HUNGARY

(Updated 2017)

PREAMBLE

This report provides information on the status and development of nuclear power programmes in Hungary, including factors related to the effective planning, decision making and implementation of the nuclear power programme that together lead to safe and economical operations of nuclear power plants.

The CNPP summarizes organizational and industrial aspects of nuclear power programmes and provides information about the relevant legislative, regulatory and international framework in Hungary.

Hungary has one nuclear power plant with four units, one research reactor and one nuclear training reactor in operation. Construction of new NPP units has been decided in order to meet future electricity demand.

1. GENERAL ENERGY OVERVIEW

1.1. Energy Information

1.1.1. Energy policy

In line with the most recent European Union Gas and Electricity Market Directives, all electricity and gas customers can freely select their supplier as of 1 July 2007. An act on electricity (Act LXXXVI of 2007) was adopted by the Hungarian Parliament, supporting full liberalization of the electricity market in order to enhance economic competitiveness and provide sustainable security of supply. The Act is harmonized with the requirements of the European Union. The provisions of the Act came into force partly from 15 October 2007 and from 1 January 2008. In the beginning of 2008, the electricity market became fully liberalized. Nevertheless, 2008 is considered a transition period, as the players in the market had to adapt to the new rules. The non-residential Hungarian electricity consumers pay for substantial subsidies to the renewables and combined heat and power sectors through levies on their tariffs. The new premium based renewable support scheme (METÁR) was accepted by the Hungarian National Parliament in 2016, and it will be introduced in 2017.

In February 2008, the National Climate Change Strategy for the period of 2008–2025 was adopted by the Hungarian Parliament. The strategy emphasizes the need for increasing energy efficiency, energy savings and the use of renewable energies (wind, solar, geothermic, biomass). It does not mention nuclear energy as part of the concept.

In April 2008, a resolution on a new energy policy concept for the period of 2008–2020 was adopted by the Parliament. The Hungarian energy policy aims at maintaining a balance between security of supply, cost effectiveness, energy efficiency and protection of the environment. According to the resolution, the Government should start working on the preparation of the decision on new nuclear capacity for the replacement of the old plants, and the proposal should be submitted to the Parliament in due time. The resolution also says that the Government should create the necessary conditions for the implementation of the programmes aimed at the final disposal of radioactive waste, and that the Government should inform the Parliament on the implementation of the energy policy at least every two years and in case of need it should propose the review of the concept.

The Hungarian Energy Strategy was adopted by the Parliament in October 2011. The Energy Strategy gives a roadmap until 2030 and it has a vision until 2050. The main aim of the strategy is to ensure the optimal balance of security of supply, competitiveness and sustainability. The energy imports should be decreased by diversification of resources and/or origins. The main elements of the strategy include the increased use of renewables, maintenance of nuclear capacity (lifetime extension and consideration of building new capacity), development of regional energy infrastructure, development of a new organizational system as well as increased effectiveness and efficiency in energy use. The National Energy Strategy can be found on the web site of the Ministry of National Development (http://www.kormany.hu/en/ministry-of-national-development). For more information see Section 2.3.1. According to government policy, energy price cuts reached 20% in 2014 for individual customers.

According to the National Policy for the Management of Spent Fuel and Radioactive Waste adopted in April 2015 by the Parliament and National Programme for the Management of Spent Fuel and Radioactive Waste approved by the Government in 2016, the national development goals and objectives relating to spent nuclear fuel and radioactive waste are: development of a national strategy for the back end of the fuel cycle with due consideration to be given to various options; continuous extension of the Spent Fuel Interim Storage Facility in Paks; phased implementation of the geological investigation programme of the Boda Claystone Formation aiming at a future deep geological repository; ongoing implementation of the safety enhancement programme at the Radioactive Waste Treatment and Disposal Facility in Püspökszilágy as well as the extension of the National Radioactive Waste Repository in Bátaapáti and optimization of its disposal concept.

The Act on Atomic Energy (Act CXVI of 1996) was modified to a great extent in 2011. The most important elements of the modification concerned the safety principles and the tasks and activity of the Hungarian Atomic Energy Authority (HAEA). The nuclear safety codes have also been modified, with the WENRA reference levels built in. The set of requirements was completed by two new volumes in order to define requirements for all parts of the lifetime of nuclear facilities. The new set of requirements came into force on 1 November 2011.

A modification of the Act in 2013 declares that in all facility level licensing procedures the HAEA shall arrange public hearings to ensure transparency and openness.

Furthermore from 1 July 2014 the responsibilities of the HAEA have undergone several changes. According to this amendment HAEA took over the task of regulatory oversight of the radioactive waste repositories. The Act also introduced new procedures regarding licences for site assessment and evaluation, and licences to define characteristics and to determine the suitability of the site.

The Hungarian Parliament approved Act VII of 2015 on the modification of the regulations involving the construction of new nuclear power plant units (the “Project” Act). The Project Act amended the Act on Atomic Energy in several sections. The new provisions (inter alia) extend the responsibility of the HAEA over the supervision of application of ionizing radiation as well as over radioactive waste repositories, and guarantee that the revenues of the HAEA can only be used for regulatory purposes. The Project Act furthermore transfers the responsibilities to HAEA for radiation protection (safety of radioactive sources, safety of equipment emitting ionizing radiation without radioactive material), personal dose monitoring, environmental monitoring, construction of general civil structures and buildings of nuclear facilities and radioactive waste repositories as of 1 January 2016. Lower level legislative amendments also entered into force on 1 January 2016.

From 1 January 2016, HAEA is the general construction supervisory authority for construction in the safety zone of nuclear installations and radioactive waste depositories. (HAEA was responsible for the supervision of special nuclear construction exclusively.) The latest amendments are to enter into force on 1 January 2017.

The modified Act and the new safety codes can be found on the HAEA’s web site (www.haea.gov.hu).

After the accident at the Fukushima Daiichi Nuclear Power Plant (NPP), all European countries operating NPPs performed the Targeted Safety Reassessment (TSR) — the so-called stress test — to meet the request of the European Council. The TSR of Paks NPP focused on topics specified by the ENSREG (the issues corresponding to earthquake and/or flooding and other external natural hazard factors, to the loss of electric power supply and loss of ultimate heat sink or a combination of those, and to severe accident management). In relation to the hazard factors it was assessed whether the design basis of the plant was duly determined and whether there were sufficient reserves beyond design basis before severe damage occurred. Based on the final report of the Paks NPP submitted to the HAEA for regulatory review, the HAEA agreed with the proposed tasks in the report to be carried out in order to further improve the plant safety and identified a few additional options. Along with the detailed coverage of the topics specified by ENSREG, HAEA also established that the national legal requirements for the safety of NPPs are in line with the international standards and best practices. HAEA submitted the National Report about the results of the review to the European Commission by the end of 2011 and published it on its web site (www.haea.gov.hu). Based on the results of the regulatory review of the TSR, HAEA concluded that the design basis of Paks NPP is adequate, and complies with the legal requirements and international practice. The safety systems and safety functions satisfy requirements of the design basis. After the last Periodic Safety Review of Paks NPP, specific safety enhancement measures were implemented, mainly in order to improve the plant’s beyond design basis capabilities. These measures are fully in line with expectations of the TSR as well. It can be concluded that Paks NPP is safe and no deficiency has occurred. The measures initiated by the last Periodic Safety Review provide robust capabilities for the plant for successful management of severe situations as well. In addition to the positive findings, the TSR identified a number of options and measures to enhance plant safety even further. The HAEA ordered the operator of the plant to develop the detailed programme by the end of the first half of 2012 in order to realize these options.

The National Action Plan of Hungary on the implementation actions decided upon the lessons learned from the Fukushima Daiichi accident was adopted in December 2012. The National Action Plan has been prepared in accordance with the recommendations of ENSREG (see ENSREG web site). The implementation of the National Action Plan is currently in progress.

As of 31 December 2016, the status of the National Action Plan at the Paks NPP on the implementation actions decided upon the lessons learned from the Fukushima Daiichi accident is the following: out of 46 tasks, 33 are ready and closed by the HAEA, 1 is ready and under review by the HAEA, and 12 tasks are still ongoing.

1.1.2. Estimated Available Energy

TABLE 1. ESTIMATED AVAILABLE ENERGY SOURCES

Estimated available (exploitable) energy sources
 Fossil fuels Nuclear  Renewables
Solid Liquid Gas Uranium Hydro Other
renewable
Total amount in specific units* 8 413.7 66.9 1 675.3 26.8
Total amount in exajoule (EJ) 0.016 60.110

* Solid, Liquid: Million tons; Gas: Billion m3; Uranium: Metric tons; Hydro, Renewable: EJ.

Source: Hungarian Office for Mining and Geology.

Hungary has estimated coal reserves of more than 10.5 billion tonnes. The bulk of this is lignite, with 5.7 billion tonnes, followed by 3.1 billion tonnes of brown coal and 1.6 billion tonnes of hard coal. The coal found in Hungary has comparatively low calorific value with high ash and sulphur content. Only lignite deposits in the north-east region of Hungary could profitably be mined. An important element of coal mining is the rigorous application of environmental protection requirements. Although the major share is used for power generation, a significant amount of coal was used for heating and cooking in households and communal facilities until the early 1990s; since then, the use of coal has rapidly declined. Domestic production of coal has also declined in the last two decades. Hungary produced about 9 263 Mt of coal in 2015, and imports are needed. The imports come mostly from the Czech Republic, Poland and the Russian Federation. Hungary’s oil and gas reserves are relatively small. Hungary’s uranium resources are limited to those of the Mecsek deposit. Between 1956 and 1997, uranium was mined at the underground Mecsek mine by the Mecsek Ore Mining Company, producing a total of just over 21 000 tU (tonnes of uranium metal). Until an ore processing plant became operational at the site in 1963, all ore was shipped to the Sillimae metallurgy plant in Estonia. After 1963, uranium concentrates produced at the processing plant were shipped to the Soviet Union. The mine was closed in 1997 due to poor market conditions. Remediation activities began the following year and were completed in 2008. Ongoing treatment of contaminated water from the mine and tailings ponds results in the collection of about 1 to 3 tU per year.

The MECSEKÉRC Environmental Protection Public Limited Company was established as a state owned company continuing the State mine remediation tasks. This company undertakes environmental protection, geoscience, technical and geotechnical jobs in the following fields:

Design and implementation of repositories to be developed with mining techniques (e.g. prospecting for low and intermediate level radioactive waste repositories, gas or LPG storage facilities, pumping energy accumulator power plants);

  1. Prospecting and preparation of interim or final disposal of radioactive and hazardous waste, and the construction of facilities for these purposes;

  2. Planning and fulfillment of the remediation activity for the uranium industry in central European countries;

  3. Full-scale remediation and land reclamation activity to wind up consequences of former mining and other environment harming activities;

  4. Soil mechanical test, control and design of earthworks;

  5. Environmental damage assessment;

  6. Planning, implementing and licensing of environmental damage remediation activities;

  7. Geological, hydrogeological and mineral resource prospecting;

  8. Geological, hydrogeological and soil mechanical planning and carriage tasks related to infrastructure investments (e.g. road and railway construction);

  9. Testing, planning and carriage work for protecting and securing drinking water resources;

  10. Surface and underground solid mineral mining activity, obtaining mining licences.

1.1.3. Energy Statistics

TABLE 2. ENERGY STATISTICS (EXAJOULE)

1990 2000 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Average annual growth rate (%)
Energy consumption**        
- Total 1.204 1.055 1.125 1.126 1.056 1.120 1.096 1.041 1.007 1.005 1.063 1.078 -0.635
- Solids*** 0.160 0.131 0.127 0.106 0.114 0.113 0.108 0.094 0.092 0.099 0.093 -3.336
- Liquids 0.330 0.315 0.304 0.292 0.284 0.270 0.253 0.245 0.275 0.294 0.302 1.029
- Gases 0.377 0.448 0.442 0.383 0.411 0.392 0.351 0.322 0.292 0.314 0.336 -3.302
- Nuclear (electricity) 0.141 0.161 0.162 0.169 0.172 0.172 0.173 0.168 0.172 0.174 0.176 0.384
- Hydro (electricity) 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.000
- Wind (electricity) 0.000 0.001 0.001 0.002 0.002 0.002 0.003 0.003 0.002 0.002 0.002 0.000
- Primary electricity (net import) 0.010 0.014 0.014 0.020 0.019 0.024 0.029 0.043 0.048 0.049 0.046 15.878
- Other
renewables
0.033  0.055  0.068 0.078 0.117 0.122 0.124 0.131 0.122 0.130 0.122 0.700
Energy production
- Total 0.634 0.485 0.427 0.436 0.458 0.497 0.493 0.492 0.480 0.464 0.473 0.472 -0.856
- Solids*** 0.121 0.074 0.071 0.065 0.067 0.069 0.067 0.067 0.066 0.064 0.061 -1.551
- Liquids 0.070 0.050 0.052 0.051 0.046 0.041 0.043 0.037 0.035 0.036 0.040 -2.302
- Gases 0.104 0.084 0.084 0.096 0.094 0.089 0.074 0.065 0.060 0.057 0.060 -7.209
- Nuclear 0.155 0.161 0.162 0.169 0.172 0.172 0.173 0.168 0.172 0.174 0.176 0.384
- Hydro 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.000
- Wind 0.000 0.001 0.002 0.002 0.002 0.003 0.003 0.002 0.002 0.002 0.000
- Other
renewables and wastes
0.035 0.054 0.069 0.079 0.116 0.120 0.131 0.140 0.127 0.139 0.132 2.177
Net import (Import - Export)
- Total 0.570 0.570 0.691 0.711 0.622 0.633 0.547 0.519 0.501 0.594 0.569 0.606 -0.724
Stock changes (Opening - Closing stock)
- Total 0.008 0.031 0.033 -0.01 0.055 0.03 0.026 -0.055 0.022 -0.000 -31.871

* Latest available data.

