TABLE 1. ESTIMATED AVAILABLE ENERGY SOURCES (2019-20)

Petroleum Natural Gas Coal Hydro Uranium
Total 0.03billion barrels 10000 BCF 2083million tons 1.5TWh per year
Total in exajoules (EJ) 0.18 10.55 61.05 0.0054

TABLE 2. ENERGY CONSUMPTION

Final Energy consumption [PJ] 2000 2005 2010 2015 2020 Compound
annual growth
rate 2000–2020 (%)
Total 634 766 954 1 183 1 490 4.37
Coal, Lignate and Peat 14 18 23 83 229 15.07
Oil 113 132 135 163 193 2.70
Natural gas 149 195 310 368 458 5.77
Bioenergy and Waste 313 340 361 383 321 0.13
Electricity 45 80 124 186 290 9.78

TABLE 3, TABLE T1.

Energy Sources Target Period 2005 2010 2015 2020 Compound
annual growth
rate 2000–2020 (%)
2020 2021 2025 2030 2035 2041
Gas/LNG 47% 45% 35% 28% 36% 35%
Coal 28% 27% 29% 30% 29% 35%
Oil 18% 17% 16% 14% 6% 1%
Hydro 1% 1% 1% 1% 1% 1%
Nuclear 0% 0% 9% 11% 11% 12%
Cross Border 6% 9% 10% 17% 17% 16%

TABLE T2). POWER IS SUPPLIED THROUGH PBCB’S POWER TRANSMISSION FACILITIES TO CUSTOMERS IN LOCAL CITIES BY BPDB, IN THE METROPOLITAN AREA BY DPDC AND DESCO, AND IN RURAL AREAS BY PBS. NOTE THAT DISTRIBUTION DEPARTMENTS IN LOCAL CITIES ARE BEING SEPARATED ONE BY ONE. FIG. 1 SHOWS THE STRUCTURE OF THE ELECTRIC POWER SECTOR IN THE COUNTRY.

Ownership of Power Plants Number of Power Plant Installed Capacity (MW)
Government of Bangladesh 57 9996
Joint Venture 1 1244
Private Sector Organizations 94 9984
Import from neighbor country - 1160
Total 152 22348

TABLE 3. ELECTRICITY PRODUCTION

Electricity production (GWh) 2000 2005 2010 2015 2020 Compound
annual growth
rate 2000dz?2020 (%)
Total 15 771 26 447 40 832 59 103 85 613 8.83
Coal, Lignate and Peat 0 163 772 997 2 622 0.00
Oil 1 020 1 526 1 477 9 666 7 665 10.61
Natural gas 13 984 23 991 37 811 47 624 73 864 8.68
Bioenergy and Waste 0 0 0 0 0 0.00
Hydro 767 767 772 600 875 0.66
Nuclear 0 0 0 0 0 0.00
Wind 0 0 0 6 0 0.00
Solar 0 0 0 210 587 0.00

TABLE 4. ENERGY RELATED RATIOS

2015 2016 2017 2018 2019 2020 2021
Nuclear/Total Electricity (%) 0.0 0.0 0.0 0.0 0.0 0.0 0.0

