back

BULGARIA

(updated on Dec. 20041)

1.  ENERGY, ECONOMIC AND ELECTRICITY INFORMATION

1.1.  General Overview

Bulgaria is a country situated in the south-eastern Europe and it occupies the biggest part of the Balkan peninsula. The northern border of Bulgaria continues for 470 km on the Danube River and later in south-eastern direction to the Black Sea for about 139 km on land. In eastern direction, Bulgaria borders the Black Sea while to the south there is a 752-km long border with Turkey and Greece. To the west, the country has a border with the Former Yugoslav Republic of Macedonia and Yugoslavia. Within these borders, Bulgaria has 110 975-km2 surface, including an altitude correction.

The demographic situation in the country is characterised with a clear tendency of decrease in the population (Table 1). For the period between 1985 and 1998, the population has decreased by 719,509 people (8.0%). At the end of 1994, the population of the country numbered 8.43 million people and population density of 76 persons per square kilometre. There exists a negative trend in the change of the population, which was for 1990 -0.4%; for 1991 -1.7%; for 1992 -2.2%; and for 1993 -2.9%; see Figure 1, which shows the birth and death rates from 1992 to 2001. According to the National Institute of Statistics, the total number of the population is expected to decrease by another 320,000 (319,392) people around the year 2000, compared to 1993 (Table 2).


TABLE 1. POPULATION INFORMATION

 

 

 

 

 

 

 

Average

annual

growth

rate(%)

 

1970

1980

1990

2000

2005

2006

2000

to

2006

Population (millions)

8.5

8.9

8.7

8.1

7.7

7.7

-0.8

Population density (inhabitants/km2)

76.7

80.1

78.8

72.9

71.2

70.9

 

Urban population (% of total)

52.3

62.1

66.4

68.9

70

70.3

 

Area(1000 km2)

 

 

 

 

 

108.6

 

Source: World Bank World Development Indicator

 

figure 1

FIG. 1. Birth and Death Rate of the Bulgarian Population


Bulgaria has four distinct seasons, which create changes in the demand for energy and in particular for electricity. The annual fluctuation of Bulgarian's electric power demand has one peak period in winter, which has been identified to be the result from using electricity for space heating. The average temperature of 12°C, below which space heating is necessary, lasts about 200 days. The average temperature in November is 5.1°C, in December - 0.0°C, in January -1.8°C, in February -0.3°C, in March 4.6°C.


TABLE 2. POPULATION OF BULGARIA (1993 - 2003)


Year

Inhabitants

Total

Men

Women

1993

8,459,763

4,151,638

4,308,125

1994

8,427,418

4,129,966

4,297,452

1995

8,384,715

4,103,368

4,281,347

1996

8,340,936

4,077,501

4,263,435

1997

8,283,200

4,044,965

4,238,235

1998

8,230,371

4,014,071

4,216,300

1999

8,190,876

3.991,161

4.199.715

2000

8,149,468

3.967.423

4.182.045

2001

7,891,095

3,841,163

4,049,932

2002

7,845,841

3,816,162

4,029,679

2003

7,801,273

3,790,840

4,010,433

Source: Statistical Yearbook, National Institute of Statistics, Sofia

 

1.1.1.  Economic Indicators

Table 3 shows the historical Gross Domestic Product (GDP) data from the IAEA Energy and Economic Database (EEDB) in USD. GDP in 1998 was 21 577 billion levs at current prices, which amounts to 112 325 million levs at 1991 prices. The economic crisis of 1996 and 1997 led to a decline in real GDP, which dropped by -10.1% and -7.0% respectively. The economy picked up again in 1998, with real growth estimated at 3.5% and remained on that level. Figure 3 shows the real GDP index for 1990 through 2006, where 1990 was taken as the base year.


TABLE 3. GROSS DOMESTIC PRODUCT (GDP)

 

 

 

 

 

 

 

Average

annual

growth

rate(%)

 

1970

1980

1990

2000

2005

2006

2000

to

2006

GDP (millions of current US$)

 

20 039.6

20 726.3

12 599.4

27 187.7

31 483.0

16.5

GDP (millions of constant 2000 US$)

 

11 805.2

14 997.4

12 599.4

16 369.4

17 366.2

5.5

GDP per capita (current US$)

 

2 261.3

2 377.4

1 563.2

3 512.6

4 089.2

17.4

Source: World Bank World Development Indicator

 

figure 2

FIG. 2. Index of the Gross Domestic Product of Bulgaria

 

1.1.2.  Energy Situation

Current status

Bulgaria has very few domestic energy resources. Data in Table 4 indicate the national provision with domestic primary energy source. Proven oil and gas reserves for the country have declined for a number or years and are only about 5 million tons of oil equivalents. In fact, it is less than six months normal hydrocarbon consumption for Bulgaria. Hydropower potential is also limited since most of Bulgaria's rivers are small and the only large river, the Danube, has a small drop in altitude where it forms Bulgaria's northern border with Romania. Largely because of this constraint, hydro capacity accounts for about 17,6% (HPP - 15.1% and PSHPP - 6.5%) of the country's total installed generating capacity and an even smaller percentage of generation. The thermal power is 50.0%, and nuclear power is 28.4% of the country's total installed generating capacity.

TABLE 4. ESTIMATED ENERGY RESERVES

  Estimated energy reserves in (*) (Solid and Liquid in million tons, Uranium in metric tons, Gas in billion cubic metres, Hydro in TWhr per year)
  Solid (1) Liquid (2) Gas (3) Uranium (4) Hydro (5)
Amount 2,187 2,000 6 5,870 15,000
 

(*) Sources: 20th WEC Survey of Energy Resources, 2004 and Uranium 2005: Resources, Production and Demand ("Red Book")
(1) Coal including Lignite: proved recoverable reserves, the tonnage within the proved amount in place that can be recovered in the future under present and expected local economic conditions with existing available technology
(2) Crude oil and natural gas liquids (Oil Shale, Natural Bitumen and Extra-Heavy Oil are not included): proved recoverable reserves, the quantity within the proved amount in place that can be recovered in the future under present and expected local economic conditions with existing available technology
(3) Natural gas: proved recoverable reserves, the volume within the proved amount in place that can be recovered in the future under present and expected local economic conditions with existing available technology
(4) Reasonably Assured Resources (RAR) under < USD 130/kgU
(5) Hydropower: technically exploitable capability, the amount of the gross theoretical capability that can be exploited within the limits of current technology
Source: IAEA Energy and Economic Database.

TABLE 4.1. ENERGY INDEPENDENCE OF THE COUNTRY


 

1998

1999

2000

2001

2002

 2003*

Total

51.13

50.18

53.50

53.97

56.03

52.08

Coal

69.26

66.69

67.21

63.16

68.50

64.04

Crude oil

0.58

0.76

0.84

0.62

0.71

0.59

Natural gas

0.74

0.82

0.41

0.66

0.67

0.52

Source: Statistical Yearbook, National Institute of Statistics, Sofia.

* Preliminary data


The country has significant but very low-grade coal reserves (Table 5). The mineable reserve amount to about 2.2 billion tons including lignite, of which 2.1 billion tons are situated in the Maritsa East deposit. The production in 2001 amounted to about 27.3 million ton per year (Table 6 and Figure 4). About 90% of these reserves have a heating value of about 1500-1600 kcal/kg, which is 20-25% of the heating value of internationally traded, steam coal. In addition, these lignite reserves have very high sulphur content. Consumption of coal in Bulgaria reached its historically highest level in 1987. In that year, 40.5 million tons of coals were consumed.

Bulgaria imports almost all of its petroleum since domestic production is negligible, for example in 1997 domestic production was 27.800 tons of oil and 35 million cubic meters of gas. Imported petroleum is in the form of crude oil and is being refined in Bulgaria or directly imported as products. Typically, about 90% of petroleum are imported as crude and most of the rest is imported as heavy fuel oil. Bulgaria has three refineries located respectively at Burgas, on the Black Sea Coast, and at Pleven and Ruse on the Danube plain in the northern part of the country. The Burgas refinery accounts for about 85% of the country refining capacity with the other two refineries being very small with insertion economics.


TABLE 5. BULGARIA COAL RESERVES


 

Mineable Reserves
(million tons)

Present Production
(million tons/year)

Lifetime
(years)

Lignite

2350

28

85

Sub-bituminous coal

210

5

40

Bituminous

10

<1

40

Anthracite

1

<1

20

Source: Country Information.

 

TABLE 6. STRUCTURE OF THE COAL PRODUCTION IN BULGARIA (IN THOUSAND TONS)


 

1999

2000

2001

2002

 2003*

Brown coal

2590

2602

2646

2766

2644

Anthracite and black

122

118

110

94

51

Lignite

22586

23712

23856

23158

24604

Total

25298

26432

26611

26018

27299

Source: Statistical guide, 2002, National Institute of Statistics, Sofia.

* Preliminary data

 

figure 3

FIG. 3. Structure of the coal production in Bulgaria

 

The average annual consumption of natural gas for the past five years (1997-2001) was around 3.5 bcm, which represents a considerable decrease compared to the highest demand in the country in 1989 and 1990 (6.8 bcm). The reduction of the share of natural gas in the structure of primary energy demand, however, is far less (15.3% in 2000 compared to 18.1% in 1990). That is due to the registered total drop of demand for energy resources over the past 10 or 12 years.

In order to fulfil Decree No 162, August 20, 1992, and Decree No 56, March 29, 1994 of the Council of Ministers, the technical liquidation of the uranium mining sites have been completed. The liquidation of the processing plants has been finalised. By 2002, the projects of technical and biological re-cultivation of the uranium mining regions shall be completed, and by 2005 - sanitary treatment and safeguarding of the tailings ponds of the processing plants. Special attention is paid to the regions of Buhovo, Eleshnitza and Sliven, where the damages to the environment are most markedly pronounced, and where their effect on the population is the most direct. In parallel to performance of the re-cultivation and sanitary treatment projects, the required treatment facilities for purification of radionuclide polluted waters and monitoring networks will be built in the uranium mining regions. For performance of the projects in these regions, we depend on the co-operation and assistance of the European Union and the PHARE Programme, especially to avert the danger of cross-border water pollution. A project for engineering works for closing of uranium mines in Eleshnitza and Dospat under PHARE CBC 1999 Bulgaria-Greece programme is under implementation. Two other projects -regional monitoring network for radio-ecological monitoring in Mesta river valley and Smolian and feasibility study for the status of the uranium mines in Southern Bulgaria are going to be implemented under PHARE CBC Bulgaria-Greece programme 2001.