** Energy consumption = Primary energy production + Net import (Import - Export) of secondary energy + stock change.

*** Solid fuels include coal, lignite.

Source: Hungarian Energy and Public Utility Regulatory Authority, Directorate of Analysis and Statistics.

1.2. The Electricity System

1.2.1. Electricity System and Decision Making Process

The reform of the electricity industry started in 1994–1995, when Act XLVIII of 1994 on Production, Transportation and Supply of Electricity was developed and came into force. The Hungarian Energy Office (at present: Hungarian Energy and Public Utility Regulatory Authority) was established in 1994. The privatization of the electricity sector took place in several phases. At present, the majority of power stations and 100% of the electricity suppliers (the grid and the distributors) are privately owned.

In Hungary, the electricity policy is an integrated part of the energy policy. The most important document upon which the Hungarian electricity market liberalization was founded was entitled “Principles of Hungarian Energy Policy and a New Business Model”. It was adopted by the Government in 1999 (Government Resolution 2199/1999).

Hungary became a member-state of the European Union in 2004 and that required further harmonization of the Hungarian legal framework with European Union legislation. An important step of the harmonization was the adoption of a new Act on Electricity (Act LXXXVI of 2007) which was adopted by the Parliament in 2007. The harmonization and electricity policy objectives were reflected in the Act. The aim of the Act is the effective operation of the competitive electricity market. Access to the electricity grid is guaranteed at regulated prices. Transmission, distribution and system operation tariffs are set and published by the Minister of National Development. New capacities are established on a commercial basis through an authorization process. The new Act regulates the rules of full market opening, which entered into force in 2008.

The energy market was fully opened on 1 January 2008. To supply vulnerable consumers, universal service supplier licences were issued in addition to the licence types previously in use. In parallel with the abolition of public utility supply, the licence for public utility wholesale was also abolished. The European Commission investigated the compatibility of long term contracts (which aimed to prepare the privatization in the single buyer model) with the competitive market. In decision No. C-41/2005, published on 4 June 2008, the Committee stated that the contracts implied prohibited state subsidy and ordered they be terminated and the prohibited state subsidy repaid. Thereby, the system of long term contracts ceased to be in force at the end of 2008. Due to the lack of generation sources in the region and the high oil prices, the full market opening resulted in an unexpected price rise on the domestic market. The Electricity Act was again amended in June 2008 to ensure an “intervention possibility” in determining the prices. Based thereon and after identifying the participants with considerable market power, the Hungarian Energy and Public Utility Regulatory Authority ordered MVM Trade Ltd. and GTER Ltd. to apply electricity price caps. The universal service category includes the household consumers and (former public utility) low voltage consumers with nominal current not greater than 3×63 A. In this circle, authority (regulated) pricing continues to exist. The competitive market consumers have to purchase the power from the traders and have to sign a network use contract with the network licence holder competent in the relevant area. Authority pricing now concerns only the system use charges; the prices of electricity traders are set by the competitive market. However, network access is ensured for each market participant. In connection with residential consumers (eligible for universal service), on 15 December 2012 the Ministry of National Development issued a decree stipulating price reductions in electricity (a cut of 10%) as of 1 January 2013. Further price cuts were introduced in 2013 and 2014 as well, reducing the tariffs by 26% altogether.The relevant laws are available on the web site of the Hungarian Energy and Public Utility Regulatory Authority (www.mekh.hu).

The responsibility for providing a reliable, efficient and environmentally friendly energy supply for Hungary belongs to the Ministry of National Development (www.nfm.gov.hu), established in 2010. Directly under the top political level, energy issues are handled by the Minister of State for Energy Affairs. Development, competitiveness, security and sustainability are the key words directing the activity of the ministry.

The Hungarian Energy and Public Utility Regulatory Authority (MEKH) (www.mekh.hu) is currently responsible for licensing energy suppliers, supervising the balance of demand and production as well as the standards of service provision, and protecting consumer interests. Pursuant to Section XIX of the Act on Electricity (Act LXXXVI of 2007), the Hungarian Energy and Public Utility Regulatory Authority is an independent governmental office with separate and independent financial management. The MEKH is self-financing. Licencees are charged a supervisory and administration fee for their activities. Following a proposal by the Ministry of National Development, the Prime Minister appoints and relieves the MEKH president. MEKH resolutions can only be appealed and amended in court. The goal of MEKH is to ensure market operation, to promote competition and to implement the efficiency requirements and principle of least cost, to sustain and improve security of supply and to protect the interests of users and licence holders as well as to regulate prices in order to guarantee fair competition.

The Ministry for Agriculture (FM — http://www.kormany.hu/hu/foldmuvelesugyi-miniszterium) is responsible for environmental issues. The task of the State Secretariat for Environmental Affairs within the Ministry is promotion of sustainable development, the preservation of air, water and soil quality and the protection of natural assets. In the area of waste management, the Ministry has the aim of reducing pollution and facilitating recycling and up to date treatment of waste.

According to the legislation in force, the approval of the Government or the Parliament is needed for the establishment of power plants above 200 MW capacity. Between 200 and 600 MW capacity, it is the right of the Government to give the approval, while above 600 MW capacity, the Parliament has to approve it. Any nuclear installation, including power and research reactors, should be approved by the Parliament independently of its capacity. In 2009 the Parliament authorized the government to start preparations for new nuclear units to be built at the Paks site.

1.2.2. Structure of Electric Power Sector

In the last decade, Hungary made substantial progress in restructuring its electricity sector and creating a market oriented, fully European Union conforming regulatory framework. Today, the power industry is restructured and mainly privatized.

Figure 1 shows the simplified model of the Hungarian electricity industry.

FIG. 1. Hungarian electricity industry.

MVM Hungarian Electricity Ltd.

MVM Hungarian Electricity Ltd. (http://mvm.hu/?lang=en) is a competitive strategic holding company and nationally owned corporate group. MVM Group is an integrated player in the domestic electricity and gas market, and it is also active in the electricity and gas industry in the region. The holding company led by MVM Ltd. has been operating as a “Recognized Corporate Group” as of 1 June 2007. The group realized an EBITDA of HUF 110 billion and a profit after tax of HUF 48 billion against sales of HUF 1 034 billion in 2016.

The integrated structure of the Group, reflecting an organizational structure widespread in Europe and conforming to the norms of the European Union, provides a proper background for the fulfilment of its diverse tasks and for the developments which are necessary in the power system.

The strategic target of MVM to 2020 is to double its EBITDA by retaining its existing positions and accessing new growth areas through:

Achieving operational excellence to increase competitiveness;

  • Partnership in providing energy security;

  • Integrating the value chain to optimize the value chain and presence in growth areas;

  • Increasing presence in renewable energy production;

  • Innovating and providing energy related services;

  • Expanding in the region.

Currently, the group controls one of the most important sectors of the national economy, the domestic electricity supply. The activities include electricity generation, transmission system operation and electricity trade (wholesale).

MVM is also taking a key role in the natural gas market. Currently the group is present in all key areas of the business, namely natural gas storage, wholesale and trading.

The key assets/companies of the group include Paks nuclear power plant (2000 MW installed capacity), open cycle gas turbines (526 MW installed capacity), CHPs (114 MW installed capacity), renewable generation units (23 MW wind, 10 MW solar), MAVIR (Hungarian Transmission Operartor), Hungarian Gas Storage Ltd. (4.43 bcm storage capacity) and the electricity and gas wholesalers (Hungarian Gas Trade Ltd. and MVM Partner Ltd).

In order to prepare the planned new units, MVM established its new project company, MVM Paks II. Nuclear Power Plant Development Ltd. (MVM Paks II. Ltd. or project company) in 2012. Due to change of ownership in November 2014 (with the aim of shortening the decision making mechanism), the project company MVM Paks II. Ltd. does not belong to the MVM Group anymore. It came under direct state control starting when the Prime Minister’s Office obtained the owner’s rights and until the end of 2026.

FIG. 2. The structure of the MVM Group.

The installed capacity of domestic power plants on 31 December 2016 was 8 339 MWe. Compared to the value of 31 December 2015 (8 453), it decreased slightly by 114 MWe. The peak load of the Hungarian electricity system was 6 749 MW in 2016, which means an increase of 292 MW compared to 2015 (6 457 MW). Though the increase in energy efficiency may help reduce the rate of increase of primary energy consumption, it is still expected that the electricity demand will increase after overcoming the world crisis. The peak demand will increase between 700 and 1 300 MW by 2031. Taking into account the necessary shutdown of old fossil power plants, new generation capacity of between 4 500 and 5 100 MW is needed by 2031.

The generation mix of the Hungarian electricity system is presently well balanced, with about 17% gas, 52% nuclear, 19% coal and an increasing ratio of renewables. The electricity production from renewable energy sources is growing in accordance with the European Union directive on green electricity. In 2015, renewable based electricity production made up a share of 7.3% of total electricity production.

The Hungarian energy supply is around 60% import dependent; therefore its security is a crucial priority of the National Energy Strategy. The safe, successful and profitable operation of the state owned Paks NPP greatly contributes to meeting this challenge. The obligatory stockpiling of nuclear fuel for two years is also an essential element in ensuring the stability of supply in case of any disturbances in imports.

Companies operating power plants of 50 MW or higher capacity:

Tisza Eromu Kft. 
http://tiszapower.eu/
Alpiq Csepel Kft.
http://csepel.alpiq.hu
Bakonyi Eromu Ltd. 
www.bakonyi.hu
Budapesti Eromu Ltd.
www.bert.hu
Debreceni Kombinált Ciklusú Eromu Kft.
www.veolia.hu
Dunamenti Eromu Ltd.
www.dert.hu
E.ON Eromuvek Kft.
www.eon-hungaria.com
ISD-Power Ltd.
www.isdpower.hu
MVM GTER Gázturbinás Eromu Ltd.
www.gter.hu
Mátrai Eromu Ltd.
www.mert.hu
MVM Paksi Atomeromu Ltd.
www.npp.hu
PANNON Hoeromu Ltd.
www.pannonpower.hu
Vértesi Eromu Ltd.
www.vert.hu

There are a further 200 companies, operating more than 300 (small) power plants under 50 MW capacity.

Transmission operator

MAVIR Ltd.
www.mavir.hu

In Hungary, high voltage electricity is transmitted on a single common transmission line network, which is owned and operated by the Hungarian Transmission System Operator, MAVIR Ltd. This oranization is, at the same time, a member of the MVM Group. The Transmission System Operator operates according to the ITO (Independent Transmission Operator) model: it operates independently of the other economic operators that use the transmission network, and its independence is prescribed by legislation. In accordance with the relevant statutory regulations, MAVIR Ltd., as an organization independent of other participants in the electricity system, is responsible for ensuring a secure energy supply.

Electricity distribution

There are six regional distribution companies responsible for operation of networks with a voltage of 120 kV and below, as well as supply for the customers.

E.ON Észak-dunántúli Áramszolgáltató Ltd.

DÉMÁSZ Hálózati Elosztó Ltd.
www.demasz.hu
E.ON Dél-dunántúli Áramszolgáltató Ltd.

