MEXICO

(Updated 2019)

PREAMBLE

This report provides information on the status and development of nuclear power programmes in Mexico, including factors related to the effective planning, decision making and implementation of the nuclear power programme that together lead to safe and economical operations of nuclear power plants.

The CNPP summarizes organizational and industrial aspects of nuclear power programmes and provides information about the relevant legislative, regulatory and international framework in Mexico.

Currently, Mexico has two operational units at the Laguna Verde nuclear power plant (LVNPP) site, which accounted for 6% of total electricity production in 2018. Since 2013, when a national energy reform was enacted, Mexico transformed its energy sector by recasting its governing structures and transforming the energy value chain in hydrocarbons and power generation. These changes reflect Mexico’s vision to modernize the economy and protect the environment (IEA, 2016).

The State’s strategic guidance for hydrocarbon and electric power industries, through stronger regulatory bodies and mechanisms, allows for private investment and association in the exploration and extraction of hydrocarbons, in their transport, storage and treatment, as well as in the generation and commercialization of the electric power industry, with the exception of nuclear power generation. The State promotes the protection of the environment through sustainability principles, the use of renewables and cleaner fuels, as well as measures to reduce polluting emissions from the electric power industry.

Power generation and distribution is included in the national electric system development programme (PRODESEN) 2018–2032, ensuring the efficiency, quality and sustainability of electricity and the energy security of the country. To satisfy the generation goals for clean energies, PRODESEN also addresses the diversification of the energy matrix, in which nuclear power has a relevant share. In recent years, LVNPP has taken part in the clean energy certificates scheme, including innovative instruments to integrate clean energies into power generation at lower costs and develop investment in clean electricity generation.

Regarding Mexico’s commitment to international conventions to protect people and the environment, the Mexican senate approved the accession to the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management on 7 December 2017, which entered in force on 17 May 2018. The instrument will strengthen the safe management of spent fuel from nuclear power generation and radioactive waste from research, medical or industrial facilities.

Regarding the operation of the LVNPP reactors, the 19th refuelling outage of Unit 1 took place in the first quarter of 2019 for 41.9 days. The 16th refuelling outage of Unit 2 was scheduled over 40 days, from 22 April to 31 May 2019.

1. COUNTRY ENERGY OVERVIEW

1.1. ENERGY INFORMATION

1.1.1. Energy policy

Since the national energy reform started in Mexico approximately five years ago, much has been achieved, and there are still plans to enact. Onshore oil and gas projects are expected to advance and continue to develop. Pemex as well as private companies are investing to increase production as a result of previously awarded blocks, contract migrations and additional farm-outs. Significant opportunities exist for engineering service companies with expertise in onshore infrastructure development related to oil and natural gas production, pipeline development and storage facilities.

The ongoing expansion of natural gas pipelines will open new markets for these fields and bolster the economy.

In the retail oil market, a combination of limited refining capacities and rising demand means that Mexico is currently a net importer of oil products. The oil products market is being liberalized ahead of the initial schedule. Since 2016, importation of oil products such as liquified petroleum gas, gasoline and diesel has been open to non-PEMEX entities. From January to November 2017, the retail oil market was opened, one year earlier than initially announced. Furthermore, subsidies on oil products were phased out from 2008 to 2014.

Natural gas is the second largest primary energy source in Mexico (23% of total primary energy supply in 2016, versus 63% for oil), and in the Ministry of Energy (SENER) projections to 2029, gas demand is set to grow gradually. This demand underlines the need to focus on upstream supply, storage and transportation in policy discussions. The expansion of the gas pipeline network has lagged behind the boom in gas demand. Further expanding the system is urgent, as the system has already reached saturation on several occasions. These events also highlight the need for more storage capacity in the system. Creating an integrated national gas grid also requires close cooperation between CENAGAS (the independent system operator) and private pipeline owners. In the retail natural gas market, it is critical that the gas release programme, under which PEMEX must reduce its market share to 30% by 2020, be implemented successfully. New investment for an estimated US $9.6 billion annually in electricity is essential to meet the rapid growth expected in electricity demand (IEA, 2016), allowing Mexico to reach its target of producing 35% of its electricity from clean sources by 2024, compared to 21% in 2019.

The clean energy target is to be met through a quota system that includes a clean energy certificate obligation on retail suppliers (currently, and until the third long term power auction carried out in 2017, only the Comisión Federal de Electricidad) and large consumers that do not use retail suppliers. Clean energy technologies are defined to include renewable energy, nuclear energy, efficient cogeneration and fossil fired generation with carbon capture and storage. Clean energy certificates have been granted to facilities since August 2014; they can be bought directly under bilateral contracts with generators, in the clean energy certificate market launched in 2018, or at long term auctions. Consequently, generators of clean electricity will obtain additional revenue by supplementing their sales of electricity with the sales of clean energy certificates.

A centerpiece of the reform effort is the auction system for energy, capacity and clean energy certificates, which allows investments from new players into the market on a competitive basis. The auctions offer long term contracts (15 years for energy and capacity, and 20 years for clean energy certificates) that provide a degree of stability over future cash flows for generation companies.

The Mexican clean energy auction system is a sophisticated procurement mechanism for the promotion of renewable energy. Distinctively, it seeks to capture the relative value for the system of different generation technologies by location and production profile. Projects located in higher priced areas of the country, or capable of delivering power at times of day when it is particularly needed, would receive higher revenues through the auctions and therefore attract more attention from potential investors.

Based on the two first tenders, held in 2016, the auction system is providing a substantial boost to growth of solar and wind energy, tapping Mexico’s wind and solar resources at competitive prices. It is unclear how new nuclear could compete under the current rules, which have yet to determine whether Mexican NPPs can legally participate in the electricity market, and which require the projects to be ready within three years of the auction.

Regarding costs, electricity prices for households and farmers up to a consumption cap are subsidized between 60% and 70% of the total cost. Artificially low electricity prices are likely to hamper government efforts to pursue efficiency yet should be replaced by targeted social policy measures for those in need. The relevant regulators and SENER have expressed their intent to work with the Federal Electricity Commission (CFE) on correcting these distortions. Bringing down technical and non-technical losses, which are currently higher than elsewhere in OECD countries, would reduce the need for investment in additional generating capacity, while improvements in operational efficiency in the newly unbundled CFE could significantly reduce the retail component of the cost structure. A strengthened transmission and distribution system would further help reduce losses and is also necessary to support the projected growth in demand and in supply from variable sources — solar and wind.

The reform is implemented in stages. The real time market, capacity market and clean certificates market are important elements that were introduced in 2017–2018. Most of the remaining challenges now lie in the decisiveness and speed of implementing the reform, including the necessary adjustments and improvements that are likely to be required after the first years of experience.