The energy intensity of Bulgarian Gross Domestic Product (GDP) does not appear to have decreased, with energy consumption and output roughly at the same rate. However, this pattern should start to change as the economic restructuring occurs and as relative energy prices continue to increase. Reduction of energy consumption and, therefore, of net energy imports is likely to be an important component of any improvement of Bulgaria's balance of trade. Table 7 shows the national energy data.

TABLE 7. ENERGY STATISTICS

(Energy values are in Exajoule exept where indicated) Annual Average
Growth Rate (%)
Total Energy Requirements 1970 1980 1990 2000 2003 2004 1980 to 2000 2000 to 2004
Total 0.74 1.07 1.18 0.81 0.82 0.79 -1.39 -0.36
Solids 0.36 0.39 0.38 0.27 0.30 0.29 -1.97 2.45
Liquids 0.35 0.42 0.39 0.17 0.18 0.16 -4.52 -1.71
Gases 0.02 0.15 0.23 0.14 0.12 0.12 -0.38 -3.98
Hydro < 0.01 0.01 < 0.01 0.01 0.01 0.01 -1.14 3.31
Nuclear 0.00 0.07 0.15 0.20 0.17 0.17 5.56 -3.75
Other Renewables and Waste 0.01 0.02 0.03 0.03 0.04 0.05 1.11 14.35
 
Final Energy Consumption 1970 1980 1990 2000 2003 2004 1980 to 2000 2000 to 2004
Total 0.18 0.14 0.70 0.38 0.41 0.40 5.16 1.32
Solids 0.13 0.03 0.07 0.07 0.09 0.08 4.39 5.11
Liquids .. .. 0.18 0.11 0.12 0.12 .. 1.97
Gases .. .. 0.11 0.08 0.07 0.07 .. -1.79
Electricity 0.06 0.11 0.14 0.09 0.09 0.09 -1.13 0.67
Other .. .. 0.20 0.04 0.04 0.04 .. -0.38
 
Net Energy Balance (Export-Import) 1970 1980 1990 2000 2003 2004 1980 to 2000 2000 to 2004
Total 0.470 0.751 0.744 0.367 0.389 0.394 -3.51 1.78
Solids 0.136 0.178 0.149 0.089 0.108 0.124 -3.39 8.50
Liquids 0.334 0.418 0.354 0.167 0.185 0.164 -4.49 -0.46
Gases .. 0.141 0.227 0.128 0.110 0.111 -0.51 -3.39
Other Renewables and Waste > -0.001 0.014 0.014 -0.016 -0.014 -0.004 ? -27.89
 

Source: IAEA Energy and Economic Database
 

The pattern of energy use in Bulgaria is significantly different from the West. The main area of difference is in the direct use of gas. In most western industrial countries, households and the service sector use gas. In Bulgaria, gas is almost entirely used in the industrial sector and in power generation, including district heating plants (many plants being combined heat and power or CHP plants), with a negligible amount being used in services and households. Furthermore, this pattern of usage will not change rapidly since Bulgaria lacks a distribution network for gas so that it cannot currently be supplied to most households and commercial establishments. Indirectly, of course, the household and service sectors use some gas since a small part of the electricity they consume and most of the heat supplied by district heating plants, comes from gas. Even considering this indirect use, however, the use of natural gas in Bulgaria is still heavily skewed towards the industrial sector.

1.1.3.  Bulgarian National Energy Development Strategy

The main objectives guiding the energy development are:

However, the establishment of an up-to-date and market-oriented energy sector, calls for a series of prerequisites that have been missing up to this date, namely:

Concurrent actions should be undertaken, mainly in the following areas:

The government policy in the area of energy will be based on the following principles:

The government policy in tender procedures will continue the good traditions and will rely on two main sources:


TABLE 8. EXPECTED ENERGY CONSUMPTION


 

2000

2005

2010

2015

2020

Minimum scenario

36,307

37,510

40,180

44,370

49,000

Maximum scenario

36,307

37,540

40,640

46,980

54,200

 

TABLE 9. RATIO OF EXPECTED ENERGY CONSUMPTION AND GDP


Year

Dimension

Basic scenario

Minimum scenario

1996

tones of reference fuel/million $

1978

1978

2000

tones of reference fuel/million $

1825

1927

2001

tones of reference fuel/million $

1788

1857

2005

tones of reference fuel/million $

1607

1665

2010

tones of reference fuel/million $

1256

1332

Sources: NEK Information

 

1.2.  Energy policy

The energy strategy of the Republic of Bulgaria is based on the national priorities and corresponds to the new lasting positive political and economic trends in the country as well as to the requirements of the European guidelines, the principles of market mechanisms and the Government's Programme. It is determined by the requirements for ensuring sustainable economic growth, and raising the living standard. The strategy has been developed in conformity with the natural and geographic factors determining the inherent role of the country in this region, and the optimal mix of energy resources used in accordance with the specific conditions.

The main goals of the Bulgarian energy industry are focused in energy efficiency improvement, development of the national energy system and energy market as a part of UCTE, maintaining of a high level of nuclear safety already achieved and establishment of a competitive domestic energy market.

The Bulgarian energy sector is a stable functioning system within the restructuring and adapting to the market conditions Bulgarian economy. Bulgaria is in possession of production capacities, which at the moment cover a great part of the electric power deficit in the Balkan region and provide for stable, of quality and continual electric power supply for the country. The manner of implementation of the fuel-energy balance is of particular significance for the economy of the country as well as what the technical and economic indicators of the transformation process during the production of the electric and heat power are.

The attained generalised technical and economic indicators of the energy transformation processes during the electric and heat power production outline the establishing tendencies of the energy consumption in the various sectors of the economy of Bulgaria during the past year 2003 and provide for an answer to the question to a what degree the national pursuit for conduct of a policy for energy efficiency results in the anticipated stabilisation and revival of the economic and public sector in our country.

The share of the imported energy resources referred to the general import of raw materials, materials, investment and consumer goods is about 18 %. For year 2003 the import of primary energy resources was about 1,45 times higher than the available primary resources in Bulgaria. The realised import of energy resources from our country is about 8,6 %. It should be underlined that from the commodity import the energy resources in monetary expression add only up to 19,9% for 2003. From these imported energy resources only 35.4 % are used in the energy sector for the production of electric and hear power, the structure of these resources or 7.1% of the commodity import of the country. The share of nuclear fuel is 37.6 % of the imported energy resources used in the energy sector, or 2.6% of the commodity import of the country. The import of energy resources in 2003 is presented below.


figure 4

FIG. 4. Share of imported energy resources used in Bulgarian energy sector


The energy sector is a determinative section of the Bulgarian industry, especially taking into account that its structure and development are based predominantly on imported energy sources and the domestic low-quality lignite coal. Moreover, the development of the sector is highly dependent on our geopolitical location on the Balkan Peninsula and in Europe. In this complicated stage of its development, Bulgaria unambiguously proves the willing to conform to the priorities of European Union and make the needed steps for technical and political integration with these structures.

As a country with limited energy resources, the basis of the energy sources of Bulgarian Energy Sector is well balanced - solid fuel, nuclear power, natural gas, hydro resources and utilisation of the new energy sources.

Bearing in mind that the future development of nuclear power is now more a political and societal issue than a purely technical one, Bulgarian strategy are aimed to advise citizens of the possible energy solutions in a dispassionate way, and should seek their involvement in the decision-making process.

Bulgarian energy strategy integrated the technical, political and economic considerations specific to our country and to the region, leading to definition of the preferred solution by the Bulgarian Government, through the normal democratic processes.

The possibility of using nuclear energy to improve security of energy supply and curb greenhouse gas emissions is causing more and more countries to re-evaluate their positions towards the current and potential role of nuclear power. Although the nuclear contribution is often taken for granted, all our "clean energy" options will have to be seriously considered if we are to meet our future energy needs in a way that is both sustainable and climate-friendly.

Electricity is a clean energy carrier, but to a large extent coal, oil and gas are burned to produce it. In the future, the emphasis in the power generation sector will have to be on cleaner production methods, such as wind, solar, biomass, hydro and nuclear energy. This change in emphasis will be needed to meet future electricity demand in a way that is low on greenhouse gas emissions and compatible with sustainable development. Nuclear power also generates electricity with no emission of sulphur dioxide or nitrogen oxides, key agents for acid rain and photochemical air pollution.

Nuclear energy is - and will continue to be - part of the solution to meet our energy needs and to mitigating climate change.

Nuclear power in Bulgaria contributes significantly to meet the need of electric energy of the economy and the population of the country, as well as in the region.

For the last 10 years Kozloduy NPP has been providing 40-47% of the average annual electricity produced in the Republic of Bulgaria.

The national responsibility for the safety of nuclear installation is the fundamental principle. In this context the adequate legislation for the nuclear installations safety and the management of radioactive wastes is primary responsibility of the Republic of Bulgaria and the Government.

The Republic of Bulgaria acknowledges that International Atomic Energy Agency's (IAEA) standards and approaches, as reflected notably in the IAEA Safety Fundamentals and Safety Requirements Series, constitute an internationally recognised framework which national safety requirements use as a reference level.

The important factors for Nuclear Power development as Safety based on proven and verified technologies, Spent Fuel and Waste Management, Proliferation Resistance, Environment Protection, Existing Infrastructure, Human Resources, Political Acceptance and Public Acceptance which are adequately addressed.

The supporting factors for Nuclear Power development are as follows:

For the last three years Republic of Bulgaria established the new legal basis and adopted completely new Bulgarian primary and secondary nuclear legislation in accordance with the good internationally recognised world-wide practices, and the same principles of containment and safety are applied, in conformity with the international standards and conventions of the IAEA. This heavy work already done is good real basis for the future development of the nuclear sector as an inherent part of Bulgarian energy mix.

1.3.  The Electricity System

1.3.1.  Structure of the Electricity Sector

The structure of the energy sector is shown in Figure 5.

1.3.2.  Decision Making Process

The energy policy of Bulgaria is developed and implemented by the Ministry of Energy and Energy Resources (MEER). The MEER has obligations to propose a strategy of energy development and efficient utilisation of energy and energy resources to be carried by the Council of Ministers and passed with a resolution of the National Assembly. The MEER manages the "Radioactive Waste" Fund and the "Nuclear Facility Decommissioning" Fund.

The State Energy Efficiency Agency is an executive agency to the MEER. It implements the state energy efficiency policy and develops effective measures for the improvement of energy efficiency, and promotion of the utilisation of renewable sources of energy.


figure 5

FIG. 5. Organisation of the Energy Sector


State regulation in the field of energy is carried out by the State Energy Regulatory Commission (SERC). The Commission has obligations for developing instruments and take the required steps to issue the permits and licenses provided by the Energy Act. The SERC issues licenses for construction of generation capacities, heat transmission systems, gas transmission systems, natural gas storage facilities, direct power lines and gas pipelines, and for decommissioning of energy facilities. In the process of performing its regulatory functions under the Act, the Commission is guided by several basic principles, as achievement of energy efficiency, environmental protection, etc.