E.ON Tiszántúli Áramszolgáltató Ltd.

ELMÜ Hálózati Ltd.
www.elmu.hu
ÉMÁSZ Hálózati Ltd.
www.emasz.hu

1.2.3. Main Indicators

TABLE 3. ELECTRICITY PRODUCTION, CONSUMPTION AND CAPACITY

              Average annual growth rate (%)
1970 1980 1990 2000 2005 2010 2011 2012 2013 2014 2015 2016
Capacity of electrical plants (GWe)
- Thermal** 5.36 6.32 6.35 6.13 6.76 6.73 6.70 5.643 5.51 5.592 1.5%
- Hydro 0.05 0.05 0.05 0.05 0.06 0.06 0.06 0.057 0.057 0.058 1.8%
- Nuclear 1.76 1.85 1.87 2 2 2 2 2 2 2 0%
- Wind 0 0 0.02 0.29 0.33 0.33 0.36 0.329 0.329 0.329 0%
- Geothermal 0 0 0 0 0 0 0 0 0.000 0 0%
- Other renewable*** 0.01 0.02 0.36 0.52 0.5 0.29 0.3 0.626 0.684 0.686 0.4%
- Total 2.48 4.98 7.18 8.29 8.6 8.99 9.65 9.41 9.40 8.655 8.579 8.665 1%
 
Electricity production (TWh)
- Thermal** 14.51 20.77 20.05 18.59 17.63 16.19 12.14 10.60 11.30 12.5 10.8%
- Hydro 0.18 0.18 0.2 0.19 0.22 0.21 0.21 0.30 0.23 0.26 10.3%
- Nuclear 13.73 14.18 13.83 15.76 15.69 15.79 15.37 15.65 15.83 16.05 1.4%
- Wind 0 0 0.01 0.53 0.63 0.77 0.72 0.66 0.69 0.68 -1.3%
- Geothermal 0 0 0
- Other renewable*** 0.02 0.07 1.66 2.30 1.86 1.66 1.86 2.18 2.28 2.22 -2.7%
- Total1 14.5 23.9 28.44 35.2 35.75 37.37 36.02 34.63 30.29 29.39 30.34 31.73 4.6%
Total electricity consumption (TWh)**** 17.94 31.3 39.58 38.63 41.98 42.57 42.63 42.55 42.2 42.15 43.98 44.44 0.1%

1 Electricity transmission losses are not deducted.

* Latest available data.

** Only fossil fuel, and non renewable municipal waste and industrial waste.

*** Renewable combustible fuel; solar.

**** Gross production + imp - export.

Sources: Hungarian Power Companies Ltd. Hungarian Energy and Public Utility Regulatory Authority (only data for 2014, 2015, 2016).

TABLE 4. ENERGY RELATED RATIOS

1990 2000 2009 2010 2013 2014 2015 2016
Energy consumption per capita (GJ/capita) 116 103 106 112 102 102 108 109
Electricity consumption per capita (kWh/capita) 3.817 3.78 4.13 4.3 4.3 4.4 4.5 4.5
Electricity production/Energy production (%) 14.4 27.0 34.1 27.1 22.7 22.8 23.1 24.2
Nuclear/Total electricity (%) 48.1 40.3 43.0 42.2 50.7 53.2 52.2 50.6
Ratio of external dependency (%) 1 47.34 54.0 62.0 56.5 49.7 59.3 53.5 56.2

1 Net import / Total energy consumption.

* Latest available data

Source: Hungarian Statistical Office.

2. NUCLEAR POWER SITUATION

2.1. Historical Development and Current Organizational Structure

2.1.1. Overview

The first Hungarian reactor was built for research purposes at Csillebérc, on the outskirts of Budapest in 1959. The reactor, of Soviet origin and refurbished by Hungarian experts after 30 years of operation, was put into operation again by the Atomic Energy Research Institute in 1993. The Budapest Research Reactor is a tank type reactor with 10 MWth power and is operated by the Centre for Energy Research of HAS.

The Training Reactor of the Institute of Nuclear Techniques (NTI) of the Budapest University of Technology and Economics (BME) was put into operation in 1971. Since then, the training reactor has been used mainly for the purposes of education in the nuclear field. It is a pool type reactor with 100 kWth power.

In 1966, it was decided to construct a NPP in Hungary. The decision included two WWER-440 type, 230 model reactors. The construction work started in 1968, but it was interrupted in 1970 because, at that time, oil fired stations were considered to be more economical. The actual construction work started after the oil crisis in 1975. The final decision included four second generation reactors, i.e. WWER-440/213, instead of the two 230 model reactors, all to be part of one NPP. The plant is located about 5 km south of the town Paks, on the right bank of the river Danube. Since 1987, these four reactors have been generating electricity for the Hungarian electric energy system. The original installed capacity of the reactors was 4 times 440 MWe. Earlier upgrades of the secondary circuit and turbine resulted in an uprated 470 MWe, with an unchanged thermal capacity at all four units. An upgrade of the primary side was decided, to increase the nominal power by 8% to 1485 MWth, resulting in about 500 MWe generated power per unit. The power uprate was completed in 2009. Based on the application of the operator, HAEA granted 20 years service life extention for Unit 1, Unit 2 and Unit 3. In November 2016 the NPP submitted its request for authorization of the lifetime extension of Unit 4.

Hungary’s national policy concerning the application of atomic energy is regulated by law. The basic purposes of Act CXVI of 1996 are those of protecting the health and safety of the population and protecting the environment. The requirements of the Act state that the use of atomic energy is allowed only in a manner provided by law and under the permanent control of the competent authority. Regardless of what aspect of atomic energy is being considered, safety is a priority.

2.1.2. Current Organizational Chart(s)

Licensees

MVM Paks Nuclear Power Plant Ltd. (www.npp.hu) — Has four WWER-440/213 type power reactors.

MVM Paks II. Nuclear Power Plant Development Ltd. (http://www.mvmpaks2.hu) — The goal of the Company is to continue performing at a high professional standard the tasks involved in the preparation of the establishment of new nuclear power plant units.

Public Limited Company for Radioactive Waste Management (PURAM) (http://www.rhk.hu/en) — Operates the Spent Fuel Interim Storage Facility at Paks and the Radioactive Waste Treatment and Disposal Facility at Püspökszilágy that manages low and intermediate level waste generated by medical, industrial and research applications. It also operates the National Radioactive Waste Repository in Bátaapáti dealing with low and intermediate level waste generated in the Paks NPP. PURAM is investigating the Boda Claystone Formation in west Mecsek to select a site for high level and long lived radioactive waste.

Hungarian Academy of Sciences Centre for Energy Research (www.energia.mta.hu) — Operates the Budapest Research Reactor.

Institute of Nuclear Techniques of the Budapest University of Technology and Economics (www.reak.bme.hu) — Operates the BME Training Reactor.

Governmental Organizations with Responsibility in Nuclear Field

The Hungarian Atomic Energy Authority (HAEA) (www.haea.gov.hu) is a public administration body acting in the field of peaceful applications of atomic energy with a specified scope of tasks and authority, and is independent from both the organizational and financial points of view. Establishing the regulatory duties in connection with the safety of the peaceful application of nuclear energy, particularly with the safety of nuclear facilities under normal and accident conditions and with nuclear emergencies, is a basic task of the HAEA. In addition, the HAEA is required to harmonize and handle the related public information activities. Acting independently and supervised by a minister appointed by the Prime Minister, the HAEA is primarily concerned with ensuring nuclear safety in accordance with the law. From 2010, the Minister of National Development is responsible for the supervision of the HAEA’s activity. The Director General of the HAEA is appointed and relieved by the Prime Minister. The HAEA resolutions can only be appealed and amended in court.

The Ministry of Human Capacities undertakes the tasks of the authority regarding issues related to radiation protection during medical irradiation.

Within the Ministry of Agriculture, the State Secretariat for Environmental Affairs, Agricultural Development and Trademarks is responsible for establishing air and water quality standards, limits on radioactive releases from nuclear facilities, as well as for controlling the emissions at the facilities to the environment.

Research Institutes

The HAS Centre for Energy Research was established in January 2012 from two former independent institutions, the Institute of Isotopes and the KFKI Atomic Energy Research Institute. The Institute of Technical Physics and Material Science (MFA) joined the centre on 1 January 2015. The Centre is part of the a research network of the Hungarian Academy of Sciences (HAS). The website of the new organization can be found at www.energia.mta.hu.

The center operates the 10 MWth Budapest Research Reactor. It is active in several fields of nuclear technology, such as reactor physics, thermal hydraulics, health physics, simulator techniques and reactor chemistry. It performs a wide variety of research related to the use of radioactive materials and nuclear techniques, among them a research and development programme for nuclear safeguards. It provides the expert support and the laboratory equipment for the HAEA.

The Institute of Nuclear Research (ATOMKI, Debrecen) of the Hungarian Academy of Sciences operates a 20 MeV cyclotron and a 5 MeV Van de Graaff accelerator, and is active on several fields of nuclear physics and nuclear techniques (www.atomki.hu).

The National Research Institute for Radiobiology and Radiohygiene (OSSKI, Budapest) performs a wide spectrum of research including on the biological effects of radiation and radioisotopes, radiohygiene (operational and environmental), sterilization, detoxification, etc. As of 3 April 2015 the Institute merged with National Public Health Centre (Országos Közegészségügyi Központ) (www.osski.hu).

The Nuclear Research Safety Institute (NUBIKI, Budapest) carries out safety analysis and risk assessment of nuclear power plants including level 1 and 2 PSA and severe accident analysis (www.nubiki.hu).

The Institute of Nuclear Techniques of the Budapest University of Technology and Economics (BME NTI) operates a training reactor, teaches nuclear technology for engineers, physicists, chemists and environmentalists, and performs research in different nuclear related topics (www.reak.bme.hu).

The Power Engineering and Contractor Co., Poyri Eroterv Co. (before 2010: ETV-EROTERV Co., Budapest) works in the fields of design, construction, commissioning and operating management of nuclear facilities. Its activities include waste management (treatment, storage and disposal) (http://www.poyry.hu/).

The Institute of Experimental Physics of the University of Debrecen operates the Laboratory for Nuclear Safety and Techniques, NUBITEL (http://falcon.phys.klte.hu/kisfiz/) and the Quantechnologies Research and Development Co. (http://www.quantec.hu/). The following main fields represent their areas of operation: in-situ alpha, beta and gamma activity measurements in NPPs (primary circuit and refueling, storage and technical ponds); exploration and handling of nuclear waste; detection of radioactivity in the environment (NORM/TENORM), underwater gamma spectrometry; data evaluation and trend analysis; and education and training in applied nuclear physics.

  1. The Department of Nuclear Medicine of the University of Debrecen (DE NMI) (http://www.pet.dote.hu/) operates a GE PETtrace cyclotron and a radiochemistry center, and develops and produces positron labeled radiopharmaceuticals for medical and research purposes. The department takes part in various IAEA training programmes.

The Institute of Radiochemistry and Radioecology at the University of Pannonia has a wide range of topics in research and education in two main fields: radiochemistry and nuclear technology, as well as radioecology and radiation protection (http://radio.mk.uni-pannon.hu/).

2.2. Nuclear Power Plants: Overview

2.2.1. Status and performance of nuclear power plants

Taking into account the energy situation in Hungary, the operation of the only NPP is crucial. The design lifetime of the WWER-440/213 Units at Paks is 30 years; the operating licence is formally limited in time by the planned operational lifetime. As in other countries, the current Hungarian legislation for nuclear energy allows the renewal of the operating licence, if the safety of the continuation of the operation can be demonstrated, and the renewal is approved by the responsible authorities.

TABLE 5. STATUS AND PERFORMANCE OF NUCLEAR POWER PLANTS

Reactor Unit Type Net
Capacity
[MW(e)]
Status Operator Reactor
Supplier
Construction
Date
First
Criticality
Date
First Grid
Date
Commercial
Date
Shutdown
Date
UCF
for
2016
PAKS-1 PWR 470 Operational PAKS Zrt AEE 1974-08-01 1982-12-14 1982-12-28 1983-08-10 90.8
PAKS-2 PWR 473 Operational PAKS Zrt AEE 1974-08-01 1984-08-26 1984-09-06 1984-11-14 80.2
PAKS-3 PWR 473 Operational PAKS Zrt AEE 1979-10-01 1986-09-15 1986-09-28 1986-12-01 100.0
PAKS-4 PWR 473 Operational PAKS Zrt AEE 1979-10-01 1987-08-09 1987-08-16 1987-11-01 92.7
Data source: IAEA - Power Reactor Information System (PRIS).
Note: Table 7 is completely generated from PRIS data to reflect the latest available information and may be more up to date than the text of the report.

