of nuclear material, equipment and sensitive technologies

(Valid for 45 years, terminated thereafter by notice 6 months prior to the said termination date)

  • Provision of services


  • Cooperation in mining and the exploitation and use of mines


  • Other means





Agreement for:
Australia

Exchange of experts
Effective date:
17 August 1982
  • Provision and exchange of information

(Valid for 30 years, terminated thereafter by notice 6 months prior to the said termination date)

  • Provision of nuclear material, equipment and sensitive technologies


  • Provision of services


  • Other means





Agreement for:
China

Exchange of experts
Effective date:
10 July 1986
  • Provision and exchange of information

(Valid for 15 years, automatically extended thereafter for 5 years unless notice is provided 6 months prior to the termination date)

  • Provision of nuclear material, equipment and facilities


  • Provision of services


  • Other means





Agreement for:
United States of America

Exchange of experts
Effective date:
17 July 1988
  • Provision and exchange of information

(Valid for 30 years, terminated thereafter by notice 6 months prior to the said termination date)

  • Provision of nuclear material, equipment and components


  • Provision of services


  • Other means





Agreement for:
Euratom

Provision of nuclear material and equipment
Effective date:
20 December 2006
  • Provision of services

(Valid for 30 years, automatically extended thereafter for 5 years unless notice is provided 6 months prior to the termination date)

  • Exchange of experts


  • Provision and exchange of information


  • Other means





Agreement for:
Kazakhstan

Exchange of experts
Effective date:
6 May 2011
  • Exchange of information

(Valid for 10 years, automatically extended thereafter for 5 years unless notice is provided 6 months prior to the termination date)

  • Provision of nuclear material, equipment and technology


  • Provision of services


  • Other means





Agreement for:
Republic of Korea

Exchange of experts
Effective date:
21 January 2012
  • Exchange of information

(Valid for 10 years, automatically extended thereafter for 5 years unless notice is provided 6 months prior to the termination date)

  • Provision of nuclear material, equipment and technology


  • Provision of services


  • Other means





Agreement for:
Viet Nam

Exchange of experts and trainees
Effective date:
21 January 2012
  • Exchange of information

(Valid for 10 years, automatically extended thereafter for 5 years unless notice is provided 6 months prior to the termination date)

  • Provision of nuclear material, equipment and technology


  • Provision of services


  • Other means





Agreement for:
Jordan

Exchange of experts and trainees
Effective date:
7 February 2012
  • Exchange of information

(Valid for 20 years, automatically extended thereafter for 5 years unless notice is provided 6 months prior to the termination date)

  • Provision of nuclear material, equipment and technology


  • Provision of services


  • Other means





Agreement for:
Russia

Exchange of experts
Effective date:
3 May 2012
  • Exchange of information

(Valid for 25 years, terminated thereafter by notice 6 months prior to the said termination)

  • Provision of nuclear material, equipment and technology


  • Provision of services







Agreement for:
Turkey

Exchange of experts and trainees
Effective date:
29 June 2014
  • Exchange of information

(Valid for 15 years, automatically extended thereafter for 5 years unless notice is provided 6 months prior to the termination date)

  • Provision of nuclear material, equipment and technology


  • Provision of services


  • Other means





Agreement for:
United Arab Emirates

Exchange of experts
Effective date:
10 July 2014
  • Exchange of information

(Valid for 20 years, automatically extended thereafter for 5 years unless notice is provided 6 months prior to the termination date)

  • Provision of nuclear material, equipment and technology


  • Provision of services


  • Other means


APPENDIX 2: MAIN ORGANIZATIONS, INSTITUTIONS, AND COMPANIES INVOLVED IN NUCLEAR POWER RELATED ACTIVITIES

NATIONAL ATOMIC ENERGY AUTHORITY


Japan Atomic Energy Commission (JAEC), Cabinet Office
tel.: (+81) 3 6257 1315

Central Government Building No.8, 1-6-1 Nagatacho, Chiyoda-ku, Tokyo, Japan
web site: http://www.aec.go.jp/



REGULATORY AUTHORITY


Nuclear Regulation Authority
tel.: (+81) 3 3581 3352

1-9-9 Roppongi, Minato-ku, Tokyo, Japan
web site: http://www.nsr.go.jp/



GOVERNMENT ORGANIZATIONS


Ministry of Education, Culture, Sports, Science and Technology (MEXT)
tel.: (+81) 3 5253 4111

3-2-2 Kasumigaseki, Chiyoda-ku, Tokyo, Japan
web site: http://www.mext.go.jp/




Ministry of Economy, Trade and Industry (METI)
tel.: (+81) 3 3501 1511

1-3-1 Kasumigaseki, Chiyoda-ku, Tokyo, Japan
web site: http://www.meti.go.jp/




Ministry of Foreign Affairs (MOFA)
tel.: (+81) 3 3580 3311

2-2-1, Kasumigaseki, Chiyoda-ku, Tokyo, Japan
web site: http://www.mofa.go.jp/



CORPORATIONS RELATED TO NUCLEAR POWER


Japan Atomic Energy Agency (JAEA)
tel.: (+81) 29 282 1122

765-1 Funaishikawa, Tokai-mura, Naka-gun, Ibaraki, Japan
web site: http://www.jaea.go.jp/index.html