Climate change objectives are deeply entrenched in Mexico’s current policy making, not least in energy reform. To meet these goals, Mexico is pursuing a number of concurrent strategies setting ambitious clean energy goals, such as the National Programme for Sustainable Energy Use 2014–2018 which, among many benefits, is likely to help bring down Mexico’s carbon intensity. With regard to new policies for world energy, such measures help to cut the carbon intensity of the economy by more than half. The strong proliferation of renewables in the power sector, where around one in two gigawatts of new capacity installed to 2040 is projected to be either wind or solar, coupled with a shift to natural gas from more polluting oil, makes a major contribution to the decrease in CO2 emissions from the power sector.

Mexico is a non-Annex I Party to the United Nations Framework Convention on Climate Change (UNFCCC) and ratified the Kyoto Protocol in 2000. It is an active non-Annex I Party in conducting and communicating national inventories on greenhouse gas emissions, having submitted five national communications under the UNFCCC. Mexico hosted a successful Sixteenth Conference of the Parties (COP16) in Cancun (2010) which lay the groundwork for a successful outcome at COP21 in Paris in December 2015. Mexico’s 2020 goal (set at COP15 in Copenhagen) of “reducing its GHG [greenhouse gas] emissions up to 30% with respect to the business-as-usual scenario by 2020” was incorporated into the UN process at Cancun. The target is conditional on the “provision of adequate financial and technological support from developed countries” (Mexico’s notification to the UNFCCC, January 2010). In September 2016, Mexico ratified the 2015 Paris Agreement.

Source: Energy policies beyond IEA countries.

1.1.2. Estimated available energy

Table 1 shows estimated availabel energy sources in Mexico.

TABLE 1. ESTIMATED AVAILABLE ENERGY SOURCES

  Fossil fuels **Nuclear Renewables
Solid Liquid Gas Uranium Hydro Other renewable
Total amount in specific units* 1 211 34 933 46 309 6 714 60 1 211
Total amount in exajoules (EJ) 0.29 222.33 48.44 26.09 0.13 0.29

*Solid, liquid: in million tonnes; gas: in billion m3; uranium: metric tonnes; hydro, renewable: TW.

**Fuente: Uranium 2018 Resources, Production and Demand, OECD/NEA 2018.

Note: 1 tonne uranium = 3.88713 x 10(3 EJ.

1.1.3. Energy statistics

Table 2 shows some energy statistics for Mexico.

TABLE 2. ENERGY STATISTICS

  1980 1990 2000 2010 2015 2016* Compound annual growth rate (%) 2000–2016*
Energy consumption (EJ)**              
Solids 0.10 0.14 0.27 0.53 0.53 0.52 0.042
Liquids 2.36 2.78 3.49 3.66 3.46 3.59 0.002
Gases 1.20 1.50 2.21 3.39 3.79 4.28 0.042
Nuclear 0.00 0.03 0.09 0.06 0.12 0.11 0.013
Hydro 0.07 0.09 0.12 0.13 0.11 0.11 (0.005
Other renewables 0.30 0.36 0.49 0.51 0.54 0.54 0.006
Total 4.029 4.902 6.677 8.291 8.553 9.159 0.020
Energy production (EJ)              
Solids 0.07 0.14 0.23 0.31 0.29 0.25 0.005
Liquids 4.30 5.71 6.76 6.10 5.17 4.92 (0.020
Gases 1.47 1.48 1.78 2.20 2.04 1.78
Nuclear 0.03 0.09 0.06 0.12 0.11 0.013
Hydro 0.07 0.09 0.12 0.13 0.11 0.11 (0.005
Other/renewables 0.30 0.36 0.49 0.51 0.54 0.54 0.006
Total 6.22 7.81 9.47 9.32 8.26 7.71 (0.013

*Latest available data.

** Exajoules.

—: Data not available.

Source: Subsecretaría de Planeación y Transición Energética, 2018.

1.2. THE ELECTRICITY SYSTEM

1.2.1. Electricity system and decision making process

The electricity reform being carried out is still under way. In 2013, the energy reform required a modification of the Mexican Constitution to liberalize the generation and retailing of energy production. Less than three years later, the new wholesale electricity market was launched in January 2016. Through November 2017, three long term electricity auctions have taken place.

In the meantime, regulated electricity tariffs had already declined sharply between 2013 and 2017 in most categories. Already at the early stage of the reform, CFE accelerated investments to enable some power plants to use natural gas instead of expensive and polluting fuel oil. Within two years, from 2013 to 2015, the consumption of fuel oil dropped by almost 50%, and this trend is expected to continue.

The long term success of the reform rests on the definition of detailed rules and implementation. However, some important steps have been taken, including the publication of market rules in September 2015 and the manuals and other regulations published in 2016 and 2017.

In February 2015, CFE became a state enterprise. With this new status, CFE gained management autonomy and corporate governance similar to a private business. It is expected that, in power generation, this new status will lead to more profit oriented investment and operation decisions, in addition to increased efficiency. This lays the groundwork for improvement of CFE’s performance and for developing its potential in the new competitive environment.

In January 2016, SENER issued a decision to vertically and horizontally unbundle CFE and to enable it to participate in the market. First, CFE is vertically separated in its network, generation and retailing activities. This unbundling is limited to a legal separation, with the creation of a subsidiary for transmission, another for distribution, yet another for basic supply and several for generation. In addition, CFE may establish other subsidiaries and affiliates as deemed necessary. The unbundling remains partial as it is carried out at a legal, not ownership, level. The only ownership unbundling concerns the system operator, the National Centre of Energy Control (CENACE), which became a state agency and does not belong to CFE’s holding group.

Second, CFE was also to be horizontally unbundled through 2017 in order to constitute a total of six generating companies, including one subsidiary managing existing independent power producer contracts, and five companies to perform the activities of conventional power plants. CFE power plants were allocated to each generation company in November 2016 in a way that creates competitive conditions in each regional location of the power system and limits market power issues.

Each of the six generating companies has similar conditions of financial sustainability and profitability, a balanced mix of technologies and remaining technical lifetime. This horizontal separation of generation should lay the foundation for competition in the electricity market. To ensure a competitive market, the bids in the electricity wholesale market must be based on costs, meaning that generation companies will not be allowed to bid above their short term marginal costs in this market. Each megawatt-hour generated will be paid at the clearing price that reflects the corresponding energy, losses and congestion components at every node. This cost based market approach is designed not only to prevent the exercise of market power, but also to set scarcity prices during tight system conditions and limit the participation of the demand side in electricity markets.