1.3.3.  Main Indicators

In 2003 Bulgaria had a total of 12331 MW installed power generation capacities consisting of:

Thermal Power Plants

6613 MW or 53,6 %;

Nuclear Power Plant

2880 MW or 23,4 %;

Hydro-Power Plants

1974 MW or 16,0 %;

Pumped-Storage Hydro-Power Plant

  864 MW or 7,0 %.


4740 MW of the TPPs are public utilities, 880 MW are co-generation plants the main purpose of which is heat supply to towns, and 993 MW are co-generation plants belonging to large industrial enterprises.

The available capacity of the existing power generation sources, however, is considerably lower than their installed capacity and amounts to 9515 MW. The main causes of that difference are:

Under these circumstances, the available capacity of the existing generating capacities is:

TPP

5015 MW or 52,7 %;

of which: -fired with local coal

2365 MW or 24,9 %;

             -fired with imported coal

2650 MW or 27,8 %;

NPP

2700 MW or 28,4 %;

HPP and PSHPP

1800 MW or 18,9 %

Total

9515 MW

 

TABLE 10. ELECTRICITY PRODUCTION AND INSTALLED CAPACITY

  Annual Average
Growth Rate (%)
Electricity Generation 1970 1980 1990 2000 2003 2004 1980 to 2000 2000 to 2004
Total 19.51 34.84 40.97 40.93 41.36 40.40 0.81 -0.32
Nuclear 0.00 6.16 13.50 18.18 16.04 15.60 5.56 -3.75
Hydro 2.15 3.71 1.88 2.95 3.30 3.36 -1.14 3.31
Geothermal .. .. .. .. .. .. .. ..
Wind .. .. .. .. 0.00 < 0.01 .. ..
Other renewables .. .. .. .. .. .. .. ..
Thermal 17.36 24.96 25.60 19.80 22.02 21.44 -1.15 2.02
 
Installed Capacity 1970 1980 1990 2000 2003 2004 1980 to 2000 2000 to 2004
Total 4.12 8.71 10.95 11.09 12.00 11.98 1.21 1.94
Nuclear 0.00 1.22 2.58 3.54 2.72 2.72 5.45 -6.34
Hydro 0.82 1.87 1.97 1.88 2.52 2.57 0.03 8.08
Geothermal .. .. .. .. .. .. .. ..
Wind .. .. .. .. 0.00 < 0.01 .. ..
Other renewables .. .. .. .. .. .. .. ..
Thermal 3.30 5.62 6.40 5.67 6.76 6.69 0.05 4.20
 

Source: IAEA Energy and Economic Database  

 

Electric power production meets the electric power requirements of the country and for export. Electric power output in 2003 was 42,5 TWh and is among the highest in 1990-2003 notwithstanding the disconnection from the grid of 880 MW nuclear capacities in the end of 2002. Kozloduy NPP reached relatively high electricity output during the period considered with most efficient loading of the generating units.

The growth of electric power production after 1999 is due mainly to increased export of electric power. The average annual growth of electric power export in 1999 - 2003 was 20.7%, the relative share of export for 2003 being 15.9% of the gross electric power output in the country. In the same period electric power demand in the country increased by 2,1%.

After the commissioning of Kozloduy NPP, Unit 6 in 1993 the imports gradually decreased and exports increased. As a result of that process, after 1997 Bulgaria became one of the leading exporters of electric power in the region. At the same time domestic demand was reduced and more efficient energy utilisation was achieved.


figure 6

FIG. 6. Electricity import-export, GWh

 

figure 7

FIG. 7. Generation and demand, GWh

 

Forecast

Since 1991, the energy consumption in the Republic of Bulgaria is characterised by large fluctuations determined by the unstable and dynamic social and economic conditions. The prognosis for development of the energy consumption is based on the policy for economical stabilisation and development. The forecast was elaborated according to two scenarios: maximum and minimum, which correspond to the maximum and minimum scenarios of GNP forecast, energy efficiency measures implementation, energy demand, and export capacity in the region. The 2004 forecast, based on the Least Cost Plan developed by the National Electric Company, define the area (green area) of most probable power generation and demand forecast with planned export or technological exchange (Figure 10).

 

figure 8

FIG. 8. Energy Consumption Forecast

 

2.  NUCLEAR POWER SITUATION

2.1.  Historical Development and current nuclear power organisational structure

The nuclear development of Bulgaria started after the Geneva conference "Atoms for peace" in 1956 and was the favoured strategy of the political leadership ever since. The first step was the construction and the start of operation of IRT-2000 research reactor and a large programme of isotope applications and scientific research. Later, in 1966, an agreement was signed with the Soviet Union to deliver commercial reactors for electricity production. This agreement laid down the foundations of the Bulgarian nuclear power programme. The main articles of this agreement described the role of the reactor manufacturer and designer as well as the participation of the Bulgarian organisations and industry.

The Soviet nuclear industry was designing and supplying the nuclear island as well as the conventional part of the plants, while the architect engineer of the conventional plant and the auxiliary systems was the Bulgarian Company "Energoproekt". The Soviet safety rules and norms were supposed to be used as long as there was no special Bulgarian legislation available. During the construction and start up period, the Russian representatives at the site adopted the role of supervisors, but later they have only taken the position of manufacturer and supplier representatives. A number of Russian organisations also carried out all of the important assembly operations.

The first two units, which are a typical WWER 440/230 model, were built and put into operation for a period of less than 5 years. The second pair of reactors was completed and connected to the grid in 1980 and 1982 accordingly. By that time, the model 230 developed towards model 213, which is the reason why Units 3 and 4 incorporate many of the safety characteristics of the 213's. The further increase in the demand for electricity resulted in the construction of additional two units of 1000 MW each from the model known as WWER-1000/320. A second site was chosen in the early eighties near the city of Belene. The site was prepared with the entire necessary infrastructure to host six 1000 MW units. Completion of the first unit reached about 40% on view point construction, and 80% on delivery of equipment, in 1990, when due to lack of financial resources and some opposition from the near by communities the construction was frozen.

2.2.  Nuclear Power Plants: Status and Operations

2.2.1.  Status of nuclear power plants

Bulgaria has six nuclear power units in operation at Kozloduy of which operation started between 1974 and 1991 comprising four WWER-440 units, net capacity 408 MW(e) and two WWER-1000 units, net capacity of 953 MW(e), all imported from the former USSR (Table 14).


TABLE 12. STATUS OF NUCLEAR POWER PLANTS

Station Type Net Operator Status Reactor Construction Criticality Grid Commercial Shutdown
    Cpacity (Mwe)     Supplier Date Date Date Date Date
KOZLODUY-5 PWR   953 KOZNPP Operational AEE 09-Jul-80 05-Nov-87 29-Nov-87 23-Dec-88  
KOZLODUY-6 PWR   953 KOZNPP Operational AEE 01-Apr-82 29-May-91 02-Aug-91 30-Dec-93  
BELENE-1 PWR   953 KOZNPP Under Construction ASE 01-Jan-87        
BELENE-2 PWR   953 KOZNPP Under Construction ASE 31-Mar-87        
KOZLODUY-1 PWR   408 KOZNPP Permanent Shutdown AEE 01-Apr-70 30-Jun-74 24-Jul-74 28-Oct-74 31-Dec-02
KOZLODUY-2 PWR   408 KOZNPP Permanent Shutdown AEE 01-Apr-70 22-Aug-75 24-Aug-75 10-Nov-75 31-Dec-02
KOZLODUY-3 PWR   408 KOZNPP Permanent Shutdown AEE 01-Oct-73 04-Dec-80 17-Dec-80 20-Jan-81 31-Dec-06
KOZLODUY-4 PWR   408 KOZNPP Permanent Shutdown AEE 01-Oct-73 25-Apr-82 17-May-82 20-Jun-82 31-Dec-06

Source: IAEA Power Reactor Information System


During the 70's, a site for the construction of a second nuclear power plant was selected near the town of Belene. In 1980, the Ministry of Energy started its construction. Initially the construction of 4 units with WWER-1000/V320 reactors was envisaged with a possibility for exceeding this capacity with additional new facilities. The engineering works on the site and the construction of the infrastructure started at the end of the year 1980. The construction of unit 1 started in 1987. In the year 1991, the Belene NPP construction was halted mainly due to lack of funds. At that time the first unit was 40% complete.

In the end of 2002 Bulgarian Government took a decision to perform a feasibility studies for renewing the construction of the second Bulgarian NPP at the Belene site. Up to this moment considerable amount of work has been done for justification of the future activities on this project, including Environmental Impact Assessment Report and Feasibility Studies Report. After public discussion performed in March 2004 it was concluded that the construction of the second NPP in Bulgaria has very strong political and public support at local (more than 97%) and national level (more than 76 %).

In April 2004 Bulgarian Government approved in principal the continuation of the construction activities at Belene site. The decision is based on the conclusion that nuclear energy is the main and most efficient way to meet our future electricity needs. It also provides high reliability of electricity generation with regard to minimisation of the expenditures in energy sector, security of supply as well as implementing the international agreements on environmental protection.

According to the implementation schedule, the project will commence in 2005 and Belene NPP Unit 1 commercial operation to be started in 2010.

2.2.2.  Performance of NPPs

For the last 10 years the electricity share of KNPP in Bulgaria has been 44-46 %. In 2003, only four of the six nuclear units on Kozloduy NPP site were in operation. As compared to the record - breaking 2002 production of 20 221 719 MWh, the electricity generation in 2003 was reduced by 14,56 % and amounted to 17 278 411 MWh. Kozloduy NPP share in the 2003 gross electricity generation dropped by 6,66% as compared to the previous year. At the same time, the share of each of the Kozloduy NPP units was increased by 2%.

During the past year Kozloduy NPP confirmed its importance as the most reliable and safe electricity supplier during the period of an unprecedented low level of the Danube River which caused an interruption of the electricity generation from many power plants in the region.

During the last few years, the generation has been in compliance with the predicted demand of the country. Despite the dispatch limitation for the plant output imposed in the period from the end of April to the middle of June, in 2003 Kozloduy NPP over-fulfilled its production targets by delivering 104% of the planed amount. All units produced more electricity than planned. Most significant is the performance of Unit 4 which operated at a greater output than planned throughout the whole year despite only very minor deviations from its operating schedule.


figure 9

FIG. 9. Nuclear Power Share in Bulgarian Energy Sector


For the last 13 years the availability of Kozloduy NPP units was increased up to average world-wide values. The Unit Capacity factor reflects the effectiveness of plant programs and practices in maximising available electricity generation and indicates how plans are operated and maintained.