Japan Atomic Industrial Forum Inc. (JAIF)
tel.: (+81) 3 6812 7100

9th Floor, Kotohira Tower, 1-2-8 Toranomon, Minato-ku, Tokyo, Japan
web site: http://www.jaif.or.jp/




Central Research Institute of Electric Power Industry (CRIEPI)
tel.: (+81) 3 3201 6601

Otemachi Bldg.,1-6-1, Otemachi, Chiyoda-ku, Tokyo, Japan
web site: http://criepi.denken.or.jp/




World Association of Nuclear Operators (WANO) Tokyo Centre
tel.: (+81) 3 6722 5900

Igarashi Building 2-11-5 Shibaura, Minato-ku, Tokyo, Japan
web site: http://www.wano-tc.or.jp/



OWNERS/OPERATORS


The Federation of Electric Power Companies (FEPC)
tel.: (+81) 3 5221 1444

1-3-2, Otemachi, Chiyoda-ku, Tokyo, Japan
web site: http://www.fepc.or.jp/




Hokkaido Electric Power Co., Inc. (HEPCO)
tel.: (+81) 11 251 1111

2, Higashi 1-chome, Odori, Chuo-ku, Sapporo, Hokkaido, Japan
web site: http://www.hepco.co.jp/




Tohoku Electric Power Co., Inc. (TOHOKU)
tel.: (+81) 22 225 2111

1-7-1 Honcho, Aoba-ku, Sendai, Miyagi, Japan
web site: http://www.tohoku-epco.co.jp/




Tokyo Electric Power Company Holdings, Inc. (TEPCO)
tel.: (+81) 3 6373 1111

1-1-3, Uchisaiwai-cho, Chiyoda-ku, Tokyo, Japan
web site: http://www.tepco.co.jp/




Chubu Electric Power Co., Inc. (CHUBU)
tel.: (+81) 52 951 8211

1 Higashi-shincho, Higashi-ku, Nagoya, Aichi, Japan
web site: http://www.chuden.co.jp/




Hokuriku Electric Power Co., Inc. (HOKURIKU)
tel.: (+81) 76 441 2511

15-1 Ushijima-cho, Toyama-shi, Toyama, Japan
web site: http://www.rikuden.co.jp/




Kansai Electric Power Co., Inc. (KEPCO)
tel.: (+81) 6 6441 8821

3-6-16 Nakanoshima, Kita-ku, Osaka, Japan
web site: http://www.kepco.co.jp/




Chugoku Electric Power Co., Inc. (CHUGOKU)
tel.: (+81) 82 241 0211

4-33, Komachi Naka-ku, Hiroshima-shi, Hiroshima, Japan
web site: http://www.energia.co.jp/




Shikoku Electric Power Co., Inc. (SHIKOKU)
tel.: (+81) 87 821 5061

2-5, Marunouchi, Takamatsu-shi, Kagawa, Japan
web site: http://www.yonden.co.jp/




Kyushu Electric Power Co., Inc. (KYUSHU)
tel.: (+81) 92 761 3031

2-1-82, Watanabe-Dori, Chuo-ku, Fukuoka-shi, Fukuoka, Japan
web site: http://www.kyuden.co.jp




Japan Atomic Power Co., Inc. (JAPC)
tel.: (+81) 3 6371 7400

1-1, Mitoshiro-cho, Kanda, Chiyoda-ku, Tokyo, Japan
web site: http://www.japc.co.jp/



FUEL CYCLE


Japan Atomic Energy Agency (JAEA)
tel.: (+81) 29 282 1122

765-1 Funaishikawa,, Tokai-Mura, Naka-Gun, Ibaraki, Japan
web site: http://www.jaea.go.jp/index.html




Japan Nuclear Fuel Limited (JNFL)
tel.: (+81) 175 71 2000

4-108, Okitsuke, Obuchi, Rokkasho, Kamikita-gun, Aomori
web site: http://www.jnfl.co.jp/

Coordinator Information

Mr. Kensuke Onishi

Institution:

Agency for Natural Resources and Energy, Ministry of Economy, Trade and Industry

Contacts:

tel.: (+81) 3 3501 1991

fax: (+81) 3 3580 8447

email: onishi-kensuke@meti.go.jp


(1) Committees and authorities prescribed in Article 3, paragraph (2) of the National Government Organization Act, which are council organizations guaranteed to exercise their authority independently.

(2) Source: Nuclear Power Pocket Book 2014, Japan Atomic Industrial Forum, Inc.