The evaluation and control of marginal production costs, fuel costs and power plant efficiency are performed by SENER on the basis of information provided by CENACE. In addition, the Energy Regulatory Commission (CRE) is designing bilateral contracts to be signed between CFE’s regulated retailers and existing CFE generation. The length of these contracts will differ for each plant to allow a smooth transition to a fully implemented market. Finally, the Market Surveillance Unit at SENER hired an independent market monitor to ensure the efficient and competitive operation of the market. This function was performed by SENER during 2016, but was transferred to the CRE in 2017.

The opening of the electricity sector to a competitive market will be progressive, since independent power producers have kept their long term contracts with CFE, and the construction of new power plants by competitors will take time. Retail suppliers have the ability to buy electricity on the wholesale market from 2017 and compete with regulated tariffs.

1.2.2. Structure of the electric power sector

The structure of the electric power sector in Mexico (Fig. 1) includes several aspects discussed in detail below.

FIG. 1. Electricity market.

Generation

On 29 January 2016, the new wholesale electricity market was launched with six subsidiaries, one nuclear business unit and other private generation companies. Installed capacity in Mexico amounted to 75 685 MW, with 70.5% from conventional power plants and 29.5% from clean power plants in 2017. Installed capacity rose 3% compared to that of 2016. Clean energy installed capacity rose by 1148 MW, a surge of 5.4%, mostly due to new wind power plants (464 MW). Conventional power plants totaled 1027 MW, a 2% relative increase to 2016. Up to 57.2% of the installed capacity was owned by CFE and the remaining 42.8% by other generators. During 2017, 329 162 GWh was generated, 3.1% more than in 2016.

In 2016–2017, installed capacity in conventional technologies increased by 1027 MW, or 2%. Almost 97% of this increase is related to the expansion of combined cycle plants (810 MW) and internal combustion (182 MW), that is, an annual increase of 3% and 12.5%, respectively.

Source: PRODESEN 2018–2032.

Transmission

The entire transmission and distribution network in Mexico is owned by CFE. The transmission system is operated by the independent system operator CENACE. The overall electricity system is referred to as the national electricity system. The national interconnected system covers the main transmission network of Mexico, excluding Baja California and Baja California Sur.

Mexico benefits from an already well developed transmission network. Electricity is transmitted over long distances, which can lead to high thermal losses. Reducing network losses is therefore an important objective for dispatching. In 2017, high voltage lines of 161–400 kV covered 52 606 km and lines of 69–138 kV covered 51 059 km. Mexico City forms a central node in the high voltage network.

Source: PRODESEN 2018–2032.

Source: Synthesis of the CFE Directive Information, December 2016 (Síntesis de información directiva de CFE).

Distribution

CFE is currently responsible for electricity distribution. There are 16 geographical divisions in charge of distribution. At the end of 2017, the Mexican transmission and distribution grids covered an overall length of around 829 925 km, providing electricity to 98.7% of the Mexican population.

The Federal Secretariat of Energy (SENER)

SENER is the main body responsible for the coordination of the electricity sector. There is no split responsibility between states. The department is in charge of electricity market reform, including preparing laws and decrees, and implementation. It has also contributed to many of the initial decisions on market design and prepared the organization of long term auctions, responsibilities that will be transferred to the regulator or the system operator at a later stage of the reform. As part of the reform, CFE was transformed into a state productive enterprise that SENER will continue to control. SENER will also regulate its unbundling. The mandate of CRE does not allow it to control state owned companies.

The regulator

CRE’s main tasks are to calculate network tariffs (transmission and distribution) and the final basic supply tariffs, as well as other regulated activities (for example, operation of the basic service suppliers, the electricity system operator CENACE). CRE enjoys technical, operational and managerial autonomy and can dispose of its own revenues coming from a tax, not from the state budget.

The Ministry of Finance and Public Credit (SHCP)

SHCP has temporary powers to determine retail tariffs for the basic service suppliers until CRE issues the final determination methods for these. The unbundling of CFE and the introduction of regulated network tariffs are expected to increase transparency about the costs of CFE.

The National Centre for Energy Control (CENACE)

The electricity system operator, CENACE, will be the cornerstone of the future system organization. CENACE is an autonomous body, formerly part of CFE. It was created in 2014 and is responsible for operating the national electricity system and the wholesale electricity markets. CENACE does not own the transmission assets, which remain the property of CFE, but CENACE operates the wholesale electricity market to ensure least cost dispatch of all power plants in adherence to economic considerations such as free competition, transparency and market efficiency. Similar to independent system operators and regional transmission operators, it also plays a key role in the planning of the power system, including investments in transmission, defining capacity requirements, operating capacity markets and running the long term auctions.

1.2.3. Main indicators

Table 3 shows installed capacity, electricity production and consumption in Mexico, and Table 4 contains energy related ratios.

TABLE 3. INSTALLED CAPACITY, ELECTRICITY PRODUCTION AND CONSUMPTION

    2000 2010 2015 2016 2018 Compound annual growth rate (%)
2000–2018
Capacity of electrical plants (GW(e)) G/N      
Thermal   29.15 39.041 40.37 40.89 39.95 0.003
Nuclear   1.36 1.36 1.5 1.61 1.608 0.021
Hydro   9.62 11.5 12.02 12.09 12.125 0.007
Wind   0 0.085 0.086 0.086 0.697 0.301
Geothermal   0.85 0.965 0.874 0.874 0.873 (0.012
Other renewables*   0.006 0.006 0.006
Total   40.98 52.951 54.856 55.556 55.259 0.005
Electricity production (TWh) G/N        
Thermal   145.52 192.09 212.97 218.61 208.70 0.010
Nuclear   8.22 5.88 11.57 10.57 13.55 0.110
Hydro   33.08 36.74 30.12 29.14 30.54 (0.023
Wind   0.01 0.166 0.2 0.19 0.12 (0.038
Geothermal   5.9 6.62 6.29 6.03 5.25 (0.029
Other renewables*   0.012 0.013 0.01
Total   192.73 241.50 261.16 264.55 258.18 0.008
Total electricity consumption (TWh)   182.8 207.947 212.2 218.9

Source: Comisión Federal de Electricidad (CFE).

*Includes efficient cogeneration as a clean energy.

—: no data available.

TABLE 4. ENERGY RELATED RATIOS

1980 1990 2000 2010 2015 2016 2017
Energy consumption per capita (GJ/capita) 59.6 59.3 66.1 72.3 70.4 74.7 74.86
Electricity consumption per capita (kWh/capita) 785.4 1101.1 1539.6 1862.2 2055.5 2126.8 2103.9
Electricity production/Energy production (%) 0.04 0.05 0.07 0.11 0.14 0.15
Nuclear/Total electricity (%) 0.0 2.4 3.9 2.4 4.4 4.0 4.0
Ratio of external dependency (%) 1.54 1.59 1.42 1.13 0.97 0.84 0.76

Source: System of Energy Information/SENER (http://sie.energia.gob.mx/).

