Korea, Republic of

TABLE 1. ESTIMATED AVAILABLE ENERGY SOURCES

Fossil fuels Nuclear Renewable**
Solid Liquid Gas Uranium Hydro Other renewables
Total amount in specific units* 1326 0.050 0.774 0.002105 0.061660

TABLE 2. ENERGY STATISTICS

2000 2005 2010 2015 2018 Compound annual growth rate (%)
2000 to 2018
Final Energy Consumption (EJ)
Total 6.28 7.17 8.16 9.00 9.74 2.47%
Heat and Other 0.05 0.07 0.08 0.08 0.11 4.73%
Electricity 0.86 1.20 1.56 1.74 1.89 4.47%
Natural Gas 0.53 0.75 0.88 0.91 1.05 3.89%
Coal/Lignite/Peat 0.82 0.93 1.18 1.46 1.36 2.82%
Oil 3.93 4.06 4.21 4.47 4.89 1.22%
Bioenergy and Waste 0.09 0.16 0.22 0.32 0.38 8.41%

TABLE 3. ELECTRICITY PRODUCTION

2000 2005 2010 2015 2018 Annual av. growth rate 2000–2018 (%)
Electricity production (TW·h)
Nuclear 108.96 146.78 148.59 164.76 133.51 1.34
Hydro 5.61 5.19 6.74 5.79 7.27 2.69
Geothermal
Wind 0.81 1.34 2.53 16.08
Solar 1.07 3.48 7.70 38.49
Natural Gas 28.49 58.25 96.19 100.75 152.87 10.88
Coal/Lignite/Peat 99.43 134.89 198.29 207.33 241.81 5.15
Oil 19.18 16.11 11.71 9.54 7.12 -0.29
Bioenergy and Waste 2.41 10.29 13.25 27.13
Other 4.73 3.42 157.70 207.00 138.10 18.09
Total* 266.40 364.64 474.92 545.52 570.65 4.35

TABLE 4. ENERGY RELATED RATIOS

2000 2005 2010 2015 2018
Nuclear/total electricity (%) 40.90 40.25 31.14 31.20 23.40

