Abstract. This paper presents the status of Canadian efforts to adapt the newly revised ITER facility design to suit the specific characteristics of the proposed Canadian site located in Clarington, west of Toronto, Ontario. ITER Canada formed a site-specific design team in 1999, comprising participants from three Canadian consulting companies to undertake this work. The technical aspects of this design activity includes: construction planning, geotechnical investigations, plant layout, heat sink design, electrical system interface, site-specific modifications and tie-ins, seismic design, and radwaste management. These areas are each addressed in this paper.
IAEA 2001