2. NUCLEAR POWER SITUATION

2.1. HISTORICAL DEVELOPMENT AND CURRENT ORGANIZATIONAL STRUCTURE

2.1.1. Overview

The National Commission for Nuclear Energy (CNEN) was established in 1956 to pave the way to introduce nuclear power and nuclear applications in Mexico. CNEN encompassed all nuclear activities in the country (exploration for uranium, nuclear research, regulation, etc.) except for the generation of electricity by nuclear means, which was the sole responsibility of CFE, and the utilization of nuclear radioisotopes. Later, CNEN was transformed into the National Institute on Nuclear Energy (INEN), which redefined its attributions but with very few changes to its responsibilities.

In 1979, INEN was replaced by three organizations: (i) The National Institute of Nuclear Research (ININ), in charge of all the aspects related to research; (ii) Mexican Uranium (URAMEX), in charge of uranium exploration and eventually uranium production; and (iii) the National Commission for Nuclear Safety and Safeguards (CNSNS), in charge of nuclear regulation and safeguards. In 1985, URAMEX was dissolved and all its functions were passed to the Secretariat of Energy.

Mexico’s interest in nuclear power dates back to the early 1960s. The first steps were taken in 1966, when a preliminary investigation of potential sites for nuclear power stations was carried out under the auspices of CFE and the CNEN. At the end of the decade, the government concluded that NPPs might play a major role in the greater energy mix. In early 1969, CFE decided to invite bids for a 600 MW(e) NPP of a proven type, and invitations to tender were sent to several manufacturers. Bids were received at the beginning of 1970, but the final decision, with up to date bids, was taken in the middle of 1972. In 1976, construction of the LVNPP was initiated, comprising two reactors of 654 MW(e) net each. The first unit went into commercial operation in July 1990 and the second in April 1995.

2.1.2. Current organizational structure

Figure 2 shows the current organizational structure of the nuclear power sector in Mexico.

FIG. 2. Current organizational chart of the nuclear power sector in Mexico.

2.2. NUCLEAR POWER PLANTS: OVERVIEW

The LVNPP reactors had an original gross capacity of 654 MW(e) per unit, but in 2010 they were upgraded to 805 for Unit 1 and 803 MW(e) for Unit 2. In 2017, the LVNPP generated 10 882.86 GWh. With the operation of the LVNPP, Mexico avoided the emission of 4.49 million tonnes of CO2 in 2018.

In 2018, the LVNPP generated 13 554.87 GWh, equivalent to 5.54% of total generation in the country, the unit capability factor was 97.49% (95.90% for Unit 1 and 99.07% for Unit 2).

2.2.1. Status and performance of nuclear power plants

As mentioned above, there is only one nuclear plant in operation in Mexico, with two boiling water reactors (BWRs). There is still a plan to add three power units towards 2029–2031, if financial means are met. PRODESEN demonstrates that 40% of the additional capacity to be installed through 2029 shall consist of clean technologies, contributing 32.552 MW. It is anticipated that up to 12% could consist of nuclear generation.

TABLE 5. STATUS AND PERFORMANCE OF NUCLEAR POWER PLANTS

Reactor Unit Type Net
Capacity
[MW(e)]
Status Operator Reactor
Supplier
Construction
Date
First
Criticality
Date
First Grid
Date
Commercial
Date
Shutdown
Date
UCF
for
2018
LAGUNA VERDE-1 BWR 777 Operational CFE GE 1976-10-01 1988-11-08 1989-04-13 1990-07-29 95.9
LAGUNA VERDE-2 BWR 775 Operational CFE GE 1977-06-01 1994-09-06 1994-11-11 1995-04-10 99.2
Data source: IAEA - Power Reactor Information System (PRIS).
Note: Table is completely generated from PRIS data to reflect the latest available information and may be more up to date than the text of the report.

Data source: IAEA — Power Reactor Information System (PRIS).
Note: Table is completely generated from PRIS data to reflect the latest available information and may be more up to date than the text of the report.

n.a.: Data not applicable.

2.2.2. Plant upgrading, plant life management and licence renewals

On 26 December 2014, LVNPP Unit 2 received permission from Mexico’s regulatory authority to operate at the extended power uprate level (120% of the original licensed thermal power); it operated during 2015 at this new power level (2 317 MW(th), 805 MW(e) and 803 MW(e)) gross capacity per unit. Yet, the new operating licence at this power level has not yet been issued by the Secretariat of Energy.

During 2017, the 18th refuelling outage of LVNPP Unit 1 was extended from an original 40 days to 48 days. In the current operating cycle 19, the unit is operating at a power level of 2 317 MW(th) and 810 MW(e). For LVNPP Unit 2, the 15th refuelling outage was planned for 43 days in 2017; the unit is operating at a power level of 2 317 MW(th) and 810 MW(e). LVNPP Unit 1 went into commercial operation in 1990 and Unit 2 followed in 1995. Both units were originally licensed for 30 years of operation. Therefore, in 2015, an application for a licence renewal of both LVNPP units, allowing their operation for 30 more years, was submitted to Mexico’s regulatory authority.

An independent spent fuel storage installation, with a capacity for storing 130 dry cask storage systems, was constructed at the LVNPP site to store fuel generated during a 60 year operational lifetime. CFE plans to store 1157 spent fuel bundles in 13 dry cask storage systems between 2018 and 2019, for which an authorization is required from the CNSNS.

As a result of the Fukushima events in March of 2011, the CNSNS requested that LVNPP take action to enhance the safety of the reactors following the below orders issued by the United States Nuclear Regulatory Commission:

  1. EA-12-049: Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events;

  2. EA-12-051: Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation;

  3. EA-13-109: Issuance of Order to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions.

Furthermore, in accordance with the international community, the CNSNS requested LVNPP to reassess its safety margins in the form of a stress test. This reassessment is set to measure the ability of LVNPP to withstand damage from hazards such as earthquakes, flooding, terrorist attacks or aircraft collisions that challenge plant safety functions and may lead to a severe accident.

To comply with the regulatory requirements requested by the CNSNS mentioned above, LVNPP is developing flexible and diverse mitigation strategies to cope with beyond design basis events caused by extreme external events such as earthquakes and hurricanes and the loss of large areas of the facility due to large fires and explosions from any cause, including beyond design basis aircraft impacts. These strategies will allow LVNPP to maintain or restore key safety functions for all reactors on-site with installed equipment, portable equipment stored on-site, or, when needed, portable equipment stored off-site. Once the strategies are implemented, LVNPP will have the capability to mitigate beyond design basis events by maintaining or restoring key safety functions like core cooling, spent fuel pool monitoring and cooling, repowering critical control and instrumentation buses, and containment integrity to prevent the release of radionuclides and combustible gases to the environment by preventing containment overpressure failure.