Data source: IAEA — Power Reactor Information System.

There are no NPP suppliers in the country; the main components of the Paks NPP were made abroad (i.e. in Russian Federation and the Czech Republic). The main constructor was AEE (Atomenergoexport) and the main architect ERBE-EROTERV (Hungary). The manufacture of many components of the Russian Federation-designed WWERs was done in the former COMECON countries under a multilateral agreement.

The Paks NPP generated 16 054 GWh of electric energy in 2016, which represents 51.3% of the gross domestic electricity production of Hungary. This amount was generated by four units as follows: Unit 1: 4 028 GWh; Unit 2: 3 576.3 GWh; Unit 3: 4 403.8 GWh; Unit 4: 4 045.8 GWh. As far as the amount of the energy produced, 2016 provided the largest production result in the history of the power plant. The amount of electricity that has been generated by Paks NPP since the date of the first connection of Unit 1 to the grid was higher than 445.5 TWh as of the end of 2016.

FIG. 3. Map of Hungary indicating the location of Paks NPP.

2.2.2. Plant Upgrading, Plant Life Management and Licence Renewals

The Paks NPP consists of four WWER-440/213 type reactor units, originally designed to produce 1375 MWth and 440 MWe each. Earlier upgrades of the secondary circuit and turbine increased the electrical output to about 470 MWe in each unit, with no change to thermal capacity. Recently, an upgrade of the primary side was completed that increased the nominal power by 8% to 1485 MWth, resulting in about 500 MWe of power generation by each unit. The power increase is primarily reached by refined primary pressure regulation, a core control system upgrade and the use of a new type of fuel assembly. Additional modifications have been performed in certain technological components, e.g. replacing some of the MCP impellers and decreasing the initiating pressure value of the hydraulic accumulators. By the end of 2009, the uprating process was completed successfully on all four units, and 2010 was the first year they operated at the increased power level.

In order to enhance its economic and operational efficiency and to improve its position in the market, the Paks NPP began an Economical Efficiency Enhancement Programme (EEP), the principal elements of which are enhancing human resource efficiency, power uprating, optimizing maintenance and initiating service life extension.

At the end of 2008, Paks NPP submitted a lifetime extension programme to HAEA to justify the establishment of the operating conditions and safe operation beyond the design lifetime. HAEA evaluated the programme and ordered the licensee to implement the programme with certain conditions. The technical preparation activities covered the determination of the ageing effects and ageing processes requiring treatment, the status of the systems, structures and components, the evaluation of the existing ageing management programmes, and if necessary, the amendment or development of new programmes. HAEA regularly reviews and evaluates the progress reports of the lifetime extension programme. In December 2011, in compliance with the legal requirements, Paks NPP submitted the beyond design lifetime licence application for Unit 1, one year before the expiration of its licensed operating time. By the end of 2012, HAEA evaluated the licence application and the additional information and made a decision on the extension. On the basis of the review of the approximately 30 000 page long licence application, the HAEA stated that nuclear safety requirements were fulfilled and safe operation was ensured. The HAEA granted the operating licence for Units 1 and 2 for the next 20 years, subject to the periodic safety assessment of the unit. In November 2015, Paks NPP submitted the beyond design lifetime licence application for Unit 3, and obtained the licence in December 2016. In November 2016, the NPP submitted its request about the authorization of the lifetime extension for Unit 4.

In December 2015, the HAEA issued a licence to introduce a 15 month operation interval at Units 1–4 of Paks NPP, and as a preliminary measure, to implement a new type of fuel assembly with the mean enrichment of 4.7%.

2.3. Future Development of Nuclear Power

2.3.1. Nuclear Power Development Strategy

The construction of new units at the Paks site was proposed in order to meet future electricity demand.

Under Hungary’s Act on Atomic Energy, the government needs to obtain a decision in principle from the Parliament in order to start any preparatory activity that could lead to the construction of a new nuclear installation. On 30 March 2009, members of the Hungarian Parliament gave their decision in principle with more than 90% of the votes in support of it.

After this, the preparation for the construction of the new units commenced. The activities included preparations for obtaining environmental and site licences. A survey was also initiated to determine the possible suppliers for the construction of the new units and the demand for the necessary labour.

In 2012, the Board of the MVM Ltd. took a decision to establish a company to continue the tasks. The company is called MVM Paks II. Nuclear Power Plant Development Ltd. (MVM Paks II. Ltd.). The tasks of the MVM Paks II. Ltd. include the examination of all essential aspects of the construction in order to prepare the project for further decision making procedures on the construction of the new units at the Paks site.

Update of the Nuclear Safety Regulation

The HAEA started preparations for the licensing of the new units by reviewing four important areas: regulatory requirements, the licensing framework, technological and safety characteristics of possible new units and the international framework. The most important goal of HAEA is to adopt the strictest requirements set by the latest findings of science and technology. As part of the review process, the representatives of the nuclear industry, the HAEA and the Hungarian National Standard Committee agreed on the promulgation of a series of international standards specific to NPPs to cover the necessary technical fields on which Hungarian National Standards were not available. The first series of standards covering the principles of instrumentation, control room and emergency control room design, display of safety parameters, detection of leakages and loose parts in the primary circuit, neutron flux monitoring, radiation monitoring and alarming were published as Hungarian National Standards in January 2011.

According to the Act on Atomic Energy, the safety requirements for use of nuclear energy shall be regularly reviewed and modernized taking into account the achievements of sciences and international experience. Government Decree 89/2005. (V. 5.) states that the Nuclear Safety Code shall be reviewed and updated if necessary at least every five years. As a result of the review, Government Decree 118/2011. (VII. 11.) on nuclear safety requirements of the nuclear facilities and on the related legal activities was issued and came into force on 10 August 2011. The reviewed Nuclear Safety Code was published in annexes to the Government Decree.

The requirements related to the new nuclear facilities were recently developed (Volume 9. of Nuclear Safety Code) and the extended set of regulations came into force on 1 April 2012 by Government Decree 37/2012 (III. 9.).

Based on the nuclear safety codes in the field of nuclear safety, it is mandatory to present an independent technical expert’s opinion with the licence applications for plant modifications. The registration and evaluation process for these technical experts is prescribed in the Act on Atomic Energy (Act CXVI of 1996) and its implementation decree (Government Decree 247/2011).

Comprehensive modification of the Nuclear Safety Code was undertaken in the second half of 2014, covering on one hand the results of the revision of the Western European Nuclear Regulators’ Association (WENRA) requirements, and also the results of other countries’ NPP construction experience, relevant Finnish and British regulations and also the Hungarian licencing experience.

In order to be prepared for the construction of the new nuclear power plant units, Volume 3/A of the Nuclear Safety Code on nuclear safety requirements to be applied during the design was published in 2015.

In addition to the continuous development of IAEA recommendations and WENRA reference levels, the Hungarian regulations are reviewed and revised more frequently than the 5 year review period stipulated by law.

2.3.1.1. Establishment of the Contractual and Legal Framework of the New-Build Project

In January 2014, the Hungarian Government signed a bilateral agreement (Intergovernmental Agreement, IGA) with the Russian Federation on cooperation in the field of peaceful utilization of nuclear energy. The agreement was promulgated in Act II of 2014. The agreement covers, among others, the cooperation necessary for replacing the capacity of the Paks NPP, which means the planning and construction of two new nuclear units at the Paks site. In accordance with the IGA, on 28 March 2014, the Government of Hungary and the Government of the Russian Federation signed an agreement on the provision of a state credit (Financial IGA, FIGA) of maximum EUR 10 billion to Hungary to finance 80% of the project (for funding details see Section 2.3.2.). This agreement was promulgated in Act XXIV of 2014. As promulgated acts, these agreements (IGA, FIGA) are available in their full scope to the public.

A government commissioner was also assigned by Government Resolution 1358/2014 (VI. 30.) to supervise and support the project from 1 July 2014. Since November 2014, the MVM Paks II. Ltd. is under direct State ownership and is controlled by the Minister leading the Prime Minister’s Office.

After the negotiations in the second half of 2014, MVM Paks II. Ltd. and the Russian Joint Stock Company Nizhny Novgorod Engineering Company Atomenergoproekt (JSC-NIAEP) signed three implementation agreements on 9 December 2014. These agreements include (1) the engineering, procurement and construction contract (EPC) for two WWER-1200 type new nuclear units; (2) operation and maintenance support contract; and (3) nuclear fuel supply contract. In April 2015, the Euratom Supply Agency cosigned the nuclear fuel supply contract.

With the intergovernmental agreements and the implementation agreements, the project’s fundamental elements — its contractual framework — was established.

Also in 2014, the Hungarian nuclear licensing regulatory framework was revisited, modernized and made fit for instant licensing procedures. As a result, Act VII of 2015 (Project Act) was adopted by the Hungarian Parliament and the licensing and investment environment of the project was successfully created. The new rules include an extension of the staff and the remuneration of the main licensing authority (Hungarian Atomic Energy Authority, HAEA) and an increase the timeframe available for the HAEA to evaluate the construction licensing documentation from 6 months to 18+3 or 12+12+3 months.

2.3.1.2. Ongoing Licensing and Pre-construction Work

The preparations for construction of the new units are coordinated by MVM Paks II. Ltd (project company) and the Government Commissioner of the project.

Site investigation and Evaluation

As stated above before, the units will be built on the site of the Paks nuclear power plant currently in operation. Despite the in-depth knowledge of the site (which is the most explored and best known geological area of Hungary) the project company decided to conduct a thorough site investigation and evaluation programme to double check whether the most up to date geological exploration methods confirm the suitability of the site to host two new units and in order to check the site-specific data necessary for the design of the plant. In 2014, the project company obtained the site investigation and evaluation licence from the HAEA, which enables the execution of the site investigation programme. In the autumn of 2014, extensive 3D seismic exploration was carried out on a territory of about 300 km2 around the site. In spring 2016, several deep drilling activities were performed or were in progress and several shallow boreholes were drilled outside the site for the identification of the geology and the tectonics of the area. Further, several other geological mapping, other geophysical, geotechnical and hydrogeological research projects were accomplished in 2016 on the site itself and/or its surroundings.

The site licence application was submitted by the project company on 27 October 2016 to the Hungarian Atomic Energy Authority. Following this, the project company held public forums on the subject in Paks, Szekszárd and Kalocsa, and every household of the 41 settlements near the site received an 8 page informative publication. To inform the public, an informative, summarized article was published in the regional newspapers of each county, and the 8 page publication was available as an appendix in the national dailies as well. The public hearing — as part of the site licensing process — was held on 13 December 2016 in Paks, organized by the HAEA.

Environmental Licensing

In 2012, the preliminary consultation document (PCD) was sent to 30 European countries. Based on this, 11 countries have registered their intention to participate in the environmental licensing procedure (according to the Espoo Convention) for the two new units. In addition, more than 10 Hungarian non-governmental environmental organizations have been registered in order to participate in the procedure as parties. The environmental licensing procedure was initiated at the end of 2014 with the submission of the more than 2000 page environmental impact assessment study, available also in English here:

http://www.mvmpaks2.hu/hu/Kozerdeku/KozerdekuDokumentumok/KornyezetvedelmiEngedelyezes/KornyezetiHatastanulmany/Lapok/default.aspx

In the spring of 2015, an information forum series was held in 41 settlements around the Paks site with the objective to draw the attention of the public to the environmental licensing procedure and request that they submit their comments on the environmental impact assessment of the new nuclear units. On 7 May, a public hearing was held in Paks with roughly 600 participants. To meet the request of the participating countries, 9 international hearings in 7 interested countries (Austria, Croatia, Germany, Romania, Serbia, Slovenia, Ukraine) were successfully concluded in September–November 2015. With this, the bulk of the international environmental licensing procedure was completed by the end of 2015.

The project company received the first instance environmental licence issued by the Authority on 29 September 2016.

Remaining Ongoing Pre-construction Activities

In 2017 the main task will be to prepare the construction licence application and the related documentation.

TABLE 6. PLANNED NUCLEAR POWER PLANTS

Station/project name Type Capacity Expected construction start year Expected commercial year
Paks 5  WWER-1200 1200 MW(e) 2018 2025
 Paks 6  WWER-1200 1200 MW(e) 2020 2026

 

2.3.2. Project Management

The delivery of the new nuclear power plant units will be a turnkey project.