In 2003, 99,38% (20 457 132 MWh) of Kozloduy NPP's maximum planned availability was provided which is within the frames of the 3% reserve agreed with the National Electricity Distribution Company. In 2003 Kozloduy NPP has used 47,78% (295 053 MWh) of the permitted unavailability time for maintenance outside the outages. As compared to 2002, there is an 11,17% decrease of the non-generation (planned and non-planned). The stable tendency for reduction of the non-generation share continues (by 5-6% per year). The capability factor values of Kozloduy NPP are comparable with the average indicators of the very best nuclear plants world-wide.


figure 10

FIG. 10. Nuclear Power Capacity Factor

 

figure 11

FIG. 11. Nuclear Power Capacity Factor world-wide


The Unit Capability Loss factor reflects the effectiveness of plant programs and practices in maintaining systems available for safe electrical generation.

After implementation of the main part of the modernisation program of Kozloduy NPP Units 5 and 6 the capability loss factor was sufficiently decreased below the average world-wide values.


figure 12

FIG. 12. Nuclear Power Capacity Loss Factor

 

figure 13

FIG. 13. Nuclear Power Capacity Loss Factor world-wide


The Unplanned Automatic Scram per 7000 Hours Critical indicator monitors progress in reduction the number of unplanned reactor shutdowns. It provides an indication of success in improving plant safety by reducing the number of undesirable and unplanned transients requiring reactor scrams, as well as an indicator of how well a plant is maintained. Taking into account the hours that a plant was critical indicates the effectiveness of scram reduction efforts while the plant is operating.

The Kozloduy NPP Units 5 and 6 have been operating without unplanned automatic scram since 1994 and 1996 respectively.


figure 14

FIG. 14. Unplanned Automatic Scram per 7000 Hours Critical

 

figure 15

FIG. 15. Unplanned Automatic Scram per 7000 Hours Critical world-wide


The Collective Radiation Exposure monitors the efforts to minimise the total radiation exposure at each unit and in the nuclear industry as a whole. It is a measure of the effectiveness of the radiation protection programs in minimising radiation exposure to plant personnel.

Optimal staff radiation protection is one of the main applied management principles, which ensures the lowest possible levels of radiation for the personnel. The Bulgarian radiation protection standards are strictly observed. In recent years there has not been any recorded case of exceeding the annual radiation dose limit of 20 mSv for exposure to radiation at work. The comparison of the personnel collective dose data averaged per unit of Kozloduy NPP, against the same WANO indicator shows that a level comparable with the best results in the world is achieved. Individual dose exposure indicators are compatible and confirm the radiation protection effectiveness.

After implementation of the complex modernisation program of Kozloduy NPP Units 1-4 the Collective Radiation Exposure was sufficiently decreased well below the average world-wide values.


figure 16

FIG. 16. Collective Radiation Exposure

 

figure 17

FIG. 17. Collective Radiation Exposure world-wide

 

2.2.3.  Plant upgrading and plant life management

2.2.3.1.  Kozloduy NPP, Units 1-4 modernisation process

The systematic analyses for compliance of the Units 1-4 with the current safety requirements and the internationally adopted codes and practices began in 1990 and were initiated by IAEA safety review and WANO missions. Considering the results of these first evaluations in 1991 the so-called Short Term Program for implementation of the safety upgrading measures on these units was developed.

The implementation of the program commenced in 1991 and was completed in 1996. A total of over 900 modifications of systems and equipment have been implemented, and many important new safety systems were installed. The total amount of the funds, allocated to the so-called Short Term Program was 145 MUSD.


program


Continuation of the safety upgrading process initiated by the Short Term Program has been assured by parallel development of a new, Complex Program based on the Periodic Safety Review methodology of IAEA. The review itself was completed within two-year period and with the support of the original designers of the units from Russian engineering organisations. The goal of this assessment was to develop an effective set of measures that would bring the units in conformity with the current safety standards. More than 450 man-months of highly qualified expert efforts were dedicated to this assessment.

A system of presented here 25 classification categories, developed on the basis of safety functions and conditions to ensure their integrity was used for the analysis.

As a result of the assessment a new comprehensive (so called Complex) Modernisation Program was developed. Altogether 100 million of USD were allocated for implementation of the proposed technical measures and during the period of 1997-1999 more than 460 design changes were implemented.

In parallel, to provide maximum effectiveness of this program, it was subjected to a broad international assessment. Several missions from IAEA and WENRA and expert assessments by EdF and Siemens have been carried out for the purpose in 1998 and 1999. In February 2000 a new revision of the program, named PR-209M was issued in order to reflect the results of these reviews.

The extended program scope was mainly applied to the modernisation of Units 3, 4 while the implementation of some measures on Units 1,2 were delayed due to the taken decision for early closure. The total amount of funds allocated to implementation of this revision of the program was 66 million of USD.

The implementation schedule has been accordingly updated keeping the approach of continuous safety upgrading of the units. According to this the major part of activities were implemented for unit 3 and 4 till 2002 (a total of 375 design changes) finishing with a total up-date of the units' SAR. Some long-term activities, mainly oriented to severe accident management, continued. The design changes implementation by the different programs represents an integrated process, which led to extremely extended changes to the design bases of the respective units.

The real implementation of the different Modernisation Programs during the years till 2002, brought the safety of Units 1-4 to a different level compared with their original design. Especially for units 3 and 4, the current extended design basis is successfully compared to the safety level of the WWER-440/213 reactors that is internationally recognised as adequate after IAEA in-depth review.


units safety

              Initial design

Short term Program

PRG'97A

PR-209M        


In 2002 an updated "Safety Analysis Report" of units 3 and 4 was issued, reflecting the new design status after the finalisation of the Modernisation Program and taking into account the operational experience of the units. It was developed in accordance with the scope and content approved by regulatory body in compliance with current world-wide practice.

The updated "Safety Analysis Report" of units 3 and 4 is the basic document and is a condition for issuing operation licenses to KNPP in compliance with the requirements of the new Safe Use of Nuclear Energy Act (SUNEA) after the expiry of current operation licenses.

Having presented this document and the other necessary documentation as well as a review under SUNEA, at the end of May 2003, the NRA issued long-term licenses for operation of units 3 and 4 for 8 and 10 year term of operation respectively.

Among the others the following extremely important results form the modernisation activities should be highlighted:


figure 20



Important assessments on Fire Risk, Environmental Impact, Equipment Classification and Reliability and others have been carried out in parallel to supplement other technical measures. The development of Rest Lifetime Management Program together with the optimisation of the ISI program creates the necessary basis for steady, safe and efficient operation of the plant.

Complex plant approach allowed significant changes in other safety significant areas.


core damage


The plant successfully implemented a set of measures to address operational safety issues, identified by IAEA in 1991. Two OSART reviews were conducted in the period 1999-2001 with a third follow-up conducted in 2002. The IAEA experts concluded that all operational safety problems, has been resolved and the plant operational practice corresponds to the international safety standards worldwide.

As a result of continuous safety improvement the plant also successfully resolved the design safety issues, identified by IAEA in the document "Ranking of Safety Issues for WWER 440 Model 230 NPPs - TECDOC 640". A special IAEA mission conducted in 2002 concluded that all safety problems, defined by international experts has been resolved and in some cases the plant efforts went well beyond them, covering other areas with possible impact on the overall units safety.

A general conclusion on all the efforts was given in the IAEA Annual Report for 2002:

"A Safety Review Mission to Kozloduy, in Bulgaria, reviewed the results of more than a decade of safety upgrades and assessments at units 3 and 4, including a series of actions recommended by various IAEA Review Teams.

The Team concluded that the operational, seismic and design safety at Kozloduy now corresponds to the level of improvements seen at plants of similar vintage elsewhere.

Many of the safety measures adopted for these plants in the design, operation and seismic areas exceeded those that were foreseen."

In line with the above conclusions was the outcome of the AQG Peer Review, conducted upon a specific Bulgarian request in 2003. In 2001 the AQG, created as an EU advisory body on the nuclear safety issue published a report identifying a set of recommendations to each of the EU accession countries in their striving for high level of nuclear safety. These were recommendations not only in the area of the safety of particular installations but also in the legislative and institutional framework existing in the country to warrant preserving of the nuclear safety level.

First assessment of the achievements of each country was conducted in 2002. In November 2003 a team of 12 experts from Austria, Belgium, Denmark, Finland, France, Germany, Greece, Ireland, Italy, Spain, United Kingdom and the EC performed new thorough evaluation of the country progress under the leadership of the Italian representative.

During this mission items related to recommendations of AQG reports were discussed with Kozloduy NPP, Nuclear Regulatory Authority (NRA) and Ministry of Energy and Energy Resources (MEER).

Although in accordance with its mandate the review was based on recommendations in the last AQG report, the discussion in many areas went out of these issues, covering all important areas of the plant program especially for Units 3&4. In the same time issues going out of the 2001 AQG report were discussed like the long-term improvements program (up to 2009) and adequacy of their financial provisions, plant and regulatory body commitments in long-term modernization plans and other condition included in the new operational licenses effective until 2011 and 2013 for Units 3 and 4.

Following the technical evaluation of the information made available before and during the mission several conclusions on the status of the recommendations contained in the 2001 Report on Nuclear Safety in the Context of Enlargement were presented in the AQG/WPNS final official report i.e. the following:

In its report AQG also commented that most of the recommendations, including all requested for units 3 and 4, are already implemented. The remaining are in progress according to established schedules. The actions, which are being carried out, concern units 5 and 6, which large scale modernisation program is underway, or long term projects on units 3 and 4 which are going well beyond AQG recommendations.

All they were assessed as adequate and feasible in terms of human and financial resources.

Based on this AQG/WPNS made the fundamental conclusion that for Bulgaria further monitoring activities by the AQG/WPNS are not considered to be necessary, fully confirming the already recognised capability of the Bulgarian nuclear program in resolution of generic safety issues.

The conclusions of the team on the specific issues and in general were in full agreements with the other previously available international assessments like the assessment of IAEA SRM 2002 on the results of Units 3 and 4 modernisation program.

The main conclusion of the reviewing team is that all AQG recommendations to Kozloduy NPP of 2001 and 2002 have been implemented and do not need further monitoring. It was stated that excellent engineering work was performed at Kozloduy NPP concerning the Accident Localisation System, which is in full compliance with the western approaches and good practices. The experts found that the reactor safety of Units 3 and 4 is provided with a considerable reserve up to the end of the term of the licenses issued by the NRA. Concerning the management of severe beyond design basis accidents, the implemented activities were assessed as exceeding the scope of AQG recommendations.