As part of the post-Fukushima lessons learned, severe accident management guidelines (SAMGs) are being developed by LVNPP. The SAMGs provide direction to the operators as to when actions should be taken and which strategies, of those mentioned above, will help to take actions during a severe accident scenario to terminate the progress of core damage and prevent/minimize further escalation of an accident sequence.

2.2.3. Permanent shutdown and decommissioning process

Not applicable.

2.3. FUTURE DEVELOPMENT OF NUCLEAR POWER SECTOR

2.3.1. Nuclear power development strategy

Pre-feasibility studies and analyses are being conducted on the possibility of increasing the nuclear fleet. PRODESEN demonstrated that three 1 360 MW nuclear power units could be added in 2029, 2030 and 2031, respectively. The energy sector programme 2013–2018 proposes the development of the electrical infrastructure, increasing nuclear power participation and including measures to strengthen the development of human resources, to strengthen national industrial and technological capabilities existing in the nuclear field and to strengthen the regulatory body (SENER, 2013). The plant has entered into agreements with the local authorities, the Department of Defense, the Department of the Navy and other pertinent organizations for cooperation in case of a nuclear or radiological emergency. Currently, there are studies to expand the installed capacity of LVNPP. Among the presentations of different suppliers of nuclear power technology, General Electric—Hitachi promoted different types of reactors for LVNPP, such as advanced boiling water reactors and economic simplified boiling water reactors.

2.3.2. Project management

Not applicable.

2.3.3. Project funding

Not applicable.

2.3.4. Electric grid development

Not applicable.

2.3.5. Sites

Not applicable.

2.4. ORGANIZATIONS INVOLVED IN CONSTRUCTION OF NUCLEAR POWER PLANTS

There are no NPP suppliers in the country. The main components of the LVNPP were acquired abroad. Initially, the main architect engineer for Unit 1 was the Electric Bond and Share Company. Later on, and especially for Unit 2, CFE acted as architect engineer, with the advice of the Electric Bond and Share Company and General Electric.

2.5. ORGANIZATIONS INVOLVED IN OPERATION OF NUCLEAR POWER PLANTS

LVNPP is owned by CFE, and the operation and maintenance is performed by CFE personnel. In the past, operator training occurred at several similar installations in Spain and the United States of America. Nowadays, training mainly happens locally, using the simulator which has been installed on the plant’s premises.

2.6. ORGANIZATIONS INVOLVED IN DECOMMISSIONING OF NUCLEAR POWER PLANTS

None.

2.7. FUEL CYCLE INCLUDING WASTE MANAGEMENT

Mexico has unexplored uranium resources, and the identified conventional uranium resources are approximately 4500 tonnes (NEA/IAEA Uranium 2016: Resources, Production and Demand (Red Book)). Yet, the uranium required for LVNPP BWR reloading is obtained from the world market. Uranium is currently procured as an enriched uranium product through a long term contract with NUKEM/TENEX (Russian Federation). Fuel fabrication currently is done in the United States of America by Global Nuclear Fuel — Americas.

The spent nuclear fuel is currently stored in spent fuel pools at the reactor buildings. These have been re-racked to increase the original capacity in order to accommodate the spent fuel that the reactors will produce during their expected operating life. In 2015, construction was started on an independent spent fuel dry storage installation at the LVNPP site to increase the long term storage capacity due to the potential life extension that CFE is pursuing and future expansion of Mexico’s nuclear power capacity. This installation is in the process of being licensed by Mexico’s regulatory authority.

2.8. RESEARCH AND DEVELOPMENT

The main research centres are the National Institute of Nuclear Research (ININ) and the National Institute of Power and Clean Energy (INEEL).

2.8.1. R&D organizations

ININ carries out actions for nuclear scientific and technological development, for the promotion, transfer, adaptation and assimilation of nuclear technologies. It also carries out research projects in response to energy sector needs and provides technical assistance to nuclear facilities. It develops disciplines from which the country could benefit in other topics for national development as well. The institute has qualified personnel, nationally and internationally recognized experts in several sciences and engineering areas, providing the ability to support multidisciplinary projects. Within the field of peaceful uses for nuclear energy, ININ has defined 11 research and development topics.

INEEL is committed to meeting energy needs through innovation, efficiency and continuous improvement of their processes, within the legal and regulatory framework applicable to the management of quality, sustainable development, labour equality and non-discrimination, environmental management, safety and health at work.

The objectives of INEEL include the following:

  • To carry out and promote scientific research, experimental development and technological research in order to solve the scientific and technological problems related to the improvement of the electrical industry;

  • To contribute to diffusion and implantation, within the electrical industry, of those technologies that best adapt to the economic development of the country;

  • To maintain effective relations with similar institutions in other countries and with academic and technological research institutes in the country;

  • To provide courses of specialization and update knowledge in science, technology and industrial administration in the area of the electrical industry;

  • To provide advice to CFE, the electrical manufacturing industry and engineering and consulting services related to the electrical industry;

  • To propose to the SENER and CFE applied and technological research programmes, and the corresponding plans of operation, investment and financing in the short, medium and long term;

  • To patent and license developed technologies and the results of the research obtained, as appropriate.

2.8.2. Development of advanced nuclear power technologies

None.

2.8.3. International cooperation and initiatives

Mexico is a member of the World Association of Nuclear Operators, the Institute of Nuclear Power Operations, the Electric Power Research Institute and the OECD Nuclear Energy Agency, and is an observer in the International Framework for Nuclear Energy Cooperation.

2.9. HUMAN RESOURCES DEVELOPMENT

The training provided in a year to station personnel is around 14 days of training for non-licensed personnel and around 25 days of training for licensed personnel. Annually, LVNNP has around 2000 training activities on approximately 500 different topics. Training programmes include the topics required by regulation and performance based training. Currently, Mexico is using the systematic approach to training to develop training programmes for Code of Federal Regulations Title 10 (Energy) Chapter 50 (10CFR50.120) job positions. Up to 200 workers are maintained as additional personnel (as trainees) in order to guarantee the replacement of qualified personnel due to vacation, sick leave and temporary assignments, as well as replacement according to retirement projections. At the NPP, there is a personal development pipeline for each position, so every worker has the opportunity to achieve a higher position.

The planning for the succession of senior positions is performed according to the leadership development programme (including risk assessment, assessment centre and 360 degree appraisal). Leaving the company and voluntary retirement levels are practically nil, so retirement projections are a strong basis for replacement planning.