TABLE 5: STATUS AND PERFORMANCE OF NUCLEAR POWER PLANTS AS OF 31 DECEMBER 2019

Reactor Unit Type Net
Capacity
[MW(e)]
Status Operator Reactor
Supplier
Construction
Date
First
Criticality
Date
First Grid
Date
Commercial
Date
Shutdown
Date
UCF
for
2019
HANBIT-1 PWR 995 Operational KHNP WH 1981-06-04 1986-01-31 1986-03-05 1986-08-25 16.6
HANBIT-2 PWR 988 Operational KHNP WH 1981-12-01 1986-10-15 1986-11-11 1987-06-10 87.1
HANBIT-3 PWR 986 Operational KHNP DHICKAEC 1989-12-23 1994-10-13 1994-10-30 1995-03-31 0.0
HANBIT-4 PWR 970 Operational KHNP DHICKAEC 1990-05-26 1995-07-07 1995-07-18 1996-01-01 0.0
HANBIT-5 PWR 992 Operational KHNP DHICKOPC 1997-06-29 2001-11-24 2001-12-19 2002-05-21 99.3
HANBIT-6 PWR 993 Operational KHNP DHICKOPC 1997-11-20 2002-09-01 2002-09-16 2002-12-24 73.0
HANUL-1 PWR 966 Operational KHNP FRAM 1983-01-26 1988-02-25 1988-04-07 1988-09-10 83.3
HANUL-2 PWR 967 Operational KHNP FRAM 1983-07-05 1989-02-25 1989-04-14 1989-09-30 78.4
HANUL-3 PWR 997 Operational KHNP DHICKOPC 1993-07-21 1997-12-21 1998-01-06 1998-08-11 75.8
HANUL-4 PWR 999 Operational KHNP DHICKOPC 1993-11-01 1998-12-14 1998-12-28 1999-12-31 95.5
HANUL-5 PWR 998 Operational KHNP DHICKOPC 1999-10-01 2003-11-28 2003-12-18 2004-07-29 74.5
HANUL-6 PWR 997 Operational KHNP DHICKOPC 2000-09-29 2004-12-16 2005-01-07 2005-04-22 77.2
KORI-2 PWR 640 Operational KHNP WH 1977-12-23 1983-04-09 1983-04-22 1983-07-25 100.0
KORI-3 PWR 1011 Operational KHNP WH 1979-10-01 1985-01-01 1985-01-22 1985-09-30 67.9
KORI-4 PWR 1012 Operational KHNP WH 1980-04-01 1985-10-26 1985-12-31 1986-04-29 51.0
SHIN-KORI-1 PWR 996 Operational KHNP DHICKOPC 2006-06-16 2010-07-15 2010-08-04 2011-02-28 74.7
SHIN-KORI-2 PWR 996 Operational KHNP DHICKOPC 2007-06-05 2011-12-27 2012-01-28 2012-07-20 79.2
SHIN-KORI-3 PWR 1416 Operational KHNP DHICKOPC 2008-10-16 2015-12-29 2016-01-15 2016-12-20 88.4
SHIN-KORI-4 PWR 1418 Operational KHNP DHICKOPC 2009-08-19 2019-04-08 2019-04-22 2019-08-29 100.0
SHIN-WOLSONG-1 PWR 997 Operational KHNP DHICKOPC 2007-11-20 2012-01-06 2012-01-27 2012-07-31 85.1
SHIN-WOLSONG-2 PWR 993 Operational KHNP DHICKOPC 2008-09-23 2015-02-08 2015-02-26 2015-07-24 74.9
WOLSONG-2 PHWR 606 Operational KHNP AECL/DHI 1992-09-25 1997-01-29 1997-04-01 1997-07-01 90.3
WOLSONG-3 PHWR 630 Operational KHNP AECL/DHI 1994-03-17 1998-02-19 1998-03-25 1998-07-01 59.1
WOLSONG-4 PHWR 609 Operational KHNP AECL/DHI 1994-07-22 1999-04-10 1999-05-21 1999-10-01 83.3
SHIN-HANUL-1 PWR 1340 Under Construction KHNP DHICKOPC 2012-07-10
SHIN-HANUL-2 PWR 1340 Under Construction KHNP DHICKOPC 2013-06-19
SHIN-KORI-5 PWR 1340 Under Construction KHNP DHICKOPC 2017-04-01
SHIN-KORI-6 PWR 1340 Under Construction KHNP DHICKOPC 2018-09-20
KORI-1 PWR 576 Permanent Shutdown KHNP WH 1972-08-01 1977-06-19 1977-06-26 1978-04-29 2017-06-18
WOLSONG-1 PHWR 661 Permanent Shutdown KHNP AECL 1977-10-30 1982-11-21 1982-12-31 1983-04-22 2019-12-24 0.0
Data source: IAEA - Power Reactor Information System (PRIS).
Note: Table is completely generated from PRIS data to reflect the latest available information and may be more up to date than the text of the report.

TABLE 6. STATUS OF DECOMMISIONING PROCESS OF NUCLEAR POWER PLANT

Reactor unit Shutdown date Shutdown reason Decom. strategy Decom. phase Management phase Decom. licensee
Kori-1 18-June-2017 Termination of continued operation Dismantling Planning Wet Storage on-site KHNP
Wolsong-1 24-Dec-2019 Economic Dismantling Planning Wet & Dry Storage on-site KHNP

TABLE 7. UNDER CONSTRUCTION NUCLEAR POWER PLANTS

Station/project name Type Capacity (MW) Construction start year Expected commercial year
Shin Hanul-1 PWR 1400 2012 2020
Shin Hanul-2 PWR 1400 2013 2021
Shin Kori-5 PWR 1400 2017 2023
Shin Kori-6 PWR 1400 2018 2024