TABLE 4. ENERGY RELATED RATIOS

1963: Rooppur site selected for the NPP.
1971–78: Feasibility studies for site and first NPP conducted.
1987–88: Further feasibility studies for site and first NPP conducted.
1996: National Energy Policy identifies nuclear power as an option.
2000: Bangladesh Nuclear Power Action Plan (BANPAP) was approved by the government.
2010: National Parliament approves first NPP project and new structure for nuclear power program development (equivalent Nuclear Energy Programme Implementing Organization, NEPIO) were formed (National Committees, Technical Committee, Working Group).
2011: IGA with the Russian Federation signed for the first NPP with two WWER-1000 units
2012: Bangladesh Atomic Energy Regulatory Act 2012 was passed in the National Parliament on 19 June 2012.
2013: Bangladesh Atomic Energy Regulatory Authority (BAERA) was formed as a separate entity on 12 February 2013.
2015: A company named Nuclear Power Plant Company Bangladesh Limited (NPCBL) was formed on 18 August 2015.
General Contract was signed with the Russian Federation for main stage construction of Rooppur NPP on 25 December 2015.
2016: Inter-Governmental State Credit Agreement for financing the main stage construction of Rooppur NPP.
ECNEC (Executive Committee of the National Economic Council) approved Construction of Rooppur NPP Project.
2017: Agreement between the Government of the Russian Federation and the Government of the People’s Republic of Bangladesh on Cooperation Concerning Return of Spent Nuclear Fuel from Rooppur Nuclear Power Plant to Russian Federation was signed on 30 August 2017.
Design and Construction License for the Unit 1 of Rooppur NPP was issued by BAERA on 04 November 2017.
Construction of the first unit of Rooppur NPP was started on 30 Nov 2017.
2018: Design and Construction License for the Unit 2 of Rooppur NPP was issued by BAERA on 08 July 2018.
Construction of the second unit of Rooppur NPP was started on 14 July 2018.
Installation of core catcher of Unit 1 of Rooppur NPP on 18 August 2018.
2019: Installation of core catcher of Unit 2 of Rooppur NPP on 03 May 2019.
General Framework Agreement on Nuclear Fuel Supply for Rooppur NPP was signed on 06 August 2019 between BAEC and TVEL, JSC Russian Federation.
2020: An amended protocol to the IGA was signed between the governments of Bangladesh and the Russian Federation which provides an opportunity to receive technical assistance from the Russian Federation for the commissioning, operation and maintenance of the Rooppur NPP.
Reactor pressure vessel for Unit l arrived at Project Site on 10 Nov 2020.
2021: A modern training center was launched at Rooppur NPP on 01 June 2021.
Two complex polar crane beams installation on the rail track of Unit 1 was completed on 03 March 2021.
Pressurizer of Unit 1 was installed on 6 June 2021.
Four reactor circulation pumps of Unit 1 were installed on 20 June 2021.
Reactor pressure vessel of Unit 1 was placed at the designed position on 10 October 2021.
Four steam generators were installed in Unit 1 on 12 November 2021.
2022: Turbo-generator stator was installed on 05 April 2022.

TABLE 4. ENERGY RELATED RATIOS

TABLE 5. STATUS AND PERFORMANCE OF NUCLEAR POWER PLANTS

Reactor UnitTypeNet
Capacity
[MW(e)]
StatusOperatorReactor
Supplier
Construction
Date
First
Criticality
Date
First Grid
Date
Commercial
Date
Shutdown
Date
UCF
for
2021
ROOPPUR-1PWR 1080Under ConstructionNPCBLAEM2017-11-30NULLNULLNULLNULL0ROOPPUR-2PWR 1080Under ConstructionNPCBLAEM2018-07-14NULLNULLNULLNULL0
—: data not available.
Data source: IAEA - Power Reactor Information System (PRIS) [12]

TABLE 4. ENERGY RELATED RATIOS

Sl. No. Designation of person Role
State Minister, Ministry of Science and Information & Communication Technology Advisor
Secretary, Ministry of Science and Technology Convener
Secretary, Economic Relations Division/Nominated Joint Secretary Member
Secretary, Legislative and Parliamentary Affairs Division/Nominated Joint Secretary Member
Secretary, Power Division/Nominated Joint Secretary Member
Additional Secretary, Finance Division, Ministry of Finance (Treasury and Debt Management) Member
Chairman, Bangladesh Atomic Energy Commission (BAEC) Member
Joint-Chief, PAMSTEC Wing, Planning Commission Member
Member, Planning and Development, BAEC Member
Member, Engineering, BAEC Member
Dr. Mohammad Shawkat Akbar, Director, Nuclear Power and Energy Division, BAEC Member
Joint-Secretary, Ministry of Science and Technology Member-Secretary

TABLE 4. ENERGY RELATED RATIOS

Sl. No. Designation of person Role
Secretary, Ministry of Science and Technology Convener
Prime Minister’s Office (one representative) Member
Ministry of Foreign Affairs (one representative Member
Legislative and Parliamentary Affairs Division (one representative) Member
Finance Division (one representative) Member
Economic Relations Division (one representative) Member
Ministry of Industries (one representative) Member
Ministry of Commerce (one representative) Member
CPTU, IMED (one representative) Member
Deputy Technological Adviser, Ministry of Science and Technology (one representative) Member
Bangladesh Atomic Energy Commission (two representatives) Member
Bangladesh Atomic Energy Regulatory Authority (one representative) Member
Project Director, Construction of Rooppur Nuclear Power Plant Project, Bangladesh Atomic Energy Comission Member-Secretary

TABLE SHELF. THE NPP SITE AT ROOPPUR IS LOCATED NEAR THIS HINGE ZONE IN THE STABLE SHELF PART.

Sl No Project Code Project Title
1 BGD/5028 Assessing crop mutant varieties in saline and drought prone areas using nuclear techniques
2 BGD/8/018 Strengthening oncology department of Bangabandhu Sheikh Mujib Medical University

TABLE SHELF. THE NPP SITE AT ROOPPUR IS LOCATED NEAR THIS HINGE ZONE IN THE STABLE SHELF PART.