2.3.3. Project Funding

Accordig to the FIGA, the Russian Party (Russian Federation) grants for the Hungarian Party (Hungary) in the maximum amount of 10 billion EUR credit will finance 80% of the Contract Price of the EPC. 20% of the Contract Price will be financed by the Hungarian State.

Conditions of the credit line available to the Hungarian state as set out in the Financial IGA are as follows:

Disbursement period: 2014–2025;

  1. Credit amount: 80% of the agreed amount of EPC, maximum EUR 10 billion;

  2. Repayment period: 21 years;

    • Years 1–7: 25% of the whole amount;

    • Years 8–14: 35% of the whole amount;

    • Years 15–21: 40% of the whole amount;

Interest rate:

  • During the investment period: 3.95%;

  • First seven years of repayment: 4.50%;

  • Second seven years of repayment: 4.80%;

  • Third seven years of repayment: 4.95%;

  1. Commitment fee: 0.25% of the undisbursed amount from the preliminarily agreed annual credit line.

2.3.4. Electricity Grid Development

A new high voltage substation and a new double circuit overhead line of 400 kV are planned to be constructed. In order to provide increased reliability, the new substation and the substation of the existing nuclear power plant will be connected by means of two coupling lines of 400 kV.

2.3.5. Sites

The planned installation site of the new Paks II nuclear power plant units falls within the boundaries of the site of the Paks Nuclear Power Plant. The site of the Paks Nuclear Power Plant is located in Tolna County, 118 km south of Budapest. The plant lies 5 km south of the centre of Paks, 1 km west of the River Danube and 1.5 km east of Main Road No. 6.

For the new units, the site investigation and evaluation licence was issued by the Hungarian Atomic Energy Authority in 2014. Project company MVM Paks II. received an environmental licence in 2016. The site licence was issued by the HAEA in 2017.

2.4. Organizations Involved in Construction of NPPs

MVM Paks II. Nuclear Power Plant Development Ltd. (http://www.mvmpaks2.hu/).

Atomstroyexport Engineering Company (http://www.atomstroyexport.ru/wps/wcm/connect/ase/eng/).

2.5. Organizations Involved in Operation of NPPs

The MVM Paks Nuclear Power Plant Ltd. is a state owned business entity. More than 99% of the shares are held by the MVM Hungarian Electricity Ltd. (with authority granted by the state), while the remaining part is held by local authorities. The operator is the MVM Paks Nuclear Power Plant Ltd. The technical support organizations (TSO) are listed in Section 2.1.2 (Current organizational chart).

2.6. Organizations Involved in Decommissioning of NPPs

Decommissioning is not a current issue for the Hungarian nuclear facilities. Nevertheless, this question has been covered in regulations, as the final phase of the life cycle of the installations. As for all other phases, it requires a nuclear safety licence. For decommissioning, a multistep licensing procedure is established, where the first step is to obtain the authorities’ consent to terminate operation. A further requirement is a valid environmental protection licence based on an environmental impact assessment and public hearings. As in all phases of the life cycle of a facility, radiation protection authorities are involved in these licensing processes, and they licence the appropriate radiation protection programme and radiation protection organization separately.

During the dismantling, decontamination and other steps, an ongoing task of the authority is the control of the radiation situation within the facility and around it, including the monitoring of personal doses and discharges, as well as the radiation in the environment. Emergency plans have to be updated with new or likely scenarios and any necessary organizational changes must be adjusted accordingly.

The Public Limited Company for Radioactive Waste Management (PURAM) is a 100% state owned, non-profit oriented enterprise, which was established by the Director General of the HAEA on behalf of the Government. Its tasks include the final disposal of radioactive waste, the interim storage of spent fuels, the closure of the nuclear fuel cycle and the decommissioning of nuclear installations. The ownership of PURAM was transferred to the Hungarian National Asset Management Inc. at the end of 2013, but the regulatory tasks remained among the responsibilities of the HAEA.

2.7. Fuel cycle Including Waste Management

Fuel Cycle

Hungary has 20 000 metric tons of exploitable uranium resources and 10 000 metric tons of additional reserves. There are three areas in Hungary where uranium occurrences are known, but only one region in Mecsek Mountains has been exploited. Hungary mined uranium ore, which was processed to yellowcake at Mecsek and then shipped to the Russian Federation. Fuel cycle services were guaranteed by the former USSR when Hungary purchased Soviet reactors, including the fabrication and shipping of the fabricated fuel assemblies to Hungary, and also the return of the spent fuel to the former USSR. Hungary does not have other fuel cycle capabilities such as fuel conversion, enrichment or fabrication.

There are no reprocessing capabilities in Hungary, and no plans to develop any. Hungarian spent fuel is reprocessed in the Russian Federation and the recovered plutonium does not have to be returned to Hungary. At present Hungary has no plans for recycling plutonium as fuel.

A new type of fuel assembly with improved parameters was introduced at the Paks NPP. The enrichment of the new fuel is increased and it contains burnable poison (Gd isotope). The increased enrichment enhances the economic efficiency of the fuel cycles, while the application of the burnable poison compensates for the negative effects of the increased enrichment on the safety features of the reactors and the transport and storage devices. This change conforms with a worldwide trend. In 2010, test operation of 18 assemblies was completed following licensing in 2009. The preliminary use of the test assemblies was necessary for the validation of the design computer codes. When the test programme was finished successfully, the HAEA issued a licence for the general use of the new fuel. On this basis, the first batch of the new fuel assemblies was loaded at Unit 4 in 2010. The results of a special inspection programme showed that the behavior of the fuel assemblies is in harmony with the preliminary estimates and design requirements. The transition to the new fuel will be finished gradually during the next 4–5 years.

National Policy and National Programme on the Management of Spent Fuel and Radioactive Waste

The basis for creating the National Programme was the Parliamentary resolution 21/2015 (V.4) on the adoption of the National Policy on the management of spent fuel and radioactive waste. The National Policy defines the basic principles of the management of all radioactive waste and spent fuel produced in Hungary upon which the National Programme was developed and adopted in 2016.

Spent Fuel

According to the Hungarian–Soviet Inter-Governmental Agreement on Co-operation in the Construction of the Paks NPP, concluded on 28 December 1966, and the Protocol concluded on 1 April 1994 attached to this Agreement, the Soviet and/or Russian party undertakes to accept spent fuel assemblies from the Paks NPP in such a manner that the radioactive waste and other by-products arising from the reprocessing of such fuel are not returned to Hungary. Until 1992, the return of the spent fuel assemblies was conducted without problems, under conditions which were very favourable for Hungary, but which nevertheless deviated from normal international practice. Following the collapse of the Soviet Union, however, this method of returning spent fuel became less and less reliable. For this reason and in the interests of ensuring the undisturbed operation of the NPP, it became necessary to find an interim solution (50 years) for the storage of spent fuel assemblies.

The Spent Fuel Interim Storage Facility (SFISF) (designed by GEC Alsthom UK) at the Paks site is a “modular vault dry storage” type spent fuel storage facility which has been receiving irradiated fuel assemblies from the Paks NPP since 1997. The increase of storage capacity is in line with the demands of Paks NPP. The planned 36 vaults are assumed to be capable of storing all spent fuel until the end of the extended service life of the plant. At present, 20 vaults in 45 storage modules are ready. Beginning with vault number 17, a square arrangement is applied for the storage tubes instead of the triangular arrangement that is used in vaults 1–16; consequently, 527 storage tubes can be stored instead of the original 450. When the storage facility reaches its maximum planned capacity it will be able to store a total of 17,740 fuel assemblies within the 36 vaults.

The aforementioned data are final, yet there are plans to further increase the capacity of the vaults.

Waste Management

The basic regulation in force at present, Act CXVI of 1996 on Atomic Energy, expresses Hungary’s national policy in the application of atomic energy. Among other aspects, it regulates the management of radioactive waste and authorizes the Government and the competent Ministers to issue executive orders specifying the most important requirements in this field. The Hungarian Parliament approved the Act on Atomic Energy in December 1996; the Act entered into force on 1 June 1997. Significant amendments were made in the Act on Atomic Energy in 2013. The recent amendment was made to take into consideration the requirement of the relevant EU directive and to reformulate the task to be performed in relation with the management of spent nuclear fuel and radioactive waste. For radioactive waste repositories, the Act prescribes that Parliament’s preliminary approval in principle is required to initiate activities for preparing their establishment. From July 2014 the authority for the repositories of radioactive waste is the HAEA.

In accordance with the basic rules laid down in the Act, radioactive waste management shall not impose any undue burden on future generations. To satisfy this requirement, the long term costs of waste disposal and of decommissioning of the NPP shall be paid by the generations that enjoy the benefits of nuclear energy production and applications of isotopes. Accordingly, by the Act and its executive orders, a Central Nuclear Financial Fund was established on 1 January 1998 to finance radioactive waste disposal, interim storage of spent fuel, the closure of the nuclear fuel cycle as well as the decommissioning of nuclear facilities. The Government authorized the Director General of the HAEA to establish the Public Agency for Radioactive Waste Management; this agency has been in operation since 2 June 1998. In line with the corporate forms used in the European Union, the Public Agency for Radioactive Waste Management has been transformed, as of 7 January 2008, into the Public Limited Company for Radioactive Waste Management (PURAM).

On the basis of the Act, PURAM shall design and carry out radioactive waste management in such a way that it shall be safe during the whole duration of the activity and it shall not affect human health and the environment abroad to a greater extent than the accepted value within the country.

In the field of radioactive waste management, the following projects are underway:

(a) Disposal of high level and long lived radioactive waste

In 1995, a programme was launched for solving the problem of the disposal of high level and long lived radioactive wastes. Though there is no final decision yet on the closure of the nuclear fuel cycle, a domestic deep geological repository must be built in any case for other high level waste, including decommissioning waste. The programme focuses on investigations in the area of the Boda Claystone Formation in west Mecsek. Currently, surface based investgations are taking place, including trenching, drilling of boreholes, geological and geomorphological mapping etc. An underground research laboratory is planned to operate from 2038 to 2054, and the repository will operate from 2064.

(b) Disposal of low and intermediate level radioactive waste (L/ILW) from the Paks NPP: National Radioactive Waste Repository (NRWR) in Bátaapáti

For the disposal of low and intermediate level radioactive waste from the Paks NPP — following a country wide screening and to bolster public acceptance — explorations were carried out in the vicinity of Bátaapáti (Tolna County) (about 65 km southwest of Paks). Reflecting the results of the extensive research work carried out, the Hungarian Geological Survey declared the site as geologically suitable for housing a L/ILW geological repository. In November 2005, after a decade spent on siting investigations, the Hungarian Parliament gave its preliminary approval in principle for the construction of the repository by the Resolution of the Parliament 85/2005 (XI. 23). It is a formal requirement in accordance with the Act on Atomic Energy. Prior to the voting in the Parliament, a local referendum was held, and nearly 91% of the large number of voters (voting percentage 75%) agreed that a L/ILW repository should be established in Bátaapáti.

In addition to the already ongoing underground research activities, both the licensing procedure and the preparation for construction started in 2006. The competent authority issued the environmental licence in 2007. The construction licence for the surface part (central and technological buildings) and for 4 underground disposal chambers entered into force in 2008. By October 2008, the surface buildings of the National Radioactive Waste Repository were completed. Later, the authority granted the operating licence valid for the surface part of the facility. The operating licence allows the buffer storage of 3000 drums (with a capacity of 200 litres each) containing low and intermediate level solid radioactive waste from the Paks NPP. The first transports of waste were delivered to the facility at the end of 2008. The first underground disposal chamber of the repository was put into operation in 2012. The second disposal chamber will start operation in 2017. The third and fourth chambers were excavated in 2015.

The capacity of NRWR will meet the demand of the Paks NPP, and the underground space will be extended to make it sufficient for the whole lifetime of the Hungarian NPP.

(c) Radioactive Waste Treatment and Disposal Facility (RWTDF) in Püspökszilágy

The Radioactive Waste Treatment and Disposal Facility was built for the disposal of institutional radioactive waste. The low level, solid waste from Paks Nuclear Power Plant was transported to the repository in Püspökszilágy only as a provisional solution. At the same time the capacity of the Radioactive Waste Treatment and Disposal Facility was increased with the financial support of the power plant. The total capacity of the repository is now 5040 m3. The RWTDF is operated based on the extendable licence that is currently valid until 3 June 2019.