2.2.3.2.  Currents status of Kozloduy NPP, Units 1-4

In accordance with the preliminary announced plans, units 1 and 2 of Kozloduy NPP were operated until the end of 2002 and then were consecutively disconnected from the grid and put in cold sub critical state. In the beginning of 2003, the nuclear fuel from the reactors was transferred to the reactor spent fuel pools and the units were brought to the corresponding mode according to the requirements of the Technical Specifications.

In the beginning of 2004, after a review of the fulfilment of the specific requirements prescribed as additional measures for safety during long term stay of the units in such mode, NRA issued licenses with term of 5 years validity. According to the licenses units 1 and 2 cannot be used for the generation of electricity and the activities are limited to the storage and cooling of irradiated and spent nuclear fuel in the reactor pools with no fuel in the reactor core.

Based on the new design basis of units 3 and 4 and the current operational practice reflected in the updated SAR, operational procedures and other documents, NRA issued long-term operational licenses. The unit 3 license was issued 22 June 2003 with an 8 years term of validity and the license of unit 4 was issued 26 February 2003 with a term of validity of 10 years.

The conditions of units 3&4 operational licenses contain requirements for the continuation of the implementation of measures, included in other programs as continuation of PRG'97A, aiming for further improvement of the safety level. Main part of these programs will be completed within 2005 with some activities with regard to residual lifetime management scheduled until 2009.

Currently in line with the conditions of the licenses, Kozloduy NPP is implementing the strategy for severe accident management. The strategy includes development of Severe Accidents Management Guidelines and implementation of technical measures for management of the fuel cooling and radioactive releases in case of core degradation. Installation of hydrogen recombiners and forced filtered venting systems in the units' accident localisation systems is in the process of implementation.

2.2.3.3.  Kozloduy NPP, Units 5 and 6 modernisation process

The Kozloduy NPP units 5 and 6 are equipped power reactors of the WWER-1000/V320 type. The design of these reactors meets entirely the international requirements for nuclear safety. The main principle for NPP safety is applied: defence-in-depth with several physical barriers, including the redundancy, diversity, independence, protection against failures, and passive elements. The active safety systems have 3x100% capacity, functional independence and they are physically separated. Their large dry containment is designed for full pressure - 0.5 MPa.

The main objective of Units 5 and 6 Modernisation Program is to implement the improvements necessary to meet all international requirements for NPP's with VVER-1000/V-320 units in terms of safety and reliability, in order to extend the unit lifetime following Periodic Safety Review process, required by NRA. The Program is based on IAEA recommendations described in Safety issues and their ranking for VVER-1000 model 320 NPPs (IAEA-EBP-VVER-05). In this document, the safety issues of VVER-1000 reactors are divided in two main groups - design and operational issues. Units 5&6 Modernisation Program solves these issues and comprises 212 measures, each including one or more issues. The identified measures' adequacy towards the list of unresolved safety issues was reviewed by IAEA in 2000. The IAEA expert mission concluded that for all safety issues, the process of their resolving was started and relevant measures are completely or partially implemented, in accordance with Safety issues and their ranking for VVER-1000 model 320 NPPs (IAEA-EBP-VVER-05).

In 2003, Unit 5 worked without an outage and the main efforts were focused on Unit 6. The modifications implemented are comparable to the commissioning of a new unit, as the scope and terms of this reconstruction have no precedent in the world practice. Over 20 international companies were involved in the works, the major effort being undertaken by the Main Contractors - European Consortium "Kozloduy" (ECK), composed of the French and German branch of Framatome together with the Russian Atomstroyexport and the American company Westinghouse. A significant part of the engineering, installation and commissioning work under the Modernisation Program was performed by Bulgarian sub-contractors. The current status of Units 5 and 6 modernisation program implementation is presented in table 13.


TABLE 13. IMPLEMENTATION STATUS OF UNITS 5 AND 6 MODERNIZATION PROGRAM BY THE END OF OCTOBER 2004


Total Number

Completed

Ongoing

To be done

212

142

66

4

Percentage

67.0 %

31.1 %

1.9 %


Units 5 and 6 Modernisation Program is developing as planned in compliance with the approved schedule, which envisages its completion in 2006. The implementation of the program is successfully by a well organised project management team applying high technologies and engineering solutions that will considerably contribute to the enhancement of safety, reliability and performance of KNPP. This program will give a positive example of high quality modernisation of an NPP with VVER reactors.

2.2.4.  Nuclear power development projections and plans

At the end of 2002 Bulgarian Government took a decision to perform a feasibility studies for renewing the construction of the second Bulgarian NPP at the Belene site. In April 2004 Bulgarian Government approved in principal the continuation of the construction activities at Belene site based on Least Cost Plan developed by National Electric Company. In November 2004 the Ministry of Environment and Water approved the Environmental Impact Assessment on Belene NPP.

The most recent generation planning forecasts of electric demands for the period 2004 - 2020 project that Bulgaria needs new electrical generating capacity to replace nuclear assets scheduled for retirement, to satisfy domestic load growth, maintain energy security, and continue with present and expected commitments for electricity export. The generation planning analysis also concludes that an additional 1000 to 2000 MWe of base load units between 2010 and 2015 represent the capacity needed to service the anticipated demand.

Of the available generation technologies, nuclear units in the 1000 MWe range is a viable and convenient option for Bulgaria, considering available alternatives, environmental attractiveness, potential economic returns, and utilisation of strong in-country nuclear engineering support structure.

Belene is the most suitable site for the new NPP, offering location advantages, ability to meet current regulatory requirements for nuclear sites, as well as the opportunity to finish the partially completed Unit 1. Bulgaria possesses strong capability and more than 30 years (131 reactor years) experience in building, operating and maintaining nuclear power plants. This capability is a valuable resource that can be maintained and used in the development, design, construction and safe and reliable operation of a new nuclear power plant. The latest forecasts of in-country consumption, export sales, reserve and peak load requirements have been combined with estimates of the available and planned generation capacity to yield the following projection:


capacity

 

capacity

Remark: 100% of Installed Capacity = base load + peak load


Using internationally accepted generation planning methods, the optimal solution for meeting capacity requirements is the commissioning of 1000 to 2000 MWe of new capacity starting in 2010. Confirmation that nuclear technology as the optimum generation type to supply this needed capacity is based upon the following:

Therefore, to satisfy domestic load growth, maintain energy security, satisfy environmental objectives, and continue with present and expected commitments for electricity export, the clear way forward for Bulgaria is to proceed with the addition of two 1000 MWe nuclear units between 2010 and 2015.

The Feasibility Study also addresses the history of the Belene site, new requirements for site selection, any excluding or limiting factors, and vicinity information. The main conclusions of the study are:

The advantage of the option utilising the WWER 1000/B-320 on Unit 1 is that it has the potential for the maximum use of the delivered equipment and minimises potential major equipment delays. Alternatively, a significant advantage of the option with use of WWER 1000/B-466 on both Units 1 and 2 is that it utilises the NPP that scored the highest in technical ranking; utilises new technology that has a higher rated output and a sixty (60) year plant life; provides for two identical units that results in minimising spare parts inventory; reduces costs associated with simulators and employee training; and aids in minimising the potential for human factor related issues.

The technical and economic evaluations resulted in the identification of the optimal two-unit variants. Nonetheless, based on the results of these evaluations, it was recommended that the final selection between the variants described in the Feasibility Study be based on firm vendor cost information obtained through a open or selective tender procedure.

The socio-economic aspects of construction of Belene and project execution approach were also analysed. The major socio-economic conclusions are:

In addition to the above, completion of Belene will allow Bulgaria to continue as a key regional energy supplier.

2.2.5.  Decommissioning information and plans

The Law on the Safe use of Nuclear Energy stipulates that licensees must have adequate financial and material resources to maintain safety at all stages of the plant's life. This includes decommissioning and the subsequent management of radioactive waste.

The legal provisions for financing the management of radioactive waste and decommissioning funds for the nuclear waste and decommissioning programs have been established since 1999.

The real functioning of the Funds started in 1999 after approval of the corresponding Regulations. The National Electric Company and later Kozloduy NPP have started with payments since 2000. The national radioactive waste management enterprise was established in 2004.

Contributions are specified by the Council of Ministers and currently these are 15% of electricity sales return for decommissioning and 3% for Radioactive Waste Management. There are also contributions from the state budget.

The Bulgarian Authorities recognise the need to keep the funds under review and have the power to impose changes. The situation is reviewed every 3 years by the Ministry of Energy, the utility, the regulator and other government departments.

Bulgaria's own contribution is currently above 18% of the revenues from electricity sales - more than in every other EU country. The Bulgarian Authorities fully recognise the financial implications associated with NPP decommissioning and waste management. Arrangements have been made to set up appropriate funds and to periodically review the contributions to these funds and the funds operations and financial transactions with the purpose to provide for the funds' adequacy.

The Technical Design for the Decommissioning of units 1-2, which was prepared by Belgatom- EWN-Energoproject Consortium still is the ruling document of the decommissioning process. The modified circumstances of, and the new requirements to the decommissioning, however drive the Kozloduy NPP to update it. The main body of the existing strategy is not going to change, but the new edition will include:

Currently there are several projects under implementation:

The Units 1 and 2 spent fuel pools de-fuelling is planned to be implemented after commissioning of Dry Spent Fuel Storage Facility expected in 2009.

2.3.  Supply of Nuclear Power Plants

Bulgaria does not supply nuclear power plants and/or equipment for nuclear power plants. The equipment for the existing plants have been purchased from Russia, but some parts and systems have been supplied from western suppliers like Siemens, Westinghouse, Sempel, Sebim, Framatome and others.

2.4.  Operation of Nuclear Power Plants

The Council of Ministers of Republic of Bulgaria adopted Resolution No.70 dated 20 February 2001, according to which all nuclear power plants and other equipment on "NPP Kozloduy" PLC are defined as one nuclear installation and "NPP Kozloduy" PLC is its operator according to the Vienna Convention on Civil Liability for Nuclear Damage.

"NPP Kozloduy" PLC as "nuclear installation operator" according to the Vienna Convention on Civil Liability for Nuclear Damage is the bearer of the corresponding civil responsibility. As "license holder" according to Nuclear Safety Convention, the company bears the responsibilities for nuclear safety. This is reflected in the NPP "Kozloduy" PLC Statute (art.2, para 2 and para 3) and in Corporate Structure and Activities Code (art. 5 and art. 6). In this respect, the company holds a license, given by the State Energy Regulation Committee on production of electrical and thermal energy (Verdict No. 049 dated 11.12.2000 of SERC).