Sl No Project Code Project Title
3 BDG/1012 Implementing an Ageing Management Programme for the TRIGA Research Reactor of Bangladesh
4 BGD/6022 Production of Therapeutic Radiopharmaceuticals
5 BGD/9012 Strengthening Occupational Radiation Protection
6 BGD/2012 Establishing Nuclear Power

TABLE SHELF. THE NPP SITE AT ROOPPUR IS LOCATED NEAR THIS HINGE ZONE IN THE STABLE SHELF PART.

Sl No Project Code Project Title
7 BDG/2014 Infrastructure Development for the First Nuclear Power Plant in Bangladesh:
Preparatory Stage Construction and Erection Phase
8 BGD 2016 Developing Infrastructure and Support Systems for a Nuclear Power Plant During the Various Stages of Construction

TABLE SHELF. THE NPP SITE AT ROOPPUR IS LOCATED NEAR THIS HINGE ZONE IN THE STABLE SHELF PART.

Sl No Project Code Project Title
9 BDG 2018 Developing Infrastructure and Support Systems for a Nuclear Power Plant During the Various Stages of Construction-Phase II
10 BGD 2020 Infrastructure Development for the First Nuclear Power Plant in Bangladesh: Commissioning and Start-Up

TABLE SHELF. THE NPP SITE AT ROOPPUR IS LOCATED NEAR THIS HINGE ZONE IN THE STABLE SHELF PART.

Name Degrees* Field Established
University of Dhaka (DU) B.Sc., ?M.Sc. & PhD Nuclear Engineering 2012
Military Institute of Science and Technology (MIST) B.Sc.,?M.Sc., MEngg& PhD Nuclear Science and Engineering 2014
Bangladesh University of Engineering & Technology (BUET) M.Sc., M.Engg. Nuclear Power Engineering 2015
Chittagong University of Engineering & Technology (CUET) B.Sc., ?M.Sc. Nuclear Engineering 2019

TABLE STAGE (E.G. UNVEILING OR CLOSING PROGRAM OF CONSTRUCTION), REPRESENTATIVES OF THE STAKEHOLDERS ARE GIVEN THE UTMOST PRIORITY TO PARTICIPATE. EVEN THE REPRESENTATIVES FROM THE LOCAL COMMUNITY PARTICIPATED IN THE CEREMONY FOR THE IGA SIGNING.

RPV Installation Publication (History of RooppurNuclear Power Plant); Web link:http://rooppurnpp.portal.gov.bd/sites/default/files/files/rooppurnpp.portal.gov.bd/page/207f35cd_b9f3_44ff_9cf8_505f8834989e/2022-04-07-07-54-d83dd1331a30bb3cb4df44b02feb2b37.pdf
IAEA - Power Reactor Information System (PRIS)

TABLE STAGE (E.G. UNVEILING OR CLOSING PROGRAM OF CONSTRUCTION), REPRESENTATIVES OF THE STAKEHOLDERS ARE GIVEN THE UTMOST PRIORITY TO PARTICIPATE. EVEN THE REPRESENTATIVES FROM THE LOCAL COMMUNITY PARTICIPATED IN THE CEREMONY FOR THE IGA SIGNING.

AGREEMENTS WITH THE IAEA
Degrees* Field
NPT related safeguard agreement INFCIRC/301 Entry into force:
11 June 1982
Additional Protocol Entry into force:
30 March 2001
Improved procedures for designation of safeguards inspectors Accepted on:
25 April 1995
Supplementary agreement on provision of technical assistance by the IAEA Entry into force:
31 December 1979
RCA Entry into force: 24 August 1987
Agreement on privileges and immunities
Non-Party
OTHER RELEVANT INTERNATIONAL TREATIES etc.
NPT 31 August 1979
Convention on physical protection of nuclear material Non-Party Entry
Convention on early notification of a nuclear accident Into force: 7 February 1988
Convention on assistance in the case of a nuclear accident or radiological emergency Entry into force:
7 February 1988
Convention on civil liability for nuclear damage Non-Party
Joint protocol Non-Party
Protocol to amend the Vienna convention on civil liability for nuclear damage Non-Party
Convention on supplementary compensation for nuclear damage Non-Party
Convention on nuclear safety Entry into force 24 October 1996
Joint convention on the safety of spent fuel management and Non-Party on the safety of radioactive waste management Non-Party
ZANGGER Committee Non-Member
Acceptance of NUSS Codes No reply
Nuclear Suppliers Group Non-Member