The results of the safety assessments, at the same time, unambiguously indicated that certain spent radiation sources may pose a risk in the distant future, after the closure of the repository in case of human intrusion. Therefore, with the aim of enhancing the long term safety of the repository (affecting, in the first place, future generations), a multi-year programme was launched in the framework of which the “critical” waste types are segregated from the recovered waste and then the rest are — as far as possible — compacted before redisposal in the vaults. By doing so, the repository — which used up its capacity in 2004 — can continue to accommodate the institutional radioactive waste from all over the country.

In order to provide the possibility of waste retrieval, it is necessary for the long term to build a large, light-structure hall which can ensure appropriate working conditions and satisfies the radiation safety and environmental protection functions necessary for the work. The documentation supporting the building licence for the light-structure building has been prepared, and the Hungarian Atomic Energy Authority has granted the building licence based on it. The building of this structure will start at the end of 2016, processing works are planned from 2019.

2.8. Research and Development

2.8.1. R&D Organizations

The legal framework for implementation of the R&D programme is established in the Act on Atomic Energy, according to which the technical support activities needed for improving the safety of the peaceful application of nuclear energy shall be financed via the HAEA. Thus, it is the responsibility of the HAEA to manage the scientific-technical support for the nuclear safety and security regulatory activities. For managing the quality of such a complex programme, the HAEA defined its basic principles and requirements for performing technical support activities. The scientific-technical support is provided by a group of scientific-technical institutions and other engineering organizations (Technical Support Organizations — TSOs). As a rule, the scientific-technical cooperation with the strategic partner TSOs (with a wide range of competency in nuclear facility operation and regulation) is based on a long term agreement accepted and signed by both the HAEA and the partner TSOs. At present there are several strategic Partner TSOs including the HAS Centre for Energy Research (CER), the Nuclear Safety Research Institute (NUBIKI) and the Institute of Nuclear Techniques of the Budapest University of Technology and Economy (BME NTI). The requested technical support from a TSO is described in a contract in which the deadline and the expected quality are further defined. In urgent regulatory matters the strategic TSO Partners — based on the above mentioned strategic agreement — provide technical support quickly and flexibly on a free of charge basis. The system of TSOs ensures that the HAEA has appropriate engineering and scientific reserve capacities to handle situations which need fast and technically correct decisions.

To efficiently harmonize TSO cooperation, the HAEA has developed a middle term R&D concept which has been regularly updated. The R&D concept assigns the main goals — the area of the support programme. The most important R&D areas are: development of the regulatory framework, support and modernization of the regulatory work, new nuclear facilities, decommissioning and radioactive waste management, development of operational safety, development of risk informed supervisory instruments, analysis of beyond design basis and severe accidents, nuclear emergency response, nuclear material accountancy and control, supervision of radioactive material, physical protection and regulatory control of radioactive waste storage facilities.

Collection of data about knowledge and competencies (so called knowledge profile) of TSOs was started in 2005, and TSOs are permanently surveyed about their competencies and cooperation affinity in 10 main areas of regulatory interest divided into 48 specific subareas. Based on the demands connected with new build units, the knowledge profile of TSOs was completely reviewed in 2015. As a result of the review the TSOs can offer their knowledge in 26 main areas which can be divided into 180 specific subareas. As a result, it can be concluded that in Hungary all major scientific-technical areas important for nuclear safety are covered by research or technical institutions.

2.8.2. Development of Advanced Nuclear Technologies

The attention of research organizations is also attracted by other nuclear systems. The Generation-4 SCWR (more accurately, its European version, HPLWR) is currently being studied in Hungary in the framework of a nationally financed project which gives a good background for participating in a European Union project with a similar aim and in several bilateral cooperation projects. The decision on constructing ITER also attracts scientists to deal with various aspects of fusion technology rather than restricting themselves to plasma physics.

The Centre for Energy Research, together with its Czech, Slovak and Polish partners, with strong technical support of CEA, started the preparatory activities to launch the ALLEGRO project for establishing a 75 MWth demonstration of gas fast reactor technology in 2010. These preparatory activities include:

  • Finalization of the design and the safety concept of the ALLEGRO reactor;

  • Clarifying fuel related problems;

  • Defining the R&D needs for starting the licensing and construction of ALLEGRO;

  • Paving the way to license ALLEGRO by the nuclear safety authorities;

  • Preparing the outline of the EIA;

  • Defining the technical details of site selection;

  • Proposing the method of site selection;

  • Defining the governance structure of the project;

  • Clarifying IPR;

  • Organizing the political support and financial support of the project.

Most of these activities will be concluded in 2014; however, R&D activities will continue in the medium and long term.

In July, 2013 four nuclear research institutes and engineering companies from central Europe’s Visegrád Group (V4) of nations decided to establish a centre of excellence for joint research, development and innovation in Generation IV nuclear reactors. The V4G4 Centre of Excellence is registered in Slovakia and managed by a steering committee and is being set up by scientific and research engineering company ÚJV Rež AS of the Czech Republic, the Academy of Sciences Centre for Energy Research (MTA EK) of Hungary, Poland’s National Centre for Nuclear Research (NCBJ) and engineering company VUJE AS of Slovakia. The preparatory phase is ongoing; the Centre is to be operational by 2020.

2.8.3. International Cooperation and Initiatives

In Hungary both the licensees and the HAEA maintain wide ranging relations with various international organizations, with other countries and institutions involved in the design, manufacture, installation and operation of nuclear facilities and research institutes.

These relations serve as a means of exchanging knowledge and experience. The fact that Hungarian experts are held in high esteem internationally is demonstrated by their active role on different committees, with many of them being board members of international organizations or invited as experts.

Hungary has been a Member of the International Atomic Energy Agency since 1957 and the OECD Nuclear Energy Agency since 1996.

Hungary has bilateral international agreements with Australia, Austria, Canada, Croatia, the Czech Republic, Germany, Romania, the Republic of Korea, the Russian Federation, Serbia, Slovakia, Slovenia, Ukraine, the United States of America and Viet Nam.

There are several memoranda of understanding on cooperation and mutual information exchange concluded by HAEA with other regulatory authorities, i.e. those of the Czech Republic, Finland, Romania, the Slovak Republic, the Republic of Belarus, the Russian Federation, Turkey, Ukraine and the United States of America.

Regional programmes organized by the European Union and the IAEA play an important role in the cooperation between the regulatory authorities of neighbouring countries. Moreover, the HAEA is taking part in quadrilateral cooperation including the Czech Republic, Slovak Republic and Slovenia.

The HAEA takes part in several international cooperation activities including:

International Organizations

International Atomic Energy Agency (IAEA);

  • Nuclear Energy Agency of the Organization for Economic Co-operation and Development (OECD/NEA);

  • European Atomic Energy Community (EURATOM);

  • Comprehensive Nuclear-Test-Ban Treaty Organization (CTBTO).

Multilateral Cooperation

Nuclear Suppliers Group (NSG);

  • Zangger Committee.

Nuclear Forums

Western European Nuclear Regulators’ Association (WENRA);

  • European Safeguards Research and Development Association (ESARDA);

  • European Nuclear Security Regulators’ Association (ENSRA);

  • Heads of European Radiological Protection Competent Authorities (HERCA);

  • European Association of Competent Authorities for Safe and Sustainable Transport of Radioactive Material (EURACA).

The Paks NPP is a member of several international bodies of major importance including the World Association of NPP Operators (WANO), the WWER-440 operators’ club, the WWER users’ group, the International Nuclear Safety Programme (the so-called Lisbon Initiative) and the Nuclear Maintenance Experience Exchange (NUMEX).

MVM Paks II. Ltd. is also a member of the World Association of NPP Operators (WANO).

The Public Limited Company for Radioactive Waste Management (PURAM) takes part in the activities of the relevant international organizations (IAEA, OECD/NEA etc.) and maintains bilateral contacts with other companies involved in rw management in other countries.

The Hungarian Nuclear Society is a member of the European Nuclear Society (ENS), and the Health Physics Section of the Roland Eötvös Physical Society is a member of the International Radiation Protection Association.

The technical support organizations of the HAEA take part in international activities including the working groups of the OECD/NEA.

2.9. Human Resources Development

The Budapest University of Technology and Economics Institute of Nuclear Techniques (BME NTI) operates a training reactor with the nominal power of 100 kWth. Using this unique facility, the university developed special nuclear education programmes for physics and energy engineering students at BSc, MSc and PhD levels. A “Medical physics” specialization of the Physics MSc education has also been available since 2010. BME offers post-graduate nuclear training for engineers working in or willing to work in the nuclear industry. Special training courses for foreign students — with different durations from 6 weeks to 3 months — are available at the institute.

There is a particle accelerator at the University of Debrecen, another source for specialists in the field of nuclear sciences.

At the Faculty of Science of Eötvös Lóránd University (ELTE), the students of the physics faculty also learn about nuclear techniques and practice at the CER.

Paks NPP

The Paks NPP has its own training organization which operates a state of the art training infrastructure. The training organization provides initial and refresher training both for its own employees and for the contractor staff. The training system is operated on the basis of the IAEA Systematic Approach to Training (SAT) system. Job specific training programmes and training materials are available for all the job positions related to nuclear safety. As part of the training infrastructure there is a full scope replica simulator for the operator training. For the training of the maintenance and technical support staff a unique Maintenance Training Center is available, this is equipped with real primary circuit equipment, like reactor vessel and its internals.

The training organization has wide cooperation in the human resource development area with national and international institutes and universities.

Hungarian Atomic Energy Authority

At the HAEA, the inspectors take part in a predefined training programme, which is reviewed annually. The training plan is divided into three parts: the training of newcomers, refresher training and specific training. The training plan also includes the utilization of results of the R&D projects.

Newcomers to the HAEA have to complete a special training course. It includes all important fields related to the HAEA responsibility areas, and also special training courses at the NPP and at the other licensees. After fulfilling the predefined training programme the newcomers have to pass the so-called inspector exam, where they analyse real events regarding the licensing, supervision and investigation process of the HAEA.

The longer term training programme contains training directions based on the knowledge profile survey and on the future projects and strategy of the HAEA, for example: bigger systems of the Paks NPP, lifetime extension at the Paks NPP, decommissioning, R&D projects, legal environment, etc.

At the initiation of the Director General of the HAEA, following thorough negotiations conducted in 2009, the representative of the leading Hungarian nuclear organizations established the Hungarian Nuclear Knowledge Management Database System on 22 June 2010 by signing a joint cooperation agreement at the headquarters of the HAEA. The main objective of the system is to collect and maintain the Hungarian made documentation of the expertise accumulated during the application of atomic energy for future generations. This continuously updated common database facilitates the sharing of knowledge and information within the nuclear community.

The code of conduct developed by the editorial committee was signed on 15 December 2010, and thus the administrative conditions for the operation of the knowledge management database were established besides the technical provisions. Consequently, the ordinary use of the “common electronic repository” of the Hungarian nuclear community started in 2010. The uploading of documents is still ongoing; the database currently consists of approximately 9000 documents.

2.10. Stakeholder Involvement

In the area of stakeholder involvement, the Hungarian Atomic Energy Authority is:

  • Arranging public hearings in all facility-level licensing procedures to ensure transparency and openness;

  • Organizing “About Atomic Energy — to everyone” student conferences, forums and meetings for other authorities, for licensees;

  • Publishing a wide range of documents on its website, such as country reports (Convention on Nuclear Safety, Joint Convention), annual report, legal framework, guiding documents and all relevant news and events;

  • Running a Facebook profile.

Public Relations and information on the Paks Nuclear Power Plant

The MVM Paks NPP Ltd. frequently informs the public of events that happen at the power plant via press releases. The press releases are also uploaded together with other information materials to the Hungarian and English website of the NPP (http://www.atomeromu.hu and http://www.atomeromu.hu/en/Lapok/default.aspx).

MVM Paks NPP Ltd. has a Visitors’ Centre and a Nuclear Energetics Museum. The Visitors’ Centre was established in 1995 and welcomes over 25 000 visitors yearly. The number of visitors in the Nuclear Energetics Museum, which has been running since 2012, exceeds 14 000 per year. Thanks to its programmes, the nuclear power plant remains a popular tourist destination.

The numbers of followers of the Facebook page of the Paks NPP increase year by year; the activity of the followers is exceptional both within and outside the industry.

Paks NPP organizes an “open day” annually, which is very popular for participants.