As the operating organisation is responsible for ensuring fulfilment of safety requirements, "NPP Kozloduy" PLC rights and obligations are defined in the Statute, Corporate Structure and Activities Code, company structural subdivision and sections activity organisation regulations, as well as in the personnel job descriptions for the whole hierarchy managing chain.

"NPP Kozloduy" PLC responsibilities and obligations are summarised in art. 7 of Corporate Structure and Activities Code and are performed through "implementation of activities for nuclear safety maintenance and enhancement, radiation protection, physical protection, emergency preparedness, technical safety, preserving the health of personnel and population and environment."

In "NPP Kozloduy" PLC Corporate Structure and Activities Code" (art.8) the implementation of overall company activity, the following principle is of top priority: "Following the requirements for nuclear safety, radiation protection, as well as preserving the life and health of personnel, population and environment has priority over operational and other public needs."

"NPP Kozloduy" PLC is a separate corporate body, registered according to Commercial Law, which has an independent balance and bank accounts. General Meeting and Board of Directors manage the Company. "NPP Kozloduy" PLC organises and manages its commercial activities in accordance with the Statute and "NPP Kozloduy" PLC Corporate Structure and Activities Code".

For ensuring safe operation, the Kozloduy NPP management:

2.5.  Fuel Cycle and Waste Management

The Kozloduy NPP Fuel Cycle includes all inherent stages as Uranium purchase, Conversion, Enrichment, Fabrication, Interim Storage, Spent Fuel transportation, Reprocessing and VHLW disposal based on the agreement between Republic Bulgaria and Russia and following long term commercial contracts for fuel supply and spent fuel reprocessing.

Kozloduy NPP has been sufficiently increasing the burn-up and achieved a reduction of spent fuel generation during transition from 2 year to 4 year fuel cycle length. These design changes also lead to decreasing of specific consumption of natural uranium up to 28%.


figure 18

FIG .18. Burn-up and Spent Fuel generation variation during transition from 2 year to 4 year fuel cycle length.


The new Strategy for spent fuel management and radioactive waste is developing. Two options of spent fuel management were analysed - spent fuel reprocessing and spent fuel disposal. The levelled fuel cycle cost was used as a criterion for decision making.


levelled fuel cycle


The results indicate that there is a small cost difference between the prompt reprocessing option compared with the long-term storage and direct disposal option. Based on best estimate data, the reference cases show a difference of less than 20 per cent of the total nuclear fuel cycle cost taking into account all spent fuel accumulated at the Kozloduy site, the cost of the direct disposal option being lower. In light of the underlying cost uncertainties, this small cost difference between the reprocessing and direct disposal options is considered to be insignificant, and in any event, represents a negligible difference in overall generating cost terms. It is likely that considerations of national energy strategy including reactor type, environmental impact, balance of payments and public acceptability will play a more important role in deciding a fuel cycle policy than the small economic difference identified.

Kozloduy NPP target is to minimise the impact on the population and environment of the radioactive wastes and spent nuclear fuel stored at the plant site. The management of these activities is in compliance with the requirements of the Vienna Convention on Safety of Spent Nuclear Fuel Management (SNF) and on Safety of Radioactive Wastes Management (RAW).

During the operation of the nuclear power plant liquid and solid radioactive wastes are generated. Compared to the unit of produced energy the RAW quantities generated by NPP are over 10 000 times lower than the wastes from coal-fired power plants.

The generally accepted principles for RAW management define the requirement the RAW to be collected, treated, conditioned and stored in a way that provides protection of human health and environment protection now and in future without being a burden to the future generations. At Kozloduy NPP site, a facility was constructed for treatment, conditioning and storage of low-level and intermediate-level liquid and solid radioactive wastes. The commissioning of this facility gave a permanent solution of the issue for reliable storage of RAW and is also a significant contribution to environment protection.

As a result of the commissioning of this facility and the program applied during the last years to minimise the radioactive wastes, the speed of treatment and conditioning of RAW for long term storage has increased.

The spent nuclear fuel (SNF) is stored at the plant site under conditions which provide safety for the environment and population. After storage in special at-reactor spent nuclear fuel pools, the fuel is removed to a specially constructed Wet Spent Fuel Storage Facility for storage of spent nuclear fuel for all units.

The capacity of the facility allows storage of all spent nuclear fuel assemblies being discharged now and for the future years until the commissioning of the new facility.

The conditions created for safe storage of SNF at the plant site, together with the fact that part of the fuel is transported for reprocessing and long term storage in Russia, provide a mid-term solution of the SNF safe management issue. Together with the Ministry of Energy and Energy Resources (MEER), NRA and other national institutions implementation is prepared applying the best practices for long term safe storage of radioactive wastes and spent nuclear fuel.

2.5.1.  Management of the Spent Fuel at the Kozloduy site

The SF removed from the reactors is stored in pools situated near by the reactors. In 1990, the construction of a pool type spent fuel storage facility (SFSF) on the site of the Kozloduy NPP was accomplished. It is situated in a separate building on the territory of the Kozloduy NPP, nearby units 3 and 4. According to the design, the SFSF is to be filled in 10 years and the assemblies can be stored in it for a period of 30 years. After 3-5 years storage in the near reactor pools, the SF is transported to the SFSF. In 1991, a programme for enhancement of the SFSF safety was elaborated which is now being updated. In 1992, the new seismic characteristics of the Kozloduy NPP site were taken in account in the Programme.

Two independent ecological assessments of the SFSF were carried out: an expertise made by a team from the Risk-Engineering company as well as a complete report of the impact on the environment made by a group of specialists from the Sofia University "Kliment Ohridski". The results of these assessments do not show any considerable negative impact on the environment from the SFSF operation.

In March 2001, the NRA has licensed the SFSF.

2.5.2.  Management of Low and Intermediate Level RAW

The generated from the NPP operation RAW are stored in auxiliary buildings (AB), one for two units. In recent years, the NPP generates annually average of about 350-m3 liquid RAW, 200 m3 conditioned solid RAW and 20 m3 low and intermediate ion exchange resins.

The work on the completion of construction of the RAW Treatment and Storage Facility for LILW at the Kozloduy NPP site is completed. The Treatment and Storage Facilities are in operation.

A fund for Management of Radioactive Waste is established by the ASUNE. All waste generators shall pay special fees to the fund: currently for NPP Kozloduy it is about 3% of the average market price of energy sold to the National Electric Company. The Minister of Energy and Energy Resources through relevant Steering Committees manages the funds.

2.6.  Research and Development Activities

In the field of nuclear R&D, Bulgaria is in co-operation with international organisations like: the Joint Institute of Nuclear Research in Dubna, Russia; the Institute of Theoretical Physics, Trieste; OECD Halden Reactor Project, CERN and other foreign institutes. NRA pays the membership fee in these organisations.

Nuclear research and development activities in Bulgaria are carried out in several institutes, the most important of which are:

All these organisations are financed by the national budget. Each year the Government donates them with the Act of the State Budget.

2.7.  International Co-operation

As a member of the world community of nuclear operators, Kozloduy NPP maintains a continuous process of information and operational experience exchange with the International Atomic Energy Agency (IAEA), the World Association of Nuclear Operators (WANO) and other international organisations and leading companies in the filed of nuclear energy.

Through participation in the international peer review process, Kozloduy NPP obtains assessment and support of its efforts in operational safety enhancement. In 2003 the plant was a host of two major reviews:

Both expert teams acknowledged the exceptional efforts invested by the plant during the last several years and the high motivation of people working at KNPP.

The plant participated in a number of regional projects and technical assistance programmes of IAEA, WANO, EU PHARE Nuclear Safety Programme, Nuclear Safety Programme of UK Department of Trade and Industry (DTI) and in different bilateral co-operation programmes. Also Kozloduy NPP took part in the activities of the largest international and European forums and organisations such as World Nuclear Association (WNA), European Nuclear Society (ENS) and European Nuclear Forum - FORATOM (through BULATOM). This enabled the KNPP specialists to be in line with nuclear energy news and to present before the international science community and bodies of EU the achievements of Bulgarian nuclear industry.

In 2003 the First National Report of the Republic of Bulgaria was presented on implementation of the obligations under the Joint Convention for Safety of Radioactive Waste and Spent Fuel Management. Bulgarian nuclear leading experts participated in the development of the report and answers to additional questions posed to Bulgaria by the Convention countries.

2.8.  Human Resources Development

The personnel of Kozloduy NPP responsible for the safe operation of nuclear facilities have a high educational status. In 2003, 80% of the KNPP employees had a university degree and high technical education. This was achieved through a system for recruitment of new personnel with higher education and qualifications as some employees reached the retirement age, and who had lower educational qualifications.

The measures for personnel number optimisation (down-sizing) undertaken after the detachment of Kozloduy NPP plc as an independent commercial company in 2000, have given good results. In the last three years the staff number has been reduced by 20% at the end of 2003. It should be noted that both output and safety levels have increased over the same period. The good performance indicators in the last several years have given the opportunity to keep a good salary level at Kozloduy NPP, as compared to the average salary in the country.

One of the most important factors of the safe, reliable and effective operation of Kozloduy NPP is the availability of well-trained and qualified personnel. The overall training process and personnel qualification control are conducted in accordance with the Systematic Approach to Training implemented in all nuclear power plants. For improving the qualification of NPP personnel, two basic forms of training are applied - theoretical training (lectures, self-training and computer-based training) and on-the-job training. The plant Training Centre is equipped with modern simulator facilities, ensuring adequate training for licensed operators and line managers as well as the performance of a number of engineering tasks and analyses. At present two simulators, VVER-1000 Full Scope Simulator (FSS-1000) and VVER-440 Multi-Functional Simulator (MFS) are used for training. Current modernisation programmes are also implemented on the simulators aiming to maintain their conformity with the reference units. All training courses are annually upgraded based on analysis of events in other plants, feedback from the training sessions, unit design modifications and other reasons, including changes of the regulatory requirements.

Provision of a safe and healthy working environment through elimination or maximum limitation of the existing hazards is one of the basic goals of Kozloduy NPP plc Management. In compliance with Bulgarian legislative requirements, which were harmonised with the European requirements for the working environment, a risk assessment of the work place was made and corrective measures were implemented. The data from the last few years proved the effectiveness of the efforts made in this direction. The trend for reducing the industrial safety accident rate is very clear and this indicator is comparable with the world's best NPP indicators according to WANO database.