Regarding academic training, the academic institutions with undergraduate and graduate programmes are the following: the Higher School of Physics and Mathematics of the National Polytechnic Institute, the Faculty of Engineering of the National Autonomous University of Mexico, the Division of Basic Sciences and Engineering of the Autonomous Metropolitan University — Iztapalapa Unit, the Academic Unit of Nuclear Studies of the Autonomous University of Zacatecas, the Faculty of Sciences of the Autonomous University of the State of Mexico and the Faculty of Mechanical and Electrical Engineering of the Veracruzana University, Xalapa campus.

These national and local institutions educate most of the human capital that works in the National Commission of Nuclear Safety and Safeguards, the National Institute of Nuclear Research, the Federal Electricity Commission, LVNPP, and in some positions of the Secretary of Energy. Among the topics are: nuclear engineering, nuclear energy systems, technology and safety of nuclear reactors, instrumentation, simulation and control of NPPs, nuclear reactor physics and radioprotection.

2.10. STAKEHOLDER INVOLVEMENT

CFE, through LVNPP, has been approached by non-government business groups, including the following:

  1. Business Coordinating Council: www.cce.org.mx

  2. Industrial Club: www.club.org.mx

  3. Mario Molina Center: www.centromariomolina.org

  4. Forum Chamber of Deputies: www3.diputados.gob.mx

  5. Academy of Engineering: www.ai.org.mx

During these meetings, studies and books were presented that included data and facts regarding the feasibility of the development of new plants and positive expressions of interest in the growth of installed capacity of NPPs.

Regarding professional associations, the Academy of Engineering of Mexico and the Mexican Nuclear Society are the most important organizations with involvement in the nuclear power sector. The Mexican Nuclear Society organizes every year its annual meeting with the participation of professionals of the universities, the regulatory body, the research institutes and the LVNPP and is involved with undergraduate and graduate students.

2.11. EMERGENCY PREPAREDNESS

The regulatory framework adopted and established by the CNSNS, the nuclear regulatory institution in Mexico, upon which the safety of LVNPP is guaranteed, is derived from the Code of Federal Regulations of the United States of America, the country of origin of the nuclear island.

As a requirement for its operating licence, LVNPP has an internal emergency plan (PEI, by its acronym in Spanish) and a radiological external emergency plan (PERE, by its acronym in Spanish), which have the function of safeguarding its personnel and the adjacent population in case of a radiological emergency.

PEI is the responsibility of CFE and it covers the real and potential radiological emergencies inside the nuclear plant.

The external radiological emergency plan comprises an 80 km zone around LVNPP, denoting the emergency planning zone, that is divided into two radii, one from 0 to 16 km, and the other up to 80 km, both of them with centres starting from the LVNPP reactor units. The area within the 16 km zone is called Zona Vía Pluma, and it contains defined protection actions for the population, including provided the emergency conditions, access control, population notification, radiological prophylaxis (ingestion of a stable iodine compound) and evacuation of the affected sectors. The area within the 80 km radius is called Zona Vía Ingestión, and the main activity is water and food monitoring to ensure that the necessary actions are taken to minimize the ingestion of food and liquids with radiation levels that may, in the long term, affect the health of those who live in the area, and also to ensure that the food produced in that zone is free of radiation, and that it does not leave the area.

PERE covers emergencies that could exceed LVNPP borders. This plan has written procedures on what to do, how to act and who must participate; consequently, these procedures provide instructions to follow and define actions to take. PERE’s mission is to be prepared with the response capacity to face any emergency at a regional level caused by an accident at LVNPP, which would go beyond the capabilities of the facilities, and would require the joint and organized participation of different public agencies in order to prevent or minimize radiation exposure to the ecosystem and, mainly, to protect the health and assets of the nearby population.

The state and federal levels are involved in the emergency preparedness plan in order to have the proper support in case of a nuclear emergency. This plan is coordinated by an external radiological emergency planning committee (COPERE, by its acronym in Spanish), presided over by the Department of the Interior (whose chairman plays the role of National Coordinator of Civil Protection) and a Technical Secretary.

COPERE comprises the following agencies or government departments:

  1. Department of the Interior (governance issues);

  2. Department of Defense;

  3. Department of the Navy;

  4. Department of Communications and Transport;

  5. Department of Health;

  6. Department of Energy;

  7. National Safety Commission;

  8. Federal Police;

  9. Federal Institute of Communication;

  10. Finance and Public Credit Ministry;

  11. Federal Electricity Commission;

  12. National Water Commission;

  13. Environment Protection Federal Agency;

  14. National Disaster Prevention Centre;

  15. CNSNS;

  16. Diconsa S.A. de C.V.;

  17. Veracruz State Government;

  18. Veracruz State Department of Civil Protection;

  19. Veracruz State Health Department;

  20. General Coordination of Social Communication of the Government of the State of Veracruz.

As in most plans, PERE requires the availability of sufficient and timely information in order to develop actions and make proper decisions. In order to help in the execution of the activities of PERE, each state department/agency must perform some activities, comprising a series of operation procedures according to its purpose and the state agencies that execute each action considered in the plan.

3. NATIONAL LAWS AND REGULATIONS

3.1. REGULATORY FRAMEWORK

3.1.1. Regulatory authority(s)

The CNSNS is the regulatory body responsible for the regulation and oversight of nuclear and radioactive installations and practices. In addition, it is responsible for inspecting and authorizing the fabrication, use, storage, reprocessing and transportation of nuclear fuel, nuclear and radioactive materials, and equipment containing such materials, and the processing, refurbishment, disposal and storage of radioactive waste. The regulatory authority is engaged in the licensing activities related to assessing applications for long term operation and preparing for the safety review of new reactors.

3.1.2. Licensing process

The licensing process for an NPP consists of two steps. The first step concludes with the granting of a construction permit, while the second step concludes with the issuance of a licence for commercial operation. The process starts with an application to build an NPP by the utility, which must present this application to the national regulatory body (CNSNS), along with preliminary studies of the following:

  • Siting environmental impact;

  • Quality assurance programme during construction phase;

  • Preliminary safety assessment report.

If these documents satisfy the scope required by CNSNS, the utility is required to present the technical information on the planned NPP. This information includes the construction procedures and fundamental safety systems designed to cope with the operational transients and postulated accidents. This is evaluated by the CNSNS’ technical personnel, and a set of questions is then transmitted to the utility before the pouring of any concrete at the site. In the case of LVNPP, three provisional construction permits were granted to CFE before the definitive construction permit was issued. This limited work authorization has been eliminated from the present procedure for future NPPs.

During the actual construction phase, the regulatory body inspects the construction of the NPP and has the legal authority to stop the work if the agreed standards are not met. After the evaluation of the documentation, the regulatory body can issue the technical basis to grant the construction permit, addressed to the Department of Energy, as this is the authority legally allowed to grant the permit.