Public Relations and information of the Paks II. project

The project company continued intensive communication regarding the site licensing in 2016. In addition, the project company reported regularly on its web site and social media platforms on the investment’s developments, events and on its web page in fulfilment of its disclosure obligations. The population next to the site receives updated information about developments in the Paks II. project. Among the local and regional media content, there has always been information about the project company’s press conferences and the latest events regarding the investment.

To inform the public — beyond the communication regarding the site licensing — the company’s informative ads and PR articles were published in national media, presenting the importance of nuclear energy and the Paks II. project, and at the end of 2016 the project company published an article summarizing the developments in 2016 for Paks II. in national county dailies.

In the Paks NPP’s Visitor’s Centre an information corner about the new nuclear power plant units was formed and has been available since September 2016.

Public relations and stakeholder involvement of the Public Limited Company for Radioactive Waste Management

The primary purpose of the communication work of PURAM is to obtain, retain and reinforce the confidence and acceptance of the public to ensure that the existing or planned facilities can safely serve, for many long decades, for the benefit of the country.

The regional communication task of the Company is to keep contact with and inform the stakeholders who live near to the facilities. Thanks to the successful cooperation between PURAM and the local associations of the municipalities, the Company receives help in organising public events, school competitions or local newspapers.

The other part of the communication strategy focuses on the national and international relationships. PURAM has a showroom in Paks, next to the Spent Fuel Interim Storage Facility and a Visitors’ Centre in Bátaapáti, on the site of the National Radioactive Waste Repository, where the Company also hosts civil and expert visitors.

PURAM has several brochures, publications and web site news stories, which also give widespread information about the activities of the Company. Additionally, PURAM organizes public opinion polls every two years, which can help to generate useful consequences and feedback about the general attitudes of the Hungarian public.

3. NATIONAL LAWS AND REGULATIONS

3.1. Regulatory Framework

3.1.1. Regulatory Authority(ies)

Before 1991, the Hungarian Atomic Energy Commission (HAEC) managed most of the nuclear aspects related to international relations, preparation for legislation, internal relations, and nuclear regulatory and licensing activities. The scope of activities and responsibilities of the HAEC were redefined in a Government Decree, which came into force on 1 January 1991. The HAEA was established as a new, nationwide central state administered organization under the supervision of its President of the HAEC. The revised Act on Atomic Energy adopted at the end of 1996 (Act CXVI of 1996 on Atomic Energy) and its Decrees on Implementation introduced further changes in the scope of authority and organizational structure of the national regulatory bodies related to nuclear safety.

According to the above mentioned changes in responsibilities, the licensing of nuclear facilities became the responsibility of HAEA. In addition, the regulatory control over certain construction, technical radiation protection and nuclear accident prevention issues was also transferred into the scope of the authority of the HAEA.

Hungary’s accession to the European Union required further strengthening of the regulatory bodies’ independence. To this end, the Parliament amended the Act on Atomic Energy in 2003. Pursuant to this amendment, the operation of the HAEC was discontinued and one of the ministers of the Government appointed by the Prime Minister — currently the Minister of National Development — was given the task to supervise the HAEA. The role of the Director General of the HAEA became more significant: he or she is responsible for giving an annual report to the government about the safety of the domestic application of nuclear energy, instead of the chair of the HAEC. Furthermore, he or she shall participate, with the right of consultation, in the sessions of the Government when any proposal related to the scope of activity of the HAEA is considered.

The administrative duty of the nuclear safety authority comprises two types of task. On the one hand, the authority shall perform the relevant regulatory tasks and issue standards and requirements, while on the other hand, these regulations and requirements must be enforced (this is realized during the implementation of the licensing and inspection/enforcement procedures).

The supervisory responsibility of the HAEA involves the following activities: it enforces compliance with the provisions of relevant statutory regulations, ensures that the requirements of Nuclear Safety Regulations are observed and the conditions serving as a basis for regulatory licences are met, and in addition, it monitors the implementation of the measures imposed by the Authority. The HAEA also carries out analysis and assessment activities that are related to its licensing and inspection responsibilities. In some cases, the official licensing and inspection activity also entails the initiation of law enforcement measures. Enforcement activities comprise all the measures to ensure that the licensees return to compliance with the regulations in the case of deviations, and also involve those that encourage participants to avoid repeated deviations.

There was an amendment to the Act on Atomic Energy in 2005 (owing to the new general rules of the administrative regulatory procedures) which introduced continuous regulatory supervision. The supervision may be exercised through on-line computer systems connected to the authority office network. The amendment gave the definition of clients in the cases of licensing and permission. Furthermore, the deadlines of the administrative regulatory procedures were also modified for the HAEA and its coauthorities (60+30 days for equipment level licences, 180+90 days for facility level licences, 30+30 / 60+30 days for the coauthorities). In case of imminent danger, accident or emergency situation in the nuclear facility, it gave an opportunity for deviations from the procedural rules as well.

Further modification of the Act CXVI of 1996 on Atomic Energy was adopted in 2011. In Act No. CIX of 2006 on the reorganization of the governmental structure the HAEA is listed among the government offices. The scope of authority and duties of a government office are required to be regulated on the statutory level. Until 2011, the legal regulation of scope and duties was included in two different sources: the Act on Atomic Energy and the Government Decree 114/2003 on the Scope of Duties, Authority and Competence to Impose Penalties of the Hungarian Atomic Energy Authority, and on the Activities of the Atomic Energy Co-ordination Council. The modification ended the two level regulation system and moved up all the relating regulation to the statutory level. The modification also concerned the use of subsidies by municipal associations around nuclear facilities; now they may use the subsidies for information, monitoring, operation and to ensure municipal development.

According to the Act, the licensee is obliged to present an expert’s report before an administrative procedure (non-procedural expert). The amendment allocates the task of evaluation of independent nuclear experts to the Hungarian Chamber of Engineers. The Hungarian Chamber of Engineers, as an independent professional public body, can give substantive assistance to the regulatory body. The new modification of the Act defines the Design Basis Threat (DBT) and nuclear security and provides a clear basis for allocating responsibilities between the organizations involved. The Act also identifies protection functions that are the responsibility of the State. The Government is empowered by the Act to develop more detailed provisions of DBT and nuclear security in a government decree.

From 2013, the Act declares that in all facility level licensing procedures, the HAEA shall arrange public hearings to ensure transparency and openess.

From 1 July 2014 the responsibilities of the HAEA underwent several changes. According to this amendment, HAEA took over the task of regulatory oversight of the radioactive waste repositories. The Act also introduced new procedures relating to licences for site assessment and evaluation, and licences to define characteristics and to determine the suitability of the site.

HAEA took over the regulatory tasks for radiation protection. The Act VII of 2015 gave the scope of duties of radiation protection to the atomic energy oversight organization from 1 January 2016. The Act separated the regulatory tasks among the authorities. The Office of the Chief Medical Officer will remain the competent authority for radiation health issues, while the Hungarian Atomic Energy Authority will be responsible for supervision of other radiation safety matters. The purpose of the amendment is to integrate the regulatory framework for nuclear safety, radiation protection and physical protection of the peaceful use of atomic energy under the same authority. This way a single level, country wide, customer centred regulatory regime will be realized, making licensing easier, reducing the number of licensing processes per licensee, and unifying data supply to be performed by the users of atomic energy.

The Project Act furthermore transfers the responsibilities to HAEA for construction of general civil structures and buildings of nuclear facilities and radioactive waste repositories as of 1 January 2016. Lower level legislative amendments are also to enter into force on 1 January 2016.

3.1.2. Licensing Process

The basic principles of licensing procedures for NPPs, and the authorities taking part in licensing procedures, are regulated by Chapter III of the Act on Atomic Energy. To establish a new NPP or a new NPP unit, the preliminary consent in principle of Parliament is required for starting preparatory work, whereas to establish ownership of a NPP that is in operation or to transfer the right of operation, the consent in principle of the Government is required. In concordance with regulations in force, a licence shall be obtained from the authorities for all phases of operation (siting, construction, commissioning, operation, decommissioning) during the lifetime of a NPP. Moreover, a separate licence shall be obtained for all plant level or safety related equipment level modifications. Within the licensing procedures, technical aspects are enforced by legally delegated authorities. The Authority shall take account of opinions of legally delegated special authorities. When the installation of a new NPP is being considered, the precondition for launching the licensing procedure is the existence of an environmental protection licence. During the licensing procedure the Licencee prepares a preliminary environmental impact study. The environmental protection authority then sends the preliminary impact study to the relevant authorities to seek the opinion of authorities of potentially affected areas who — in turn — expose it to public view. The environmental protection authority, if it does not reject the detailed environmental impact study that has been submitted, shall subsequently hold a public hearing. Based on the detailed environmental impact study and on any responses received, the environmental protection authority may issue an environmental protection licence for the construction and operation of the plant.

The safety related licensing of a nuclear installation takes place after the environmental licensing. The environmental protection authority plays the role of special authority in the course of licensing a nuclear installation. During the licensing of installations and equipment, and the licensing of their modifications, the contributing procedure of the environmental protection special authority provides the possibility for the civil organizations to act as clients. The decisions of the nuclear safety authority are made public. Those licences to be issued based on Act CX. of 2001 on Electric Energy are also required for establishing and operating a nuclear plant. Licences are valid for fixed periods; on request and provided that the necessary requirements are fulfilled, they may be extended. A licensee can appeal against the decisions of the Authority. It has the right to appeal in court.

Every ten years a periodic review of the safety of the NPP is performed on the basis of a comprehensive, predefined programme known as the Periodic Safety Review. Any decision on the further validity and conditions of the operating licence is made within the framework of the review. For certain facilities, beyond the regulatory licensing procedure, the Act on Atomic Energy prescribes higher approval as well.

3.2. Main National Laws and Regulations in Nuclear Power

Main National Laws and Decrees
Act CXVI (1996) on Atomic Energy (Nuclear Law, establishing responsibilities for different areas).

Government Decree 227/1997. (XII. 10.) on the type, conditions and sum of the liability insurance or other liability financial coverage concerning atomic damage (Civil nuclear liability).


Law-decree 9 of 1972 on the promulgation of the agreement concluded between the Hungarian People’s Republic and the International Atomic Energy Agency for the application of safeguards in connection with the Treaty on the Non-Proliferation of Nuclear Weapons, signed in Vienna on 6 March 1972.

Act XC of 1999 on the confirmation and promulgation of the Additional Protocol signed in Vienna on 26 November in 1998 in connection with the agreement for the application of the safeguards concerning the treaty on non-proliferation of nuclear weapons, concluded between the Republic of Hungary and the International Atomic Energy Agency and signed in Vienna on 6 March 1972.

Decree of the Minister of transport, telecommunication and energy 11/2010. (III.4.) KHEM on the rules of accountancy for and control of radioactive materials, and on the corresponding data provisions (implementing IAEA safeguards).

Government Decree 144/2011. (VII. 27.) on the regulation of international transfer of nuclear and nuclear dual use items (import and export controls of nuclear material and items).

Law-decree 8 of 1987 on the promulgation of the convention on physical protection of nuclear materials (security principles, including physical protection of nuclear material and facilities and protection of sensitive information).

Regulations related to the planned new nuclear units at Paks
Act II of 2014 on the promulgation of the agreement about the cooperation in the field of peaceful utilization of nuclear energy between the Hungarian Government and the Government of the Russian Federation (IGA).
Act XXIV of 2014 on the promulgation of the agreement about the state loan provided to the Hungarian Government in order to finance the construction of the nuclear power plant in Hungary between the Hungarian Government and the Government of the Russian Federation (Financial IGA).
Act VII of 2015 on the project on the sustainment of Paks NPP and on the modification of related regulations.


Main Regulations in the field of Nuclear Power:
Government Decree 112/2011. (VII. 4.) on the scope of activities of the Hungarian Atomic Energy Authority in connection with its international obligations including the European Union, its authority and penalizing rights, the assignments of its coauthorities and on the Scientific Committee assisting the HAEA’s activity (regulation for establishing an authorization system, responsibilities of the operator, inspection and enforcement).

Governmental Decree 118/2011 (VII.11.) on the nuclear safety requirements for nuclear facilities and the procedures of the Hungarian Atomic Energy Authority in nuclear safety regulatory matters.

Annex No.1: Nuclear Safety Code Volume 1, Authority procedures applied to nuclear facilities.

Annex No. 2: Nuclear Safety Code Volume 2, Management systems of nuclear facilities.

Annex No. 3: Nuclear Safety Code Volume 3, General requirements for the design of nuclear power plants.
Annex No. 3a: Nuclear Safety Code Volume 3a.
Design reguirements for nuclear power plants.