The social policy of Kozloduy NPP plc is oriented towards provision of equal social benefits aiming at maintaining and increasing the personnel's motivation. Together with the five Trade Unions in the plant a number of social benefits were agreed in accordance with the possibilities given by the labour legislation. The Company annually provides BGN 8 millions for social and cultural funds. The priorities for these funds are determined by the General Assembly of the Kozloduy NPP employees. Kozloduy NPP maintains two recreational complexes, a cultural centre in the town of Kozloduy and a sports facility with two swimming pools and other opportunities for sport and relaxation. Kozloduy NPP Management pursues an open dialogue in communication with the personnel on all the issues - the ones related to production and safety as well as the social problems.

3.  NATIONAL LAWS AND REGULATIONS

3.1.  Safety Authority and the Licensing Process

The National Regulatory Authority in the field of safe use of nuclear energy is the Nuclear Regulatory Agency (NRA). The legal framework in respect of the NRA is provided for in the Act on the Safe Use of Nuclear Energy (ASUNE - in force from July 2002). According to Article 4 (1) of the Act, "State regulation of the safe use of nuclear energy and ionising radiation, the safety of radioactive waste management and the safety of spent fuel management is implemented by the Chairman of the Nuclear Regulatory Agency". Article 4 specifies: "the Chairman is an independent specialised authority of the executive power" and "The NRA Chairman shall be designated by a decision of the Council of Ministers and shall be appointed by the Prime Minister for a mandate of five years and may be selected for one more term of office (mandate)". The functions of the NRA are effectively separated from those of the bodies and organisations involved in promotion or use of nuclear technology.

3.1.1.  Safety Authority responsibilities

Pursuant to Article 5 of the ASUNE, the Nuclear Regulatory Agency shall have the following powers:

An administration helps the NRA in implementation of its authorities, assures technically its activity, and performs activities on administrative service provided to legal persons and citizens. In its activities, the NRA and its administration is guided by the adopted by the Council of Ministers Organisational Rules of Procedure. The administration is organised in a general department and 4 departments, distributed into general and specialised administration.

3.1.2.  Organisational Structure of the NRA

A Chairman supported by two Deputy Chairmen and an Executive Secretary governs the NRA. The permanent number of the NRA staff is 102 persons (4 - management team, 19 positions in the general administration and 79 experts and inspectors). Six inspectors work permanently at the Kozloduy NPP site. 95% of inspectors have university education and more than 60% of them have over 15 years of experience in the nuclear field. Six NRA employees have Ph.D. degree, including the Chairman and one of the deputies. The organisational structure of the NRA is shown in Figure 19.

The NRA is forming its own budget within the overall state budget. In accordance with Article 10, p. 1 of the ASUNE, the Agency operation is financed by the national budget and by income from the licensing fees collected under the Act provisions. Each year, the incomes and the expenditures at NRA budget and its relations to the central state budget, subsides or donations are defined by the annual Act of the State Budget. The draft budget is developed by the Agency following the Act on the State Budget Organisation. The Ministry of finance considers the budget, proposed by NRA and defines the final version, which is included in the bill of the Act on the State Budget (ASB) for the next year. The ASB is passed in accordance with the order of the Acts passing in the Republic of Bulgaria.

The organisational structure and duties of the NRA structural units are described in the Statute of the NRA (Rules of Procedure), adopted by the Council of Ministers Decree No.199 dated 29 August 2002, as shown in Figure 19.


figure 19

FIG 19. Organisational Structure of the NRA

 

3.1.3.  Licensing Process

The main legal provisions for the licensing of nuclear installations in Bulgaria are outlined in the ASUNE. The Act specifies the conditions, the order, terms and time limits for issuance of licenses and permits. The NRA Chairman based on a written application by the applicant shall issue licenses and permits for utilisation of nuclear energy. According to ASUNE Article 20 (1), a licence shall be issued for a term of validity not exceeding ten years.

All documentation submitted in respect of requested license issuance shall be in Bulgarian language. Submission of the original documents in a foreign language is permissible if a notarised translation into Bulgarian language is thereto attached.

3.2.  Main National Laws and Regulations in Nuclear Power

The new Nuclear Law (the Act on Safe Use of Nuclear Energy - ASUNE) entered into force in the middle of 2002 (2 July 2002). According to the ASUNE, the NRA Chairman has no power to issue regulations. The NRA Chairman develops and submits regulations for the application of the Act to the Council of Ministers for adoption (Article 5, item 14 of the ASUNE), through the Deputy Prime Minister.

The ASUNE specifies areas, which have to be regulated by the regulations and submitted to the Council of Ministers on a motion of the NRA Chairman or other State Authority. The Transitional and Final Provisions of the ASUNE require that within two years after the entry into force of the ASUNE, the Council of Ministers adopts new regulations and until then the old regulations are valid if they are not in conflict with the ASUNE.

After entry into force of ASUNE, the NRA initiated a large-scale legislative program for development of a comprehensive set of regulations. The programme included the responsible persons and the deadlines for the development of 19 secondary legal documents (18 Regulations and 1 Rate Schedule) in the area of the safe use of nuclear energy and ionising radiation, safe management of RAW and SNF, physical protection, emergency planning and preparedness, etc. The IAEA IRRT mission and the Peer Review of AQG expressed a high opinion of the programme. As the NRA objective is to establish exact and clear regulatory requirements, the program was based on:

The regulatory practice of the NRA has been build up and developed during a long time by taking into account of the legislative requirements, Agency's own experience and the good international practices. The NRA continuously improves its regulatory practice by conducting self-assessment, inviting well known international experts as management consultants, inviting independent external reviews, as well as by making use of the vast potential of the IAEA, WENRA and the leading regulators of the world scale.

During development of the secondary legislation (regulations), the systematic approach was applied in accordance with the national legislation, the importance of the legislative document and the resources available. All NRA employees participated actively in the development of the secondary legislation, as well as representatives of Ministries and other organizations concerned. An internal procedure, part of the QM system (IN QMS-RG-P1/0), has been developed by the NRA and has been used in the process of regulations drafting and adoption.

In September 2003, the Council of Ministers approved two of the 19 normative documents - Rate Tariff for the Fees Collected by NRA under the ASUNE and Regulation for the Fees Payment Procedure. The Regulation and the Rate Schedule guarantee the stable financing of NRA within the framework of the national budget.

At the beginning of 2004, all remaining regulations, included in the programme, except the Transport regulation, were submitted in one package for co-ordination with the ministries and the national institutions concerned. Thus, synchronisation and interrelation between the secondary legislation, its simultaneous entry into force and standardisation of the specific terminology have been achieved. Also, in the development of the regulations, the NRA used the advice and opinion provided to the Chairman by the Advisory Councils on nuclear safety and radiation protection.

At the middle of 2004, the Council of Ministries adopted all regulations under the ASUNE. All regulations should be translated into English and published at the NRA web site to facilitate foreign users and the NRA international partners.

The following fundamental acts of legislation are currently applicable in the matter of safe utilisation of nuclear energy and in respect of nuclear material procurement, accountability, storage and transport:

4.  CURRENT ISSUES AND DEVELOPMENTS ON NUCLEAR POWER

4.1.  Energy policy

The efficient functioning of the energy sector is vital for any economy. Energy is present as an essential component in any end product of industry or services. For this reason, the implementation of the strategy for economically viable, secure and environment-friendly energy supply is a fundamental prerequisite for the attainment of national objectives aimed at a significant and sustainable economic growth and eradication of poverty. Failure to undertake timely actions in this sector leads to the risk of turning it into a heavy burden for the economy as a whole.

On 26 November 2003, the National Assembly adopted the new Energy Act. The Act is in full compliance with the new Electric Power and Gas Directives of the EU with regard to the production, the operation of the systems for transfer and distribution, the separation and the transparency of the accountancy balance sheets and the access to the transfer and distribution systems.

A new market model of regulated access of a third party to the networks is introduced with the new act, which shall replace the model of the "single buyer". The liberalised share of the electric energy market is gradually expanded, following the model of "bilateral contracts with a balancing market." The new act anticipates that the monopoly over the import and export of enteric energy will drop off after the date of the accession of Bulgaria to the EU. The creation of a liberalised gas market with a new market model of regulated equally treated and non-discrimination access of a third party to the networks is regulated as well. Legal separation of the operators of the transfer and distribution systems from the activities relating to production and delivery is introduced. The new Energy Act renders an account of the rules for accelerated opening of the market of electric energy and natural gas. The final goal of the development of the internal energy market is the creation of a competitive retail market, at which all the users will have a possibility of selection of a supplier. The act creates stimulus for promotion of the production of electric energy from renewable energy sources (RES) and of the combined production of heat and electric energy.

At the end of 2003 a Draft of an Ordinance on the Issuance of Certificates of Origin of Electric Energy Produced by Renewable Energy Sources and/or in a combined manner was published for public discussion, for the issuance of green certificates and trade with them. In September 2003, the Council of Ministers adopted a bill of the Energy Efficiency Act. The following measures were anticipated:

4.2.  Privatisation and deregulation

The energy sector needs significant investments for the improvement of the existing infrastructure whose current status is a result of low levels of investments during the past decade. Privatisation represents a powerful instrument through which this goal can be achieved. In the main energy sectors - electricity sector, heat supply, gas supply and coal mining - partial privatisation has been carried out, mainly of companies providing secondary or ancillary activities. Successfully implemented reforms are a mechanism to gain confidence of foreign investors and to ensure the needed especially large investments in energy at low risk premiums and under diversified risk. Privatisation transactions in the energy sector were finalised from July 2001 to December 2003 with total revenues for the budget of 219 million BGN.

The privatisation of hydro power plants, differentiated parts of NEK EAD commenced in 2000. 34 HPP were sold out for the time period 2001 - 2003. The proceeds in the budget add up to over 138 million BGN.

The coal output branch comprises 15 companies with 100 % state participation, which are in a procedure for privatisation. 6 coal output mines and one colliery, a differentiated part, were privatised from July 2001 by the end of 2003. The proceeds in the budget add up to 51 million BGN.

On 5 July 2003, the Council of Ministers adopted Strategy for the Privatisation of Electricity Distribution Companies, which was approved by the National Assembly on 29 July 2003. The consultant for the privatisation was a Consortium, led by BNP - Paribas. The strategy anticipates simultaneous sale of the seven companies, differentiated in three packages:

The Privatisation Agency adopted the decisions for selection of a privatisation method on 24 October 2003. The sale was performed through a publicly announced two-stage tender without a preliminarily determined minimal price.