At a certain stage of construction, before the start of the pre-operational test period, the utility is required to present the regulatory body with technical information related to the following:

  1. Final design of the NPP;

  2. Final site studies;

  3. Final environmental impact studies;

  4. The quality assurance programme for NPP operation;

  5. Final studies on plant performance during transients and postulated accidents;

  6. The set of operating procedures;

  7. The operations personnel training programme;

  8. The pre-operational and start-up test programme;

  9. Proposed technical specifications.

If these process documents are not clear enough in any technical subject, the regulatory body generates questions to clarify the topic. As a result of this process, the regulatory body issues the following documents:

  1. Permit to load the fuel;

  2. The set of technical specifications.

The technical basis to grant the operating licence is addressed to the Department of Energy, as according to the nuclear law this is the only authority that can grant such documents.

After the fuel load, the regulator monitors the performance of the low power test period and any change of power (0–5%, 5–10%, 10–25%, 25–50%, 50–75% and 75–100%). Engineers of the national body review the test results and evaluate possible discrepancies between the results and the acceptance criteria.

3.2. NATIONAL LAWS AND REGULATIONS IN NUCLEAR POWER

Following are the essential legal texts regulating nuclear power in the country:

  1. Constitution of Mexico, Article 27, in effect;

  2. Regulatory Law of Article 27 of the Constitution on Nuclear Matters, published in the official gazette on 4 February 1985;

  3. Law on Third Party Liability for Nuclear Damage, published in the official gazette in December 1974;

  4. Radiological Safety Regulation, published in the official gazette on 8 November 1988;

  5. General Act on Ecological Balance and Environmental Protection, published in the official gazette on 28 January 1987;

  6. Mexican Official Guidelines NOM-OI2-STPS-1993, on health and safety at work in premises where ionizing sources are handled, stored or carried, published in the official gazette on 15 June 1994;

  7. Safe Transportation of Radioactive Material Regulation, published in the official gazette on 10 April 2017.

Mechanisms in place for financing decommissioning and waste disposal include the following:

  1. For waste resulting from radioisotope applications, storage costs recuperated from the generators;

  2. For low and intermediate level radioactive waste resulting from LVNPP, storage in a repository to be located on-site;

  3. For high level radioactive waste, temporary storage at the plant until a final decision is reached.

The final disposal of radioactive waste is the responsibility of the State. In the case of waste from LVNPP, the Federal Electricity Commission will be in charge of financing its storage.

Nuclear power stations are a proven alternative in Mexico, as demonstrated by the high availability, reliability and safety indicators at LVNPP. Nuclear power is also a realistic option in order to better comply with environmental requirements that are anticipated to become stricter in the future. However, there are no immediate plans for developing new nuclear facilities due to the high initial investments required. At the moment, these are not competitive when compared with those of plants based on natural gas. The Department of Energy is responsible for nuclear fuel cycle policy and operations, and can by law authorize some of these responsibilities to public entities, such as CFE and ININ. CFE has been authorized by the Department of Energy to negotiate uranium stock purchases, uranium enrichment and fuel fabrication contracts.

An interim waste repository managed by ININ collects all low and intermediate level radioactive waste produced in medical, industrial and other radioisotope applications. This repository will be replaced by a permanent one in the future. Another interim low and intermediate level radioactive waste repository is operated by LVNPP to handle its waste. Spent nuclear fuel from LVNPP is being stored in the reactors’ pools, which have been re-racked to increase the original capacity. An independent spent fuel storage installation, with a capacity for storing 130 dry cask storage systems, has been constructed at the LVNPP site to store fuel generated during an extended 60 year operational lifetime.

REFERENCES

IEA, Mexico Energy Outlook 2016.

Comisión Federal de Electricidad (CFE) Annual Report of Federal Electricity Commission 2016.

Comisión Nacional de Hidrocarburos, Balance de gas natural.

Directorio Estadístico Nacional de Unidades Económicas. National Statistics Directory of Economic Units.

INEGI. Sistema de Cuentas Nacionales de Mexico. National Counts System.

———. Sistema de Información Energética con información de CFE, incluye Extinta LyFC.

Instituto Nacional de Estadística y Geografía (INEGI). National Institute of Statistics and Geography.

International Renewable Energy Agency. Renewable Energy Capacity Statistics 2015.

National Electricity System Development Programme (PRODESEN 2017–2031).

Presidencia de la República. Presidency of the Republic.

SENER, Energy Sector Programme 2013–2018.

----------, Prospectiva de Gas Natural 2016-2030.

----------, Prontuario del Sector Energético, 2016.

----------, Prontuario Estadística de Gas Natural y Petroquímicos/Enero 2018.

Sistema Nacional de Información Estadística y Geográfica. National System of Information of Statistics and Geography.

APPENDIX 1: INTERNATIONAL, MULTILATERAL AND BILATERAL AGREEMENTS


AGREEMENTS WITH THE IAEA
NPT and Treaty of Tlatelolco related Safeguards Agreement — INFCIRC/197
Entered into force: 14 September 1973
Improved Procedures for Designation of Safeguards Inspectors
Accepted: 27 February 1989
Supplementary Agreement on Provision of Technical Assistance by the IAEA
Entered into force: 4 June 1981
Agreement on the Privileges and Immunities of the IAEA
Entered into force: 19 October 1983

OTHER RELEVANT INTERNATIONAL TREATIES
Treaty on the Non-Proliferation of Nuclear Weapons (NPT)
Entered into force: 21 January 1969
Treaty for the Prohibition of Nuclear Weapons in Latin America (Tlatelolco Treaty)
Entered into force: 20 September 1967
Convention on the Physical Protection of Nuclear Material
Entered into force: 4 May 1988
Amendment to the Convention on the Physical Protection of Nuclear Material
Entered into force: 8 May 2016
Convention on Early Notification of Nuclear Accidents
Entered into force: 10 June 1988
Convention on Assistance in the Case of a Nuclear Accident or Radiological Emergency
Entered into force: 10 June 1988
Vienna Convention on Civil Liability for Nuclear Damage
Entered into force: 25 July 1989
Convention on Nuclear Safety
Entered into force: 24 October 1996
Nuclear Suppliers Group Guidelines
Country Member
Acceptance of Nuclear Safety Standard codes as guidelines in preparation for and application of national requirements (Mexican nuclear safety legislation is in conformity with codes)
Summary: Codes to be used by 11 July 1963
Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management
Entered into force: 17 May 2018
MULTILATERAL AGREEMENTS
Standard Agreement concerning Technical Assistance to Mexico