Annex No. 4: Nuclear Safety Code Volume 4, Operational safety requirements of nuclear power plants.

Annex No. 5: Nuclear Safety Code Volume 5, Design and operation of research reactors.

Annex No. 6: Nuclear Safety Code Volume 6, Design and operation of spent fuel storage facilities.

Annex No. 7: Nuclear Safety Code Volume 7, Site assessment of nuclear facilities.

Annex No. 8: Nuclear Safety Code Volume 8, Decommissioning of nuclear facilities.

Annex No. 9: Nuclear Safety Code Volume 9, Requirements for the construction of new nuclear facilities.

Annex No. 10: Definitions of nuclear safety codes.

Decree of the Minister of Health 16/2000. (VI. 8.) on the execution of certain provisions of Act CXVI of 1996 on Atomic Energy associated with radiation protection (radiation protection, including protection of workers public and environment).

Government decree 215/2013. (VI. 21.) on the designation, activity and funding of the organization performing certain tasks in relation with radioactive waste and spent fuel (radioactive waste and spent fuel management, including storage and disposal, decommissioning, including funding and institutional control of mining and milling).

Government Decree 190/2011. (IX. 19.) on physical protection requirements for various applications of atomic energy and the corresponding system of licensing, reporting and inspection (physical protection).

Act LXXXI of 2015 on the promulgation and inland application of Appendixes “A” and “B” of the European Agreement about the International Public Road Transportation of Dangerous Goods.

Decree of the Minister of National Development 51/2013. (IX.6.) on the transportation, carriage and packaging of spent nuclear fuel.

Decree of the Minister of Transportation, Telecommunication and Water 14/1997. (IX. 3.) on the transportation, shipment and packaging of radioactive materials (transport of radioactive material).

Govt. Decree 155/2014. (VI. 30.) Korm. on the safety requirements for facilities ensuring interim storage or final disposal of radioactive wastes and the corresponding authority activities.

Govt. decree 487/2015. (XII. 30.) Korm. on the protection against ionizing radiation and the corresponding licensing, reporting (notification) and inspection system.

Govt. decree 489/2015. (XII. 30.) Korm. on monitoring radiation conditions relevant for public exposure of natural and artificial origin and on the scope of quantities obligatory to be measured.

Ministerial decree 5/2015. (II.27.) BM of the Minister of the Interior on specific fire safety requirements associated with the application of atomic energy and on the method of their enforcement in the practice of authorities.

REFERENCES

For the detailed LIST OF LEGISLATIVE ACTS governing the peaceful use of Nuclear Energy, see the HAEA (web site: http://www.oah.hu).

APPENDIX 1: MULTILATERAL AND BILATERAL INTERNATIONAL AGREEMENTS

Hungary is a party to the following multilateral international treaties:

Treaty on the non-proliferation of nuclear weapons (NPT)

Agreement between Hungary and the Agency for the Application of Safeguards in Connection with the Treaty on the Non-Proliferation of Nuclear Weapons. (The application of the Agreement is suspended as of 1 July 2006.)

Convention on the Physical Protection of Nuclear Material (CPPNM).

Convention on Early Notification of a Nuclear Accident (NOT).

Convention on Assistance in the Case of a Nuclear Accident or Radiological Emergency (ASSIST).

Revised Supplementary Agreement Concerning the Provision of Technical Assistance by the IAEA (RSA).

Vienna Convention on Civil Liability for Nuclear Damage (VC).

Joint Protocol Relating to the Application of the Vienna Convention and the Paris Convention (JP).

Convention on Nuclear Safety (NS).

Comprehensive Nuclear-Test-Ban Treaty (CTBT). (Not yet in force.)

Protocol Additional to the Agreement between the Republic of Hungary and the International Atomic Energy Agency for the application of safeguards in connection with the Treaty on the Non-Proliferation of Nuclear Weapons. (The application of the Protocol is suspended as of 1 July 2006.)

Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management. (JC).

Convention concerning international carriage by rail as amended by the Vilnius Protocol.

Agreement between the Kingdom of Belgium, the Kingdom of Denmark, the Federal Republic of Germany, Ireland, the Italian Republic, the Grand Duchy of Luxembourg, the Kingdom of the Netherlands, the European Atomic Energy Community and the International Atomic Energy Agency in implementation of Article III, (1) and (4) of the Treaty on the Non-Proliferation of Nuclear weapons.

Amendment to the the Convention on the Physical Protection of Nuclear Material.

Regulation concerning the international carriage of dangerous goods by rail (RID - Appendix C to the Convention).

Agreement between the Government of Hungary, the Ministerial Cabinet of Ukraine and the Government of the Russian Federation on the transport of nuclear material between Hungary and the Russian Federation through the territory of Ukraine.

European Agreement concerning the International Carriage of Dangerous Goods by Road (ADR).

Annexed Regulations of the European Agreement concerning the International Carriage of Dangerous Goods by Inland Waterways (ADN).

Bilateral international agreements concluded by Hungary:

Agreement on questions of mutual interest in the field of nuclear facilities between the Government of the Hungarian People’s Republic and the Government of the Republic of Austria signed at Vienna, 29 April 1987.

Agreement between the Government of the Hungarian People's Republic and the Government of Canada for cooperation in the peaceful uses of nuclear energy signed at Budapest, 27 November 1987.

Agreement on questions of mutual interest in the field of nuclear safety and radiation protection between the Government of the Republic of Hungary and the Government of the Federal Republic of Germany signed at Budapest, 26 September 1990.

Agreement on mutual notification and cooperation in the field of nuclear safety and radiation protection between the Government of the Republic of Hungary and the Government of the Czech and the Slovak Federative Republic signed at Vienna, 20 September 1990.

Agreement between the Government of the Republic of Hungary and the Government of the United States of America for cooperation in the peaceful uses of nuclear energy signed at Vienna, 10 June 1991.

Agreement for early exchange of information in the event of a radiological emergency between the Government of the Republic of Hungary and the Government of the Republic of Slovenia signed at Budapest, 11 July 1995.

Agreement for early exchange of information in the event of a nuclear accident between the Government of the Republic of Hungary and the Government of Romania signed at Bucharest, 26 May 1997.

Agreement for early exchange of information in the event of a nuclear accident and for mutual notification and cooperation in the field of nuclear safety and radiological protection between the Government of the Republic of Hungary and the Government of Ukraine signed at Budapest, 12 November 1997.

Agreement for early exchange of information in the event of a radiological emergency between the Government of the Republic of Hungary and the Government of the Republic of Croatia signed at Zaghreb, 11 June 1999.

Agreement for cooperation in the peaceful uses of nuclear energy and transfers of nuclear material between the Government of the Republic of Hungary and the Government of Australia, signed at Budapest, 8 August 2001.

Protocol between the Government of the Republic of Hungary and the Government of the Russian Federation on the conditions of transfer of spent fuel of the Paks Nuclear Power Plant of Russian origin to the Russian Federation signed at Moscow, on 29 April 2004.

Agreement between the Government of the Republic of Hungary and the Government of the Russian Federation on cooperation in the field of transfer of spent fuel of the research reactor to the Russian Federation signed at Moscow, 22 July 2008.

Agreement between the Government of Hungary and the Government of the Socialist Republic of Viet Nam on training, research, regulatory and technical cooperation in the peaceful uses of nuclear energy signed at Budapest, 16 September 2013.

Agreement between the Government of Hungary and the Government of the Republic of Korea for cooperation in the peaceful uses of nuclear energy signed at Seoul, 18 October 2013.

Agreement between the Government of Hungary and the Government of the Russian Federation for cooperation in the peaceful uses of nuclear energy, signed at Moscow, 14 January 2014.

Agreement between the Government of the Republic of Serbia and the Government of Hungary for the early exchange of information in the event of radiological emergency, signed at Beograd, 1 July 2014.

OTHER RELEVANT INTERNATIONAL TREATIES

Treaty banning nuclear weapon testing in the atmosphere, in outer space and under water.
Entry into force:
5 August 1963
Treaty of the prohibition of the emplacement of nuclear weapons and other weapons of mass destruction on the seabed and the ocean floor and in the subsoil thereof.
Entry into force:
13 August 1971
ZANGGER Committee.
Member

Improved procedures for designation of safeguards inspectors.
Accepted:
9 May 1988
Nuclear Export Guidelines.
Adopted

Acceptance of NUSS Codes.
Accepted

Nuclear Suppliers Group.
Member

Standard agreements concerning technical assistance to Hungary.
Parties:
- United Nations Organization
- International Labour Organization
- Food and Agriculture Organization of the UN
- International Civil Aviation Organization
- World Health Organization
- International Telecommunications Union
- International Atomic Energy Agency

APPENDIX 2: MAIN ORGANIZATIONS, INSTITUTIONS AND COMPANIES INVOLVED IN NUCLEAR POWER

NATIONAL NUCLEAR ENERGY AUTHORITY
Hungarian Atomic Energy Authority
H-1539 Budapest P.O. Box 676
Hungary
tel.: (+36) 1 436 4800
web site: http://www.haea.gov.hu

RELATED ACTIVITIES

NUCLEAR RESEARCH INSTITUTES
HAS Centre for Energy Research
Address: 29-33 Konkoly Thege Miklós street
1121 Budapest, Hungary
Mailing address: 1525 Budapest 114., P.O. Box 49., Hungary
tel.: (+36) 1 392-2222
fax: (+36) 1 395-9293
web site: http://www.energia.mta.hu
Institute of Nuclear Research (ATOMKI Debrecen) of the Hungarian Academy of Sciences
P.O. Box. 51
4001 Debrecen,
tel.: (+36) 52 509 200
fax: (+36) 52 416 181
web site: http://www.atomki.hu
Nuclear Safety Research Institute
(NUBIKI)
1525 Budapest, POB: 49
tel.: (+36) 1 392 2700
fax: (+36) 1 392 2701
email: nubiki@nubiki.hu
web site: http://www.nubiki.hu/
National Research
Institute for Radiobiology and Radiohygiene
P.O. Box 101,
1775 Budapest
tel.: (+36) 1 482 2000
fax: (+36) 1 482 2003
web site: http://www.osski.hu

Power Engineering and Contracting Co.
(Pöyry-EROTERV)
P.O. Box 111
1450 Budapest
tel.: (+36) 1 455 3600,
fax: (+36) 1 215 1854
http://www.etv.hu
OTHER NUCLEAR ORGANIZATIONS
MVM Paks Nuclear Power Plant Ltd.
H-7031 Paks
P.O. Box 71
tel.: (+36) 75 505 000
fax: (+36) 75 506 634, (+36) 75 506 787
web site: http://www.atomeromu.hu
MVM Paks II. Nuclear Power Plant Development Ltd.
H-7031 Paks,
P.O. Box 116.
tel.: (+36) 75 501 867
fax: (+36) 75 501 647
web site: http://www.mvmpaks2.hu/
PLC for Radioactive Waste
Management (PURAM)
H-7031 Paks,
P.O. Box 12.
tel.: (+36) 23 445 990
web site: http://www.rhk.hu
UNIVERSITIES
Eötvös Loránd University of Sciences
http://www.elte.hu
Budapest University of Technology and Economy
Institute of Nuclear Techniques
Muegyetem rkp. 9
1111 Budapest
tel.: (+36) 1 463 2523
fax: (+36) 1 463 1954
web site: http://www.reak.bme.hu/en/
University of Debrecen
Institute of Experimental Physics
Quantechnologies Research and Development Co.
Laboratory for Nuclear Safety and Techniques, NUBITEL
H-4026 Debrecen, Bem ter 18/A
H-4010 Debrecen, P.O. Box 105.
Hungary
web site: http://fizika.ttk.unideb.hu/ip/

web site: http://www.quantec.hu/




tel.: (+36) 52 415 222
fax: (+36) 52 315 087
University of Pannonia
Institute of Radiochemistry and Radioecology
Address: Egyetem St. 10. 8200 Veszprém, Hungary
8201 Veszprem, POB. 158.

web site: http://radio.mk.uni-pannon.hu/

tel./fax: (+36) 88 624 178
email: rri@almos.vein.hu

  

Report coordinator

 
Gábor Körmendi
Communication Manager
 
Hungarian Atomic Energy Authority

Address: 1036 Budapest, Fényes A. u. 4, HUNGARY
Mail: 1539 Budapest, P.O.B. 676.
tel.: (+36) 1 436 4863
fax: (+36) 1 436 4843