By Resolution No 485 of the Council of Ministers dated 15.07.2002 an Annual List of the Trade Companies with State Participation in the Capital was adopted, the shares of which (up to 49% of the capital) were anticipated for trading at the Bulgarian Stock Exchange. Energoremont Holding EAD - Sofia, Energoremont Bobov Dol AD - Bobov Dol, Energoremont Varna AD - Varna, Energoremont Rousse AD - Rousse and TPP Maritsa 3 - Dimitrovgrad were included in the List. In 2003 the companies were successfully traded at the Bulgarian Stock Exchange, after their transformation in public ones. The initially offered 49% of the shares were sold out against non-monetary payment means - compensatory notes with a nominal of 33,8 million BGN, (or 8 million BGN real price). The remaining 51% shares of the companies were traded at the second stage, at the total value of 3 million BGN.

The revenues in the budget from the privatisation of servicing and repair companies add up to 30 million BGN. 9 companies were sold in the time period March 2002 - December 2003 through competitions and tenders, conducted by the Privatisation Agency.

4.3.  Role of the government in the nuclear R&D

All these organisations are financed by the national budget. Each year the Government donates them with the Act of the State Budget. In addition, in the nuclear R&D, Bulgaria is in co-operation with international organisations like: the Joint Institute of Nuclear Research in Dubna, Russia; the Institute of Theoretical Physics, Trieste; OECD Halden Reactor Project, CERN and other foreign institutes. NRA pays the membership fee in these organisations.

4.4.  Nuclear Energy and Climate Change

The energy sector is a major source of carbon dioxide and sulphur oxide emissions in the country. The thermal power plants are also a large source of nitrogen oxides and non-toxic dust. Coal-fired TPP release about 80% of the national emissions of sulphur oxides and about 60% of the national emissions of carbon dioxide.

Bulgaria ratified the UN Framework Convention on Climate Changes in 1995. According to the Kyoto Protocol signed in connection with the Convention in December 1997 it undertook the commitment to reduce the anthropogenic emissions of greenhouse gases by 8% per year within 2008-2012 compared to the emissions in 1988. The same joint commitment to reduce the emissions of greenhouse gases was also undertaken by the EU countries.

Emissions of 1 012 752 tons of sulphur dioxide, 36 182 tons of dust, about 52 758 tons of nitrogen oxides and 23 676 261 tons of carbon dioxide were saved in 2003 as a result of the production of electricity and heat from nuclear power, hydro power and co-generating capacities. The emissions were calculated as compared with the adopted reference TPP, burning lignite coal.


TABLE 14. STRUCTURE OF THE AVOIDED EMISSIONS AS A RESULT OF ELECTRICITY AND HEAT GENERATION IN 2003, T


SO2

Dust

NOx

CO2

NPP

808115

9253

36419

19110491

TPP

0

0

0

0

HPP

154173

1763

6940

3641420

CHP

49464

25165

9399

924350

Total

1012752

36182

52758

23676261

 

figure 20

FIG. 20. Estimated emissions of CO2


Nuclear power generates electricity with virtually none of the greenhouse gas emissions that cause climate change. Nuclear power generates electricity with hardly any emission of sulphur dioxide or nitrogen oxides, key agents for acid rain and photochemical air pollution.

The impact of Kozloduy NPP operation upon the environment components is subject to detailed and systematic studies since the plant commissioning in 1974. The electricity production technology at Kozloduy NPP in practice does not generate any greenhouse gases and considerably contributes to the environment protection. In June 2002, the Kozloduy NPP was awarded by the Ministry of Environment and Water of the Republic of Bulgaria for the significant contribution to the protection of the environment reproduction and natural resources.

4.5.  Safety and waste management issues

The radioactive waste management activities are carried out in compliance with the requirements of the Joint Convention on Safety of Spent Nuclear Fuel Management and on Safety of Radioactive Waste Management, the IAEA radioactive waste management principles being applied.

At Kozloduy NPP site, a facility was commissioned and licensed for treatment, conditioning and storage of low-level and intermediate-level liquid and solid radioactive waste. This facility is unique in Eastern Europe in terms of purpose and technology. The commissioning of this facility gives a long-term solution of the RAW reliable storage issue and significantly contributes to the environment protection. The achieved reduction factor of the solid radioactive waste volume is about 7.

The RAW generated from the use of radioactive substances in medicine, industry and research is stored at the Novi Han Permanent Radioactive Waste Repository (NHRWR), which is under reconstruction and upgrade.

The safety upgrading of the NHRWR is supported by an IAEA Technical project. For the period 2003-2004, the project focuses on the development of the necessary documents for the NHRWR licensing as well as studies of the "Gabra" site. The NRA actively participates in the process through review of the developed licensing documents, expert missions, etc.

4.6.  Other issues

 

REFERENCES

[1]

Nuclear Regulatory Agency, Annual Reports 2002, 2003.

[2]

Kozloduy NPP, Annual Reports 2002, 2003.

[3]

National Electric Company Annual Reports.

[4]

Report No.116110, Bulgaria - Power Demands and Supply Options, WB.

[5]

Strategy for Development of the Energy Sector, Committee of Energy December, (1995).

[6]

Tariffs for Electricity and Heat Energy Bechtel Int. Inc., prepared for USAID, (June 1996).

[7]

European Bank for Reconstruction and Development, Annual Reports 1994, 1995.

[8]

Collection of Bulgarian Nuclear Regulatory Documents, Balbok ltd. Sofia, (1994).

[9]

Social and Economic Development of Bulgaria 1990 -1993, National Institute of Statistics, Sofia, (1994).

[10]

Additional unpublished materials have also been used, like:
a) Reports of NEK prepared for the Commission for State Energy Regulation.
b) Materials prepared for the Council of Ministers concerning the Association procedure of Bulgaria in the European Union.

[11]

Data & Statistics/The World Bank, www.worldbank.org/data.

[12]

IAEA Energy and Economic Data Base (EEDB).

[13]

IAEA Power Reactor Information System (PRIS).

 

Appendix 1

INTERNATIONAL (MULTILATERAL AND BILATERAL) AGREEMENTS

AGREEMENTS WITH THE IAEA

  • NPT related safeguards agreement INFCIRC/178

Entry into force:

29 February 1972

  • Additional Protocol

Entry into force:

10 October 2000

  • Improved procedures for designation of safeguards inspectors

Entry into force:

16 October 1988

  • Supplementary agreement on provision of technical assistance by the IAEA

Entry into force:

18 August 1980

  • Agreement on privileges and immunities

Entry into force:

17 June 1968

OTHER RELEVANT INTERNATIONAL TREATIES, etc.

  • NPT

Entry into force:

5 September 1969

  • Convention on physical protection of nuclear material

Entry into force:

8 February 1987

  • Convention on early notification of a nuclear accident

Entry into force:

26 March 1988

  • Convention on assistance in the case of a nuclear accident or radiological emergency

Entry into force:

26 March 1988

  • Vienna convention on civil liability for nuclear damage and joint protocol

Entry into force:

24 November 1994

  • Protocol to amend the Vienna convention on civil liability for nuclear damage

Not signed

 

  • Convention on supplementary compensation for nuclear damage

Not signed

 

  • Joint convention on the safety of spent fuel management and on the safety of radioactive waste management

Entry into force:

18 June 2001

  • Convention on nuclear safety

Entry into force:

24 October 1996

  • Convention on Black Sea contamination protection

 

 

  • ZANGGER Committee

Member

 

  • Nuclear Export Guidelines

Adopted

 

  • Acceptance of NUSS Codes

No reply

 

  • Nuclear Suppliers Group

Member

 

BILATERAL AGREEMENTS

 

Appendix 2

DIRECTORY OF THE MAIN ORGANIZATIONS, INSTITUTIONS AND COMPANIES INVOLVED IN NUCLEAR POWER RELATED ACTIVITIES

NATIONAL NUCLEAR ENERGY AUTHORITIES

Nuclear Regulatory Agency
69 Shipchenski Prokhod Blvd.
1574 Sofia, Bulgaria

Tel: +359-2-9406800
Fax: +359-2-9406919
http://www.bnsa.bas.bg

Ministry of Energy and Energy Resources
8 Triaditza str., 1040 Sofia, Bulgaria

Tel: +359-2-9878425
Fax: +359-2-9865703
http://www.doe.bg

OTHER NUCLEAR ORGANIZATIONS

Bulgarian Academy of Sciences (BAS)
Institute of Nuclear Research and Nuclear Energy (INRNE)
72 Tzarigradsko shosse Blvd., 1784 Sofia, Bulgaria

Tel: +359-2-7144616
Fax: +359-2-9753619
http://www.inrne.bas.bg

Bulgarian Academy of Sciences
Institute of Metallurgy
53 Shipchenski Prokhod Blvd.
1574 Sofia, Bulgaria

Tel: +359-2-703485
Fax: +359-2-703207
http://www.bas.bg

National Electric Company
5 Vesletz Str., 1040 Sofia, Bulgaria

Tel: +359-2-9861819
Fax: +359-2-9872550
http://www.nek.bg

Kozloduy Nuclear Power Plant
3321 Kozloduy, Bulgaria

Tel: +359-973 7177
Fax: +359-973 80591
http://www.kznpp.org

Technical University of Sofia
8, Kliment Ohridski St.
Sofia- 1000, Bulgaria

Tel: +359-2-623073
Fax: +359-2-685343
http://www.tu-sofia.bg

Sofia University St. Kliment Ohridski
Department of Nuclear Physics and Nuclear Energy
5 J. Boucher Blvd., 1126 Sofia, Bulgaria

Tel: +359-2-62561
Fax: +359-2-622028
http://www.uni-sofia.bg

Sofia University - Radiochemical Laboratory
1 J. Boucher Blvd., 1126 Sofia, Bulgaria

Tel: +359-2-62565
Fax: +359-2-622127

RISK ENGINEERING LTD.
34 Totleben str., 1660 Sofia, Bulgaria

Tel: +359-2-9516915
Fax: +359-2-9549100
http://www.riskeng.bg

EQE Bulgaria Ltd.
1 Hristo Smirnensky Blvd.
1164 Sofia, Bulgaria

Tel: +359-2-9631951
Fax: +359-2-9631976
http://www.eqe.bg

ENPRO CONSULT Ltd. 16 G. M. Dimitrov Blvd,
1797 Sofia, Bulgaria

Tel:  +359-2-9711416
Fax: +359-2-9711421
http://www.enproco.com

ENERGOPROEKT JSC
51 James Boucher Blvd.
1407 Sofia, Bulgaria

Tel: +359-2-9607800
Fax: +359-2-8668951
http://www.enpro.bg

ATOMENERGOREMONT JSC
3321 Kozloduy, Bulgaria

Tel: +359-973 7 2927
Fax: +359-973 8 0736

_______________________________________

1. The statistical tables in this profile have been updated with data as of the end of 2007 from IAEA databases, namely the Power Reactor Information System (PRIS) and Energy and Economic Data Bank (EEDB), and the World Bank's World Development Indicators (WDI).