Parties:
United Nations Organization
International Labour Organization
Food and Agriculture Organization of the United Nations
United Nations Educational, Scientific and Cultural Organization
International Civil Aviation Organization
World Health Organization
International Telecommunications Union
World Meteorological Organization
International Atomic Energy Agency
Universal Postal Union

Transfer of enriched uranium for a research reactor
Entered into force: 18 December 1963
Parties:
Mexico
United States of America
IAEA

Lease of source material for a subcritical assembly
Entered into force: 20 June 1966
Parties:
Mexico
United States of America
IAEA

Lease of source material for a subcritical facility
Entered into force: 23 August 1967
Parties:
Mexico
United States of America
IAEA

Transfer of a training reactor and enriched uranium
Entered into force: 21 December 1971
Parties:
Mexico
Germany
IAEA

Second supply agreement for transfer of enriched uranium for a research reactor
Entered into force: 4 October 1972
Parties:
Mexico
United States of America
IAEA

Supply of uranium enrichment services
Entered into force: 12 February 1974
Parties:
Mexico
United States of America
IAEA

Second supply agreement for supply of uranium enrichment services for a second reactor unit
Entered into force: 4 June 1974
Parties:
Mexico
United States of America
IAEA

Transfer of title to natural uranium
Entered in force: 23 May 1989
Parties:
Mexico
United States of America
IAEA

Plan of operation for a UN special fund project in Latin America (eradication of Mediterranean fruit fly)
Entered into force: 29 July 1965
Parties:
Mexico
Costa Rica
El Salvador
Guatemala
Honduras
Nicaragua
Panama
UN Special Fund
IAEA

Plan of operation for a UN development programme project in Latin America
Entered into force: 31 July 1968
Parties:
Mexico
Costa Rica
El Salvador
Guatemala
Honduras
Nicaragua
Panama
UN Special Fund
IAEA

Preliminary study of a nuclear electric power and desalinization plant
Entered into force: 7 October 1965
Parties:
Mexico
United States of America
IAEA

Agreement concerning provision of a dose assurance service by IAEA to irradiation facilities in its Member States (exchange of letters)
Entered into force: 18 September 1985
Parties:
Mexico
India
Syrian Arab Republic
Argentina
Philippines
Malaysia
Belgium
Chile
Switzerland
Egypt
Hungary
Thailand
South Africa
Republic of Korea
Algeria
Netherlands
Lebanon
Singapore
Denmark
Yugoslavia
Brazil
China

BILATERAL AGREEMENTS
Agreement between the Government of the United Mexican States and the Government of Australia concerning cooperation in the peaceful uses of nuclear energy and the transfer of nuclear material
Signed on 28 February 1992; entered into force 1 October 1992
Agreement between the Government of the United Mexican States and the Government of Canada for cooperation in the peaceful uses of nuclear energy
Signed in 16 November 1994; entered into force 9 May 1995
Agreement between the Government of the United Mexican States and the Government of the Republic of Argentina for cooperation in the peaceful uses of nuclear energy
Signed on 4 July 2002; entered into force on 20 February 2013
Agreement between the Government of the United Mexican States and the Government of the Republic of Korea for cooperation in the peaceful uses of nuclear energy
Signed on 16 June 2012; entered into force on 12 July 2013
Agreement between the Government of the United Mexican States and the Government of the Russian Federation for cooperation in the peaceful uses of nuclear energy
Signed on 24 December 2013; entered into force on 28 August 2015
Agreement between the Government of the United Mexican States and the Government of the French Republic for the development of the peaceful uses of nuclear energy
Signed on 30 July 2014; entered into force on 31 July 2015

APPENDIX 2: MAIN ORGANIZATIONS, INSTITUTIONS AND COMPANIES INVOLVED IN NUCLEAR POWER RELATED ACTIVITIES — NATIONAL ENERGY AUTHORITIES

Department of Energy (SENER)
Tel.: (+52) 55 55000 6000
Av. Insurgentes Sur 890
Col. del valle
Ciudad de Mexico, C.P. 03100
Mexico D.F.
www.gob.mx/sener
Federal Electricity Commission (CFE)
Tel.: (+52) 55 52 29 44 00
Paseo de la Reforma 164
Col. Juárez
Mexico D.F.
www.cfe.mx
National Commission for Nuclear Safety and Safeguards (CNSNS)
Tel.: (+52) 55 90 41 81
Fax: (+52) 55 90 61 03
Dr. José Ma. Barragán 779
Col. Narvarte
Ciudad de Mexico, C.P. 03020
Mexico D.F.
www.gob.mx/cnsns

NUCLEAR RESEARCH INSTITUTES AND ACADEMIA
National Institute of Nuclear Research (ININ)
Tel.: (+52) 55 21 94 02
Fax: (+52) 55 90 61 03
Carretera Mexico Toluca-La Marquesa s/n, Ocoyoacac, Estado de Mexico C.P. 52750
www.gob.mx/inin/
National Institute of Power and Clean Energy (INEEL)
Tel.: (+52) 55 21 94 02
Fax: (+52) 55 21 37 98
Reforma 113,
Palmira, Morelos C.P. 62490
Temixco, Morelos
www.ineel.mx/inicio.html
National Institute of Nuclear Sciences (UNAM)
Tel.: +(52) 55 5622 4683
Fax: +(52) 55 5623 3375
Circuito Exterior S/N, Ciudad Universitaria, 04510 Coyoacan, CDMX
www.nucleares.unam.mx
Faculty of Engineering (UNAM)
Nuclear Engineering Group (GRIN)

Higher School of Physics and Mathematics (ESFM) of the National Polytechnic Institute
Building 9, Av Instituto Politécnico Nacional, San Pedro Zacatenco, Nueva Industrial Vallejo, 07738 Gustavo A. Madero, CDMX
Tel.: (+52) 55 5729 6000
Autonomous Metropolitan University, (Iztapalapa Unit)

Autonomous University of Zacatecas
Academic Unit of Nuclear Studies

Autonomous University of the State of Mexico
Faculty of Sciences

University of Xalapa
Faculty of Mechanical and Electrical Engineering


OTHER ORGANIZATIONS
Agency for the Prohibition of Nuclear Weapons in Latin America and the Caribbean (OPANAL)
www.opanal.org
Instituto Mexicano del Petróleo (IMP)
www.imp.mx

Name of report coordinator:

Mr. Hugo Capetillo Aguirre

Institution:

Laguna Verde NPP

Comisión Federal de Electricidad

Contact:

Address: Km 42.5

Carret. Fed. Cardel — Naulta

91476 Mpio, Alto Lucero, Veracruz

Mexico

Tel.: (+52) 229 989 9090; 47010

Email: hugo.capetillo@cfe